First Notice | | 4/3/2015 | 4/27/2015 | | DONE |
|
|
|
This permit finaled on the web by Todd Kurns
|
First Notice | | 4/3/2015 | 4/27/2015 | | DONE |
|
|
|
This permit finaled on the web by Todd Kurns
|
Permanent Occupancy | | | 3/24/2015 | | DONE |
|
|
|
|
BLD-Final | 2/13/2015 | 2/13/2015 | 2/13/2015 | P | PASS |
Phil Shearer
|
|
|
Tod Phone #: ###-####
|
FIRE-Final Inspection | 2/13/2015 | 2/13/2015 | 2/13/2015 | P | PASS |
Troy Cobbley
|
|
|
life safety passed. Acid detection not required per plan review.
|
Plan Reviewer's activity | | | 2/13/2015 | | DONE |
|
|
|
Review the comment for leak detection. Do to the small dilouted amount it is not an issue in this case. The comment is therfore voided.
|
Temporary Occupancy | 2/9/2015 | 5/10/2015 | 2/9/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (CJW) | 1/30/2015 | | 2/9/2015 | | DONE |
Carl Westfall
|
|
|
Wings Center - Pool TI - Plan mod
|
Routing - PLAN CHECK | 1/30/2015 | | 2/9/2015 | | PASS |
Carl Westfall
|
|
|
Nothing for Building to review
|
Routing - FIRE | 2/9/2015 | | 2/9/2015 | | PASS |
Carl Westfall
|
|
|
Issues were resolved with small documents. A revised sheet having a revised note was submitted but such revised sheet was not needed. The sheet was discarded.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/9/2015 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/9/2015 | | DONE |
Candy A. Nichols
|
|
|
as per Carl Westfall-no plan mod needed, no new valuation. changing permit back to temp CO
|
Temporary Occupancy | 1/30/2015 | 4/30/2015 | 1/30/2015 | | DONE |
Kristal Soland
|
|
|
|
Plan Modification Accepted | | | 1/30/2015 | | DONE |
Candy A. Nichols
|
|
|
received Plan Mod-1permit app and 2 sheets of A2.1-took to Carl Westfall
|
BLD-Final | 1/8/2015 | 1/9/2015 | 1/9/2015 | A | PART |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Kurns
|
FIRE-Final Inspection | 1/8/2015 | 1/9/2015 | 1/9/2015 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given with scott's permission until the acid detection requirement is satisfied.
|
FIRE-Alarm Testing | 1/8/2015 | 1/9/2015 | 1/9/2015 | A | CANC |
Troy Cobbley
|
|
|
Waiting for installation of duct smoke detector
|
Telephone call | | | 1/8/2015 | | DONE |
Scott Arellano
|
|
|
Spoke with Todd (the GC). Informed Todd that if all related trade permits have been finaled to go ahead and call in the BLD life safety inspection. A Temporary Certificate of Occupancy (TCO) can be authorized while the pool equipment room leak detection system is completed. All other life safety items must also be completed prior to occupancy of the pool area.
|
BLD-Ceiling Grid Inspection | 11/19/2014 | 11/19/2014 | 11/19/2014 | A | PASS |
Phil Shearer
|
|
|
Please call when on way. Thx todd Phone #: ###-#### Inspection requested via web by Todd Kurns
|
BLD-Energy code compliance | 9/26/2014 | 9/26/2014 | 9/26/2014 | A | PASS |
Phil Shearer
|
|
|
|
BLD-Wall cover | 9/25/2014 | 9/26/2014 | 9/26/2014 | A | CANC |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Kurns
|
BLD-Framing/Rough-in | 9/4/2014 | 9/4/2014 | 9/4/2014 | P | NR |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Kurns
|
BLD-Framing/Rough-in | 8/13/2014 | 8/13/2014 | 8/13/2014 | A | PART |
Phil Shearer
|
|
|
Please call me when on your way. Thanks todd Phone #: ###-#### Inspection requested via web by Todd Kurns Exterior wall grid lines A and 5
|
Issue PAID IN FULL permit | | | 7/29/2014 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 7/25/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 7/25/2014 | | DONE |
Candy A. Nichols
|
|
|
calledWard-let know permit is ready and how much is owed-left message on his phone
|
Plan assigned to (CJW) | 5/12/2014 | 5/12/2014 | 7/24/2014 | | PASS |
Carl Westfall
|
|
|
WINGS POOL TI - Level 3 TI - paper plans - (15 days - May 28)
|
Plan resubmittals received | | | 7/24/2014 | | DONE |
Tisha Gallop
|
|
|
received three copies of plan sheet A2.1; taken to Carl Westfall.
|
Routing - FIRE | 7/24/2014 | | 7/24/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 2 07-24-14
|
Routing - PLAN CHECK | 7/24/2014 | | 7/24/2014 | | DONE |
Carl Westfall
|
|
|
Routing completed
|
Routing - PLAN CHECK | 7/10/2014 | | 7/24/2014 | | DONE |
Carl Westfall
|
|
|
Waiting for resubmittals
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2014 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/24/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - FIRE | 7/8/2014 | | 7/10/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 07-10-14
|
Routing - PLAN CHECK | 7/7/2014 | | 7/8/2014 | | PASS |
Carl Westfall
|
|
|
Drawings approved with "red lines".
|
Plan resubmittals received | | | 7/7/2014 | | DONE |
Tisha Gallop
|
|
|
received two copies of plan sheets A2.2, A2.1; taken to Carl Westfall.
|
Routing - PLAN CHECK | 6/2/2014 | | 7/1/2014 | | FAIL |
Carl Westfall
|
|
|
Remaining resubmittals were received on June 27. Resubmittal review started on July 1. The 2nd review failed. Revised drawings were required.
|
Plan resubmittals requested | | | 7/1/2014 | | DONE |
|
|
|
Email sent to Ward asking him for revised drawings.
|
Plan resubmittals received | | | 6/27/2014 | | DONE |
|
|
|
rec'd two copies of sheet E-2 and M-1; taken to carl westfall
|
Route to Impact Fee Review | 6/19/2014 | 6/22/2014 | 6/20/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals received | | | 6/12/2014 | | DONE |
Candy A. Nichols
|
|
|
Architect brought in 2 sheets of A2.1 & 2 sheets of A2.2. Took to Carl Westfall
|
Routing - FIRE | 5/29/2014 | | 6/2/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-02-14
|
1st review completed | | | 6/2/2014 | | FAIL |
|
|
|
Failed: Plan Check, Fire
|
Routing - PLAN CHECK | 5/15/2014 | | 5/29/2014 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required. Called Ward and left a voice mail discussing what is required. Also Emailed him a copy of the plan review report in both Word and PDF.
|
Routing - Design Review | 5/14/2014 | | 5/15/2014 | | PASS |
Josh Wilson
|
|
|
Josh Wilsion - DRH14-00056
|
Routing - PLUMBING | 5/13/2014 | | 5/14/2014 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing PW Sewer Rating | 5/13/2014 | | 5/13/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 5/12/2014 | | 5/13/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 5/12/2014 | | 5/12/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Pending Assignment by JCB | 5/8/2014 | | 5/12/2014 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/8/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 5/8/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/8/2014 | | DONE |
Christina Prado
|
|
|
|
Application received | | 5/8/2014 | | | |
|
|
|
|