First Notice | | 9/29/2014 | 7/2/2015 | | DONE |
|
|
|
This permit finaled on the web by Jeremy Amar
|
BLD-Final | 9/18/2014 | 9/19/2014 | 9/19/2014 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
Zoning Approval | 9/19/2014 | 9/19/2014 | 9/19/2014 | | PASS |
Josh Wilson
|
|
|
|
Permanent Occupancy | | | 9/19/2014 | | DONE |
Candy A. Nichols
|
|
|
|
FIRE-Final Inspection | 9/17/2014 | 9/17/2014 | 9/17/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 9/16/2014 | 9/16/2014 | 9/16/2014 | P | CANC |
Troy Cobbley
|
|
|
The project related fire alarm and fire sprinkler permits need addressed.
|
FIRE-Final Inspection | 9/15/2014 | 9/15/2014 | 9/15/2014 | P | NR |
Forrest France
|
|
|
Project related fire alarm and sprinkler permit finals pending.
|
BLD-Other | 8/13/2014 | 8/13/2014 | 8/13/2014 | P | PASS |
Mike Jordan
|
|
|
pat Phone #: ###-####
|
BLD-Energy code compliance | 8/8/2014 | 8/8/2014 | 8/8/2014 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Energy code compliance | 8/7/2014 | 8/8/2014 | 8/8/2014 | A | CANC |
Mike Jordan
|
|
|
Pat Phone #: ###-####. cancelled per phone call from contractor.
|
BLD-Framing/Rough-in | 8/6/2014 | 8/6/2014 | 8/6/2014 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 8/1/2014 | 8/4/2014 | 8/4/2014 | P | NR |
Jim Storey
|
|
|
Pat Phone #: ###-#### pending trade aprovals
|
BLD-Wall Bracing | 8/1/2014 | 8/4/2014 | 8/4/2014 | A | PASS |
Phil Shearer
|
|
|
Pat Phone #: ###-####
|
BLD-Foundation | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PASS |
Tom Arcoraci
|
|
|
John Phone #: ###-####
|
BLD-Footing | 6/23/2014 | 6/24/2014 | 6/24/2014 | A | PASS |
Tom Arcoraci
|
|
|
john Phone #: ###-####
|
OVERRIDE | | | 6/19/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/19/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 6/19/2014 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/19/2014 | | DONE |
Sam Zahorka
|
|
|
|
Permit Ready to Issue | | | 6/19/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (SRZ) | 5/14/2014 | | 6/19/2014 | | PASS |
Sam Zahorka
|
|
|
Pending Plumbing and Mechanical to PASS.
|
Routing - MECHANICAL | 6/16/2014 | | 6/17/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 6/16/2014 | | 6/17/2014 | | PASS |
Daryl Spivey
|
|
|
per plans and ISPC
|
Routing - PLANNING | 5/14/2014 | | 6/9/2014 | | PASS |
Joshua Johnson
|
|
|
|
Routing - PLANNING Land Div | 5/14/2014 | | 6/9/2014 | | PASS |
Todd Tucker
|
|
|
|
Routing - PLAN CHECK | 5/14/2014 | | 6/9/2014 | | PEND |
Sam Zahorka
|
|
|
Pending Plumbing and Mechanical to PASS.
|
Routing PW Drainage | 5/14/2014 | | 6/9/2014 | | CANC |
Brian Murphy
|
|
|
|
1st review completed | | | 6/9/2014 | | DONE |
Sam Zahorka
|
|
|
Pending Plumbing and Mechanical to PASS.
|
Routing - MECHANICAL | 5/14/2014 | | 5/23/2014 | | FAIL |
Troy James
|
|
|
need fresh air design on plans
|
Routing - FIRE | 5/14/2014 | 5/14/2014 | 5/21/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 05-21-14
|
Routing - Design Review | 5/14/2014 | | 5/16/2014 | | PASS |
Josh Wilson
|
|
|
|
Route to Impact Fee Review | 5/14/2014 | | 5/15/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLUMBING | 5/14/2014 | | 5/15/2014 | | FAIL |
Daryl Spivey
|
|
|
move water services into easement
|
Routing PW Sewer Rating | 5/14/2014 | | 5/14/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 5/14/2014 | | PASS |
John Menard
|
|
|
|
Pending Assignment by JCM | 5/14/2014 | | 5/14/2014 | | DONE |
John Menard
|
|
|
|
Routing - Addressing | 5/14/2014 | | 5/14/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 5/14/2014 | | 5/14/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 5/14/2014 | | 5/14/2014 | | PASS |
Evan Jenkins
|
|
|
Contractor to Update Site Maps showing where each indivisual building will be placed
|
Application received | | | 5/9/2014 | | DONE |
|
|
|
Application submitted via PDS Online on May 9 2014 7:23PM
|