Description
(Boise Towne Square Mall - Pavement Rehab 2014) Grading permit to remove approximately 16,905 square yards existing asphalt recompact the base material and repave in two separate areas at the Boise Towne Square Mall parking lot. Drainage is to be installed as approved by the Public Works Department. Striping and signage will be done as approved under CZC14-00136. No construction is allowed under this permit. **leg
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 9/5/20149/12/2014 DONE
DetailsChristina Prado
completed 9-12-14
First Notice7/22/20147/22/20148/26/2014 DONE
DetailsMike Jordan
BLD-Final7/21/20147/22/20147/22/2014ADONE
DetailsMike Jordan
Jesse Phone #: ###-####
DOC - Permit Finaled7/22/20147/22/20147/22/2014PPASS
DetailsMike Jordan
FIRE-Final Inspection7/21/20147/21/20147/21/2014PPASS
DetailsTroy Cobbley
Life safety passed
Issue PAID IN FULL permit  5/27/2014 DONE
DetailsTisha Gallop
OVERRIDE  5/21/2014  
Telephone call  5/21/2014 DONE
DetailsTisha Gallop
called Jesse Geary and left mssg permit is ready and fee due.
Routing - FIRE5/20/2014 5/21/2014 PASS
DetailsCraig D. Hanson
No Report
Inspection Record Card- Bld  5/21/2014 DONE
DetailsTisha Gallop
PLANS/APPL TAKEN TO FRONT DESK  5/21/2014 DONE
DetailsTisha Gallop
1st review completed  5/21/2014 DONE
DetailsTisha Gallop
Permit Ready to Issue  5/21/2014 DONE
DetailsTisha Gallop
Plan assigned to (LEG) Tisha5/12/2014 5/21/2014 DONE
DetailsTisha Gallop
office copy taken to Records
Routing - PLAN CHECK  5/21/2014 PASS
DetailsTisha Gallop
Tisha Gallop
Routing - PLANNING5/20/2014 5/20/2014 PASS
DetailsJosh Wilson
OK per CZC14-00136
Routing - Erosion and Sediment5/19/2014 5/20/2014 PASS
DetailsAndy J. Long
ESC site map and narrative approved. Valid PD and RP designated. Site prep inspection/pre-con meeting required.
Routing PW Drainage5/14/2014 5/19/2014 PASS
DetailsBrian Murphy
Routing - PUBLIC WORKS5/13/2014 5/14/2014 PASS
DetailsJason C. Taylor
Routing - PLANNING Land Div5/13/2014 5/13/2014 PASS
DetailsDave Abo
Parcel over 5 acres in size.
Case Summary (BLD)  5/13/2014 DONE
Application received 5/12/20145/12/2014 DONE
Plans ACCEPTED BY PLAN TECH  5/12/2014 DONE