First Notice | | 10/16/2014 | 11/10/2014 | | DONE |
Christina Prado
|
|
|
|
Permanent Occupancy | | | 10/6/2014 | | DONE |
|
|
|
|
BLD-Final | 9/25/2014 | 9/25/2014 | 9/25/2014 | P | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-#### sink was removed no ada issues
|
BLD-Final | 9/12/2014 | 9/12/2014 | 9/16/2014 | P | PART |
Dave Hannah
|
|
|
Derrick Phone #: ###-#### ok for temp occ
|
FIRE-Final Inspection | 9/10/2014 | 9/10/2014 | 9/10/2014 | P | PASS |
Forrest France
|
|
|
Life safety inspection completed satisfactory.
|
BLD-Ceiling Grid Inspection | 8/15/2014 | 8/15/2014 | 8/18/2014 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Concrete | 8/15/2014 | 8/15/2014 | 8/15/2014 | P | CANC |
Dave Hannah
|
|
|
Dereck Phone #: ###-####
|
BLD-Framing/Rough-in | 7/21/2014 | 7/21/2014 | 7/21/2014 | P | PART |
Jim Storey
|
|
|
Derrick Phone #: ###-#### fire blk ceilling line of hvac #2 restarm. ok to cover
|
OVERRIDE | | | 6/27/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/27/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/27/2014 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 6/26/2014 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/25/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 6/25/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 6/2/2014 | | 6/25/2014 | | PASS |
Tim L. Woodard
|
|
|
Level 3 TI - paper - Spark MD (reassigned)
|
Routing - PLAN CHECK | 6/11/2014 | | 6/25/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Route to Impact Fee Review | 6/19/2014 | 6/22/2014 | 6/20/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals received | | | 6/20/2014 | | |
|
|
|
Received 2 copies of sheets CS, A2, A5, A6, Letter from Larry Knopp dated 6/18/14, Letter from Dr Gunther dated 6/16/14, Occupancy Calculation, 1 set of 81/2 x 14 of CS, A2, A5, A6 inserted into plans by architecs office then taken back to TIm's office
|
1st review completed | | | 6/11/2014 | | FAIL |
|
|
|
Failed: Plan Check
|
Routing - PLAN CHECK | 6/2/2014 | | 6/11/2014 | | FAIL |
Tim L. Woodard
|
|
|
Refer to attached "Plan Review Report". TLW
|
Routing - FIRE | 6/11/2014 | | 6/11/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-11-14
|
Plan assigned to (AJS) | 5/16/2014 | 5/16/2014 | 6/2/2014 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
Due 6/12 Level 3 TI - Spark MD - Project reassigned to Tim Woodard
|
Routing - Design Review | 6/2/2014 | | 6/2/2014 | | PASS |
Sarah Schafer
|
|
|
Exterior ramp and door. Approved through the building permit plans.
|
Routing - PLUMBING | 5/23/2014 | | 5/27/2014 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - Erosion and Sediment | 5/20/2014 | | 5/23/2014 | | PASS |
Evan Jenkins
|
|
|
|
Routing - PUBLIC WORKS | 5/20/2014 | | 5/21/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 5/20/2014 | | 5/20/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Drainage | 5/20/2014 | | 5/20/2014 | | PASS |
Brian Murphy
|
|
|
|
Routing - Addressing | 5/16/2014 | | 5/20/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Intake Approval | | | 5/16/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Pending Assignment by JCB | 5/12/2014 | | 5/16/2014 | | DONE |
Jason Blais
|
|
|
|
Plan resubmittals received | | | 5/16/2014 | | DONE |
Christina Prado
|
|
|
Received letter addressed to planning & zoning dept regarding front door re-use;taken to plan review to attached to building plans
|
Application received | | 5/12/2014 | 5/12/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/12/2014 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/12/2014 | | DONE |
Barbara Stitt
|
|
|
|