Print Occupancy Form | | | 9/30/2019 | | DONE |
|
|
|
|
BLD-Final | 3/25/2015 | 3/26/2015 | 3/26/2015 | A | PASS |
Jim Storey
|
|
|
Don Phone #: ###-#### no card on site final ok
|
FIRE-Final Inspection | 3/24/2015 | 3/25/2015 | 3/25/2015 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed okay at the new addition per scope of work.
|
FIRE-Final Inspection | 3/17/2015 | 3/17/2015 | 3/19/2015 | P | PEND |
Forrest France
|
|
|
Final pending project related fire sprinkler permit work.
|
CHANGE STATUS TO (ISS) | | | 3/17/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 2/6/2015 | | |
|
|
|
|
Routing - PLAN CHECK | 2/5/2015 | | 2/6/2015 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/6/2015 | | DONE |
John Menard
|
|
|
|
Permit Ready to Issue | | | 2/6/2015 | | DONE |
|
|
|
Revised Value
|
Plan assigned to (JCM) | 2/2/2015 | | 2/6/2015 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 2/2/2015 | | 2/4/2015 | | PASS |
Scott Arellano
|
|
|
No change in review comments. Attached revised report to case.
|
Routing - PLAN CHECK | 2/2/2015 | | 2/3/2015 | | FAIL |
John Menard
|
|
|
Plan Modification
|
BLD-Framing/Rough-in | 1/30/2015 | 2/2/2015 | 2/2/2015 | A | PASS |
Jim Storey
|
|
|
Don Phone #: ###-####
|
Plan Modification Accepted | | | 1/30/2015 | | DONE |
Christina Prado
|
|
|
Plan Mod requested by Shawn Reeder for COMcheck updates
|
BLD-Foundation | 10/23/2014 | 10/24/2014 | 10/24/2014 | P | PASS |
Jim Storey
|
|
|
reqeust around 1 // stem wall // Don Phone #: ###-####
|
BLD-Footing | 10/16/2014 | 10/16/2014 | 10/16/2014 | P | PASS |
Jim Storey
|
|
|
Don Phone #: ###-####
|
OVERRIDE | | | 9/30/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/30/2014 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 9/30/2014 | | DONE |
Tisha Gallop
|
|
|
Per phone call from Christi Little at ACHD, the original documentation/letter that these plans were reviewed by them was misplaced. There is no impact fees for this project and no inspection requried.
|
Permit Ready to Issue | | | 9/30/2014 | | DONE |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2014 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 7/2/2014 | | 9/27/2014 | | PASS |
John Menard
|
|
|
1st Review Complete 7/16/2014 - Rocky Mtn Packaging
|
Routing - PLAN CHECK | 9/24/2014 | | 9/26/2014 | | PASS |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 9/24/2014 | | 9/26/2014 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 9/15/2014 | | 9/23/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 09-23-14
|
Routing - PLAN CHECK | 9/15/2014 | | 9/22/2014 | | FAIL |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 9/15/2014 | | 9/19/2014 | | FAIL |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 8/23/2014 | | 9/8/2014 | | FAIL |
John Menard
|
|
|
|
Telephone call | | | 9/2/2014 | | DONE |
Scott Arellano
|
|
|
Spoke with Sean Reeder. Informed Sean of the necessity of an approved cross access agreement with the property owner on the east parcel where two existing fire hydrants are located. Qualifying this roadway access and use of the two existing fire hydrants on that parcel hinges on the cross access agreement document. Additionally, we discussed the proximity of the existing Fire Department Connection relative to the nearest available fire hydrant and what the code requires on that resubmittal item. A revised site plan addressing and indicating the aforementioned resubmittal items is necessary, prior to approval.
|
Routing - PLAN CHECK | 8/7/2014 | | 8/23/2014 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 8/7/2014 | | 8/18/2014 | | FAIL |
Scott Arellano
|
|
|
See attached Fire Code plan review report. Resubmittal items also indicated within the electronic case.
|
Routing PW Drainage | 8/7/2014 | | 8/11/2014 | | PASS |
Brian Murphy
|
|
|
|
1st review completed | | | 7/17/2014 | | FAIL |
John Menard
|
|
|
|
Routing PW Solid Waste | 7/2/2014 | | 7/17/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - PLAN CHECK | 7/2/2014 | | 7/17/2014 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 7/2/2014 | 7/2/2014 | 7/10/2014 | | FAIL |
Craig D. Hanson
|
|
|
No report. More information being requested by building, will do review when recieved.
|
Routing PW Drainage | 7/2/2014 | | 7/7/2014 | | FAIL |
Brian Murphy
|
|
|
needs 2 more civil sheets grading
|
Route to Impact Fee Review | 7/2/2014 | | 7/3/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Intake Approval | | | 7/2/2014 | | PASS |
John Menard
|
|
|
|
Intake Approval | | | 7/2/2014 | | PASS |
John Menard
|
|
|
|
Routing - PLANNING Land Div | 7/2/2014 | | 7/2/2014 | | PASS |
Dave Abo
|
|
|
Parcel A of ROS 9510
|
Routing - PUBLIC WORKS | 7/2/2014 | | 7/2/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 7/2/2014 | | 7/2/2014 | | PASS |
Evan Jenkins
|
|
|
Steel Building Shell to attached 2 Existing Steel Buildings
|
Routing - Design Review | 7/2/2014 | | 7/2/2014 | | PASS |
Josh Wilson
|
|
|
|
Pending Assignment by JCM | 7/2/2014 | | 7/2/2014 | | DONE |
John Menard
|
|
|
|
Intake Approval | | | 6/20/2014 | | FAIL |
Sam Zahorka
|
|
|
Please provide the following information:
The Metal Building drawings and calculations stamped and signed by a licensed engineer.
An Electrical Lighting Plan with switching.
It appears the means of egress from the new building addition will require the occupants to travel through the existing buildings. If so, please provide floor plans showing the means of egress paths through the existing buildings to the public way.
If assistance is needed please call me directly at ###-####.
Thanks.
Sam Zahorka
|
Application received | | | 5/14/2014 | | DONE |
|
|
|
Application submitted via PDS Online on May 14 2014 9:21AM
|