Second Notice | | 1/12/2015 | 2/2/2015 | | DONE |
|
|
|
|
First Notice | | 1/2/2015 | 1/2/2015 | | DONE |
|
|
|
|
BLD-Final | 12/23/2014 | 12/23/2014 | 12/23/2014 | P | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
Permanent Occupancy | | | 12/23/2014 | | DONE |
|
|
|
|
BLD-Final | 12/16/2014 | 12/16/2014 | 12/17/2014 | P | PART |
Dave Hannah
|
|
|
Chris Phone #: ###-#### ok for temp occ needs to change out side light by door and ada signage at restrom doors
|
FIRE-Final Inspection | 12/15/2014 | 12/16/2014 | 12/16/2014 | A | PASS |
Forrest France
|
|
|
Noted correction items verified for completion. Fire life safety finaled.
|
BLD-Final | 12/15/2014 | 12/16/2014 | 12/16/2014 | A | CANC |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Final | 11/17/2014 | 11/18/2014 | 11/19/2014 | P | NR |
Dave Hannah
|
|
|
DUAL Phone #: ###-####
|
FIRE-Final Inspection | 11/17/2014 | 11/18/2014 | 11/18/2014 | P | FAIL |
Forrest France
|
|
|
Items noted include; adjust door closure and provide seal at main entry/exit, post PFE, maintain access to required second exit- missing exit signage at passageway. Provide stamped plans and review notes at next inspection.
|
BLD-Framing/Rough-in | 8/18/2014 | 8/20/2014 | 8/21/2014 | A | PASS |
Dave Hannah
|
|
|
Duel Phone #: ###-####
|
Permit Ready to Issue | | | 7/1/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 7/1/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 7/1/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 5/15/2014 | 5/15/2014 | 6/6/2014 | | PASS |
Carl Westfall
|
|
|
OWYHEE PLACE FITNESS CENTER - Level 3 TI - ePlanReview - (15 days - June 4)
|
Routing - FIRE | 6/4/2014 | | 6/6/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 06-06-14
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2014 | | DONE |
|
|
|
|
Routing PW Sewer Rating | 6/4/2014 | | 6/4/2014 | | PASS |
Connie Baumgartner
|
|
|
Drinking fountains added
|
Routing - PLAN CHECK | 6/3/2014 | | 6/4/2014 | | PASS |
Carl Westfall
|
|
|
Drawings approved after the 2nd review
|
Plan resubmittals received | | | 6/3/2014 | | DONE |
|
|
|
|
Routing - FIRE | 5/15/2014 | 5/15/2014 | 6/2/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-02-14
|
1st review completed | | | 6/2/2014 | | DONE |
|
|
|
Failed fire and plan check
|
Plan resubmittals requested | | | 6/2/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/15/2014 | | 5/30/2014 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Plan Reviewer's activity | | | 5/23/2014 | | DONE |
Jason Blais
|
|
|
No ACHD impact fee and no inspection required per email from Christy Little.
|
Routing - PLUMBING | 5/15/2014 | | 5/16/2014 | | PASS |
Bill VanDegrift
|
|
|
per pland and ISPC
|
Routing - Addressing | 5/15/2014 | | 5/16/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing PW Sewer Rating | 5/15/2014 | | 5/16/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | | 5/15/2014 | | DONE |
|
|
|
Application submitted via PDS Online on May 15 2014 7:33AM
|
Intake Approval | | | 5/15/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin and plan review fees paid.
|
Pending Assignment by JCB | 5/15/2014 | | 5/15/2014 | | DONE |
Jason Blais
|
|
|
|
Routing - PUBLIC WORKS | 5/15/2014 | | 5/15/2014 | | PASS |
Beverly Mountain
|
|
|
|