BLD-Final | 4/15/2015 | 4/15/2015 | 4/15/2015 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Matthew Evans,,, hill side ok per Jason Taylor via e-mail
|
DOC - Permit Finaled | 4/15/2015 | 4/15/2015 | 4/15/2015 | P | PASS |
Tony Young
|
|
|
c pof c issued
|
BLD-Final | 4/7/2015 | 4/8/2015 | 4/8/2015 | A | FAIL |
Tony Young
|
|
|
Please call Matthew before inspection. I will meet you there. Phone #: ###-#### Inspection requested via web by Matthew Evans,, c/n posted,, need hillside,, fireplace permit etc
|
BLD-Final | 3/10/2015 | 3/10/2015 | 3/10/2015 | P | NR |
Tony Young
|
|
|
Matthew Phone #: ###-####,, need address #s,, need fire seperation between the house and garage,, steps out of the doors,, finish the exterior for protection of the elements.. etc
|
Fees Due Hold | 11/14/2014 | | 3/10/2015 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 11/14/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 11/12/2014 | | DONE |
|
|
|
Restoration Pro called and said taking over job from Cafco. Told him need to have owner send letter or e-mail stating Cafco no longer on job, he is new GC. The transfer fee is $46.31 and need GC form from Restoration Pro. Told him we could print out plans for on site.
|
BLD-Energy code compliance | 11/3/2014 | 11/3/2014 | 11/3/2014 | P | PART |
Tony Young
|
|
|
Bill Phone #: ###-####,, ok to insulate the garage front for the garage door only
|
BLD-Conference | 9/23/2014 | 9/24/2014 | 9/24/2014 | A | PEND |
Tony Young
|
|
|
status review,, need mechanical,, work in progress,, Bill will call in for cover after mech signs off
|
BLD-Wall cover | 9/3/2014 | 9/4/2014 | 9/4/2014 | A | PEND |
Tony Young
|
|
|
Bill; Phone #: ###-####,, need mech pass
|
BLD-Wall cover | 9/2/2014 | 9/3/2014 | 9/3/2014 | A | PEND |
Tony Young
|
|
|
Bill; Phone #: ###-####
|
BLD-Wall cover | 9/2/2014 | 9/3/2014 | 9/2/2014 | A | CANC |
Tony Young
|
|
|
|
BLD-Wall cover | 9/2/2014 | 9/2/2014 | 9/2/2014 | A | NR |
Tony Young
|
|
|
need mechanical 1st
|
BLD-Conference | 8/29/2014 | 8/29/2014 | 8/29/2014 | P | NR |
Tony Young
|
|
|
Bill; Phone #: ###-####
|
BLD-Conference | 8/27/2014 | 8/28/2014 | 8/28/2014 | A | PART |
Tony Young
|
|
|
Bill Phone #: ###-####,, status review,, still need mechanical pass,, ok to cover various walls noted in walk through
|
BLD-Conference | 8/26/2014 | 8/27/2014 | 8/27/2014 | P | PEND |
Tony Young
|
|
|
Bill Phone #: ###-####,, status review,, needs mechanical pass
|
BLD-Conference | 8/25/2014 | 8/26/2014 | 8/26/2014 | A | PART |
Tony Young
|
|
|
Bill Phone #: ###-####,, some ceilings ok to cover
|
BLD-Conference | 8/25/2014 | 8/25/2014 | 8/25/2014 | P | PART |
Tony Young
|
|
|
Bill Phone #: ###-####,, see prior notes
|
BLD-Conference | 8/21/2014 | 8/25/2014 | 8/25/2014 | A | PART |
Tony Young
|
|
|
Bill Phone #: ###-####,, status review,, need reinspection on mech,, piece meal areas of insulation and cover,, vent holes drilled for attic vent in blocking,, need approval for soffit fire rating if other than plan,, can one side interior walls with dry wall
|
BLD-Framing/Rough-in | 8/20/2014 | 8/21/2014 | 8/21/2014 | A | FAIL |
Tony Young
|
|
|
Bill Phone #: ###-####,, needs mech and plumbing issues taken care of,, ok to insulate non related areas
|
BLD-Framing/Rough-in | 8/20/2014 | 8/20/2014 | 8/20/2014 | P | NR |
Tony Young
|
|
|
Bill Phone #: ###-####
|
BLD-Framing/Rough-in | 8/19/2014 | 8/20/2014 | 8/20/2014 | A | NR |
Tony Young
|
|
|
Bill Phone #: ###-####
|
BLD-Framing/Rough-in | 8/19/2014 | 8/19/2014 | 8/19/2014 | P | NR |
Tony Young
|
|
|
Bill Phone #: ###-####,, walk through only
|
Plan Modification Accepted | | | 8/15/2014 | | DONE |
|
|
|
revised manual j report
|
Routing - MECHANICAL | 8/15/2014 | | 8/15/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
Routing - MECHANICAL | 8/12/2014 | | 8/12/2014 | | PASS |
Troy James
|
|
|
new manual j report reviewed
|
BLD-Wall Bracing | 7/17/2014 | 7/18/2014 | 7/18/2014 | A | PASS |
Phil Shearer
|
|
|
Bill Phone #: ###-####
|
BLD-Wall Bracing | 7/17/2014 | 7/17/2014 | 7/17/2014 | P | FAIL |
Tony Young
|
|
|
Bill Phone #: ###-####,,re do nail schedule
|
BLD-Footing | 6/18/2014 | 6/19/2014 | 6/19/2014 | A | PART |
Tony Young
|
|
|
Bill Phone #: ###-####,, back ftg
|
BLD-Foundation | 6/11/2014 | 6/12/2014 | 6/12/2014 | A | PART |
Tony Young
|
|
|
Phone #: ###-####,, walls work in progress
|
BLD-Footing | 6/9/2014 | 6/10/2014 | 6/10/2014 | A | PASS |
Tony Young
|
|
|
bill Phone #: ###-####,, back area ok
|
BLD-Footing | 6/6/2014 | 6/9/2014 | 6/9/2014 | A | PART |
Tony Young
|
|
|
Bill- Phone #: ###-####,, garage ftg ok
|
BLD-Footing | 6/6/2014 | 6/6/2014 | 6/7/2014 | P | PART |
Tony Young
|
|
|
Bill; Phone #: ###-####,, garage ftg ok,, need to see plan review to add anything additional
|
Routing Walk-In (BLD) | 6/4/2014 | 6/4/2014 | 6/6/2014 | P | PASS |
Perry Paine
|
|
|
modified the plans to reflect a new stepped foundation. engineerind (sealed0 TO BE PRESENTED TO THE INSPECTOR AT FOOTING INSP.
|
PubWorks Subgrade Approval | 6/2/2014 | 6/2/2014 | 6/2/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Conference | 5/27/2014 | 5/28/2014 | 5/28/2014 | A | NH |
Tony Young
|
|
|
Bill Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/21/2014 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 5/20/2014 | | |
|
|
|
|
Routing Walk-In (Erosion) | 5/20/2014 | 5/20/2014 | 5/20/2014 | P | PASS |
Evan Jenkins
|
|
|
For ESC Plan Waiver Request
Site Prep Inspection Required Prior to Any Earth Disturbance to walk the site to ensure all aspect of ESC Ordiance 8-17 Is Addressed and met. Waiver Request Approved due the small size of addition & minimal earth disturbance.
|
Plan assigned to (PEP) | 5/20/2014 | 5/20/2014 | 5/20/2014 | | PASS |
Perry Paine
|
|
|
|
Routing Walk-In (PW Hillside) | 5/19/2014 | 5/19/2014 | 5/20/2014 | P | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing Walk-In (BLD) | | | 5/20/2014 | | DONE |
|
|
|
|
1st review completed | | | 5/20/2014 | | PASS |
|
|
|
ESC Plan Waiver Request pep Routed to EEJ
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2014 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/20/2014 | | |
|
|
|
|
Telephone call | | | 5/20/2014 | | DONE |
Christina Prado
|
|
|
called Bill to advise permit is ready for pick up and gave fees due
|
Permit Ready to Issue | | | 5/20/2014 | | DONE |
Christina Prado
|
|
|
|
Routing Walk-In (Zoning) | 5/19/2014 | 5/19/2014 | 5/19/2014 | P | PASS |
Colleen T Carroll
|
|
|
|
Application received | | 5/19/2014 | | | |
|
|
|
|