First Notice | | 9/27/2014 | 9/18/2014 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
BLD-Final | 9/17/2014 | 9/17/2014 | 9/17/2014 | P | PASS |
Jim Storey
|
|
|
Please call Kelly prior to inspection for door code access. Phone #: ###-#### Inspection requested via web by Brian McCoy plm n/a final ok
|
FIRE-Final Inspection | 9/16/2014 | 9/17/2014 | 9/17/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed.
|
Permanent Occupancy | | | 9/17/2014 | | DONE |
Tisha Gallop
|
|
|
Per conversation with Emily Dixon this is for suite 100
|
FIRE-Sprinkler Rough-in | 8/29/2014 | 8/29/2014 | 8/29/2014 | A | PART |
Forrest France
|
|
|
Okay to cover overhead fire sprinkler modifications at the grid ceilings in the front office remodel areas.
|
BLD-Ceiling Grid Inspection | 8/28/2014 | 8/29/2014 | 8/29/2014 | A | PASS |
Jim Storey
|
|
|
Please call for code to lock box on door Phone #: ###-#### Inspection requested via web by Brian McCoy
|
BLD-Wall cover | 8/15/2014 | 8/15/2014 | 8/15/2014 | P | PASS |
Jim Storey
|
|
|
Please call 30 minutes prior to inspection for access code. Thank you Kelly Phone #: ###-#### Inspection requested via web by Brian McCoy
|
CHANGE STATUS TO (ISS) | | | 8/5/2014 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 8/5/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 8/4/2014 | | 8/4/2014 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/4/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/4/2014 | | DONE |
Tisha Gallop
|
|
|
do not reissue,;plan modification was batch stamped, fees due.
|
BLD-Framing/Rough-in | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PASS |
Jim Storey
|
|
|
Please call for code access prior to inspection. Thanks Kelly Phone #: ###-#### >> Inspection requested via web by Brian McCoy
|
Permit Ready to Issue | | | 6/12/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 6/12/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 6/12/2014 | | DONE |
Christina Prado
|
|
|
|
Routing PW Sewer Rating | 5/22/2014 | | 6/11/2014 | | PASS |
Connie Baumgartner
|
|
|
Signed off per E-Plan
|
Routing PW Solid Waste | 5/22/2014 | | 6/11/2014 | | PASS |
Peter J. McCullough
|
|
|
Signed off per E-plan
|
Routing - PLAN CHECK | 6/11/2014 | | 6/11/2014 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/11/2014 | | 6/11/2014 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2014 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 5/21/2014 | | 6/11/2014 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 5/21/2014 | | 6/5/2014 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 6/5/2014 | | DONE |
|
|
|
|
Routing - MECHANICAL | 5/21/2014 | | 6/2/2014 | | PASS |
Troy James
|
|
|
No mechanical submitted for review.
|
Routing - FIRE | 5/21/2014 | 5/21/2014 | 5/28/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 05-28-14
|
Routing - PUBLIC WORKS | 5/21/2014 | | 5/22/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Environmental | 5/22/2014 | | 5/22/2014 | | PASS |
Walt Baumgartner
|
|
|
|
Application received | | | 5/21/2014 | | DONE |
|
|
|
Application submitted via PDS Online on May 21 2014 8:55AM
|
Intake Approval | | | 5/21/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/21/2014 | | DONE |
|
|
|
|
Routing - Addressing | 5/21/2014 | | 5/21/2014 | | PASS |
Emily Dixon
|
|
|
|