BLD-Final | 4/27/2015 | 4/28/2015 | 4/28/2015 | P | PASS |
Tony Young
|
|
|
Scott Phone #: ###-####
|
DOC - Permit Finaled | 4/28/2015 | 4/28/2015 | 4/28/2015 | P | PASS |
Tony Young
|
|
|
c of o issued
|
PubWorks Occupancy Approval | 4/28/2015 | 4/28/2015 | 4/28/2015 | | DONE |
Jason C. Taylor
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Final | 4/24/2015 | 4/27/2015 | 4/27/2015 | P | PEND |
Tony Young
|
|
|
Scott Phone #: ###-####
|
BLD-Final | 4/24/2015 | 4/24/2015 | 4/24/2015 | P | PASS |
Tony Young
|
|
|
Scott Phone #: ###-####,, ok pending hillside sign off in system
|
BLD-Conference | 4/15/2015 | 4/15/2015 | 4/15/2015 | P | PASS |
Tony Young
|
|
|
Scott-please call 15 minutes prior Phone #: ###-####,, final walk through,, ok,, need public works
|
BLD-Conference | 4/10/2015 | 4/10/2015 | 4/10/2015 | P | NH |
Jim Sly
|
|
|
Scott Phone #: ###-####
|
BLD-Conference | 1/27/2015 | 1/28/2015 | 1/28/2015 | A | PASS |
Tony Young
|
|
|
Scott Phone #: ###-####,, stair ?s,, 3/8" tolerance ok
|
BLD-Other | 1/23/2015 | 1/23/2015 | 1/23/2015 | P | PASS |
Jim Storey
|
|
|
sheet rock exterior softets... please call // Scot ###-#### exterior soffits gyp ok ok to cover
|
BLD-Energy code compliance | 12/10/2014 | 12/10/2014 | 12/10/2014 | P | PASS |
Tony Young
|
|
|
insulation//Scott Phone #: ###-####
|
BLD-Framing/Rough-in | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | PASS |
Tony Young
|
|
|
insulation//Scott Phone #: ###-####
|
BLD-Framing/Rough-in | 12/2/2014 | 12/2/2014 | 12/2/2014 | P | PASS |
Tony Young
|
|
|
Scott; Phone #: ###-####,, ok to insulate
|
BLD-Framing/Rough-in | 12/1/2014 | 12/2/2014 | 12/2/2014 | A | DEFR |
Tony Young
|
|
|
Scott; Phone #: ###-####
|
BLD-Framing/Rough-in | 12/1/2014 | 12/1/2014 | 12/1/2014 | P | PART |
Tony Young
|
|
|
Scott Phone #: ###-####,, need fire blocking,, rated soffits,, ok to insulate
|
BLD-Framing/Rough-in | 11/26/2014 | 11/26/2014 | 11/28/2014 | P | NR |
Jim Sly
|
|
|
scott Phone #: ###-#### Need Electr R/I
|
BLD-Conference | 11/25/2014 | 11/26/2014 | 11/26/2014 | A | PASS |
Tony Young
|
|
|
scott,, mechanical ; Phone #: ###-####,, mechanical is ok with insulation
|
BLD-Conference | 11/24/2014 | 11/25/2014 | 11/25/2014 | A | PASS |
Tony Young
|
|
|
scott Phone #: ###-####,, frame walk through,, need fire blocking,, rated soffits,, tighten connections,, etc
|
Plan Modification Accepted | | | 11/13/2014 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 11/13/2014 | | 11/13/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 10/27/2014 | 10/27/2014 | 10/27/2014 | P | PASS |
Mike Jordan
|
|
|
Scott Phone #: ###-####
|
BLD-Foundation | 10/8/2014 | 10/8/2014 | 10/9/2014 | P | PASS |
Dave Hannah
|
|
|
Scott-re-bar Phone #: ###-####
|
BLD-Other | 9/23/2014 | 9/24/2014 | 9/24/2014 | A | PART |
Tony Young
|
|
|
Scott// retaining wall/// please try as close to noon as possible Phone #: ###-####,, 3 walls ok,, 2 retaining, 1 stair wall,, also garage bond beam,, all work in progress
|
BLD-Conference | 9/15/2014 | 9/15/2014 | 9/15/2014 | P | PASS |
Tony Young
|
|
|
20 ft,, grounding rod verified
|
BLD-Footing | 9/12/2014 | 9/12/2014 | 9/12/2014 | P | DONE |
Tony Young
|
|
|
Scott Phone #: ###-####,, 316 looked at
|
BLD-Other | 9/11/2014 | 9/11/2014 | 9/11/2014 | P | PART |
Jim Sly
|
|
|
Rob- wall re-bar Phone #: ###-#### OK up to approx 8' above finished floor
|
BLD-Footing | 9/9/2014 | 9/11/2014 | 9/11/2014 | A | PART |
Jim Sly
|
|
|
retaining wall - Scott Phone #: ###-#### Retaining wall footings ......OK.
|
PubWorks Subgrade Approval | 9/8/2014 | 9/8/2014 | 9/8/2014 | | DONE |
Jason C. Taylor
|
|
|
*RETAINING WALL FOOTINGS ONLY* A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 9/4/2014 | 9/4/2014 | 9/5/2014 | P | PASS |
Phil Shearer
|
|
|
Scott Phone #: ###-#### Interior footings
|
BLD-Foundation | 8/14/2014 | 8/14/2014 | 8/14/2014 | P | PART |
Tony Young
|
|
|
Rob-rebar Phone #: ###-####,, ok to add to ftgs not on lay out
|
BLD-Foundation | 8/13/2014 | 8/14/2014 | 8/14/2014 | A | PART |
Tony Young
|
|
|
Robert Phone #: ###-####-rebar,, lower coarse,,wip
|
BLD-Foundation | 8/12/2014 | 8/13/2014 | 8/13/2014 | A | PART |
Tony Young
|
|
|
Robert Phone #: ###-####-rebar,, work in progress on 1st coarses
|
BLD-Foundation | 8/11/2014 | 8/12/2014 | 8/12/2014 | A | PART |
Tony Young
|
|
|
Robert Phone #: ###-####-rebar,, IFC blocks,, lower coarse
|
BLD-Footing | 8/1/2014 | 8/4/2014 | 8/4/2014 | A | PASS |
Phil Shearer
|
|
|
early please // Sean Phone #: ###-####
|
BLD-Footing | 7/31/2014 | 8/1/2014 | 8/1/2014 | P | NR |
Tony Young
|
|
|
early pm please // Sean Phone #: ###-####
|
PubWorks Subgrade Approval | 7/29/2014 | 7/29/2014 | 7/29/2014 | | DONE |
Jason C. Taylor
|
|
|
*FOOTINGS ONLY NO SLABS* A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 7/11/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 7/7/2014 | | |
|
|
|
|
Plan assigned to (JG) | | 5/23/2014 | 7/7/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, Due 6/11 W L2 Hillside**
|
Application received | | 5/21/2014 | 7/7/2014 | | DONE |
|
|
|
|
Telephone call | | | 7/7/2014 | | DONE |
Tisha Gallop
|
|
|
called Flynner Homes and left vm permit is ready and fee due.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/7/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/7/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 7/7/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 6/10/2014 | | 7/3/2014 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 7/3/2014 | | DONE |
Javier Guzman
|
|
|
|
Plan resubmittals received | | | 6/30/2014 | | DONE |
Tisha Gallop
|
|
|
received two copies of plan sheets CV, SP1, C1, ESC, A1, A2, A3, A4, A5, A6, A7, A8, A9, A10, A11, A12, S1, S2, S3, S4, E1, E2; taken to Javier
|
Routing PW Grading-Hillside | 6/12/2014 | | 6/12/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PLAN CHECK | | | 6/10/2014 | | FAIL |
Javier Guzman
|
|
|
emailed review report to applicant
|
Routing - MECHANICAL | 6/10/2014 | | 6/10/2014 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 6/10/2014 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Grading-Hillside | 6/5/2014 | | 6/9/2014 | | FAIL |
Jason C. Taylor
|
|
|
Grading plans are not signed by engineer. 3 new sheets will need to be submitted with "Preliminary" stamp removed and Engineers signed stamp with date. Jason Taylor ###-####.
|
Routing - PLANNING | 6/5/2014 | | 6/6/2014 | | PASS |
Susan Riggs
|
|
|
|
Routing - Erosion and Sediment | 6/2/2014 | | 6/4/2014 | | PASS |
Evan Jenkins
|
|
|
|
Routing - FIRE | 6/4/2014 | | 6/4/2014 | | PASS |
Scott Arellano
|
|
|
Approved. This plan has been evaluated for Fire Department vehicle access.
|
Routing - MECHANICAL | 5/29/2014 | | 6/2/2014 | | FAIL |
Troy James
|
|
|
emailed building energy
|
Plan resubmittals received | | | 5/30/2014 | | DONE |
Christina Prado
|
|
|
Received two set of revised plan sheets marked CV, SP1, C1, ESC, A1, A2, A3, A4, A5, A6, A7, A8, A9, A10, A11, A12, S1, S2, S3, S4, E1 & E2 as well as one additional C1;Plans stamped and taken to Javier for further review
|
Routing - PUBLIC WORKS | 5/27/2014 | | 5/28/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 5/23/2014 | | 5/27/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing PW Grading-Hillside | | | 5/27/2014 | | FAIL |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/23/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 5/23/2014 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/23/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 5/21/2014 | | FAIL |
Christina Prado
|
|
|
needs to have all structural sheets stamped by engineer(foundation, framing plans, etc) as well as floor bracing details
|
Routing - PLANNING | 5/28/2014 | | | | FAIL |
Susan Riggs
|
|
|
Condition #2 of the approval letter from Planning requires a minimum three -foot wide setback and and screening area along the full length of the driveway adjacent to the west property bounday. This is not indicated on the plans.
|