First Notice | 11/17/2014 | 11/17/2014 | 11/26/2014 | | DONE |
Mike Jordan
|
|
|
This permit finaled on the web by Brian McCoy
|
BLD-Final | 11/17/2014 | 11/17/2014 | 11/17/2014 | P | PASS |
Mike Jordan
|
|
|
Doug Phone #: ###-####
|
DOC - Permit Finaled | 11/17/2014 | 11/17/2014 | 11/17/2014 | P | PASS |
Mike Jordan
|
|
|
Final letter from engineer has been recieved.
|
BLD-Final | 11/12/2014 | 11/13/2014 | 11/13/2014 | A | PEND |
Mike Jordan
|
|
|
Doug Phone #: ###-####. Need final leeter from special inspection agency and from engineer of record accepting the in place concrete that had low air entraiment.
|
FIRE-Final Inspection | 10/24/2014 | 10/24/2014 | 10/24/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 10/23/2014 | 10/24/2014 | 10/24/2014 | A | FAIL |
Troy Cobbley
|
|
|
Repair the east door exit sign.
|
BLD-Final | 10/23/2014 | 10/23/2014 | 10/23/2014 | P | NR |
Mike Jordan
|
|
|
Doug Phone #: ###-####. Needs fire/life/safety.
|
BLD-Framing/Rough-in | 9/23/2014 | 9/24/2014 | 9/24/2014 | A | CANC |
Mike Jordan
|
|
|
Entry canopies ok.
|
BLD-Framing/Rough-in | 9/22/2014 | 9/22/2014 | 9/22/2014 | P | FAIL |
Mike Jordan
|
|
|
Doug Phone #: ###-####
|
BLD-Foundation | 8/4/2014 | 8/5/2014 | 8/5/2014 | A | PASS |
Jim Storey
|
|
|
Doug-late AM pour time noon Phone #: ###-####
|
OVERRIDE | | | 8/4/2014 | | |
|
|
|
|
BLD-Footing | 7/30/2014 | 7/31/2014 | 7/31/2014 | A | PASS |
Phil Shearer
|
|
|
Doug Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/23/2014 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Bld | | | 7/23/2014 | | DONE |
Barbara Stitt
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/23/2014 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 7/10/2014 | | DONE |
Barbara Stitt
|
|
|
|
Routing Off Site - STRUCTURAL | 7/7/2014 | | 7/10/2014 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2014 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 6/4/2014 | | 7/10/2014 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 7/7/2014 | | 7/7/2014 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 6/4/2014 | | 6/19/2014 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 6/19/2014 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 6/4/2014 | | 6/18/2014 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - Erosion and Sediment | 6/4/2014 | | 6/11/2014 | | PASS |
Evan Jenkins
|
|
|
|
Routing - FIRE | 6/4/2014 | | 6/6/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-06-14
|
Routing - Design Review | 6/4/2014 | | 6/4/2014 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLANNING Land Div | 6/4/2014 | | 6/4/2014 | | PASS |
Dave Abo
|
|
|
Parcel 2 of ROS 4117.
|
Application received | | | 5/23/2014 | | DONE |
|
|
|
Application submitted via PDS Online on May 23 2014 9:35AM
|
Pending Assignment by JCM | 6/4/2014 | | | | |
John Menard
|
|
|
|