Second Notice | | 11/13/2014 | 11/6/2014 | | DONE |
|
|
|
|
First Notice | | 10/10/2014 | 11/3/2014 | | DONE |
|
|
|
|
BLD-Final | 9/30/2014 | 9/30/2014 | 9/30/2014 | P | PASS |
Tony Young
|
|
|
David Phone #: ###-####
|
FIRE-Final Inspection | 9/30/2014 | 9/30/2014 | 9/30/2014 | P | PASS |
Forrest France
|
|
|
Life safety inspection passed. PFE and address numbers posted while on site.
|
Permanent Occupancy | | | 9/30/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 7/15/2014 | | DONE |
Barbara Stitt
|
|
|
|
OVERRIDE | | | 7/14/2014 | | |
|
|
|
|
Plan assigned to (CDM) | | 6/13/2014 | 7/14/2014 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 7/14/2014 | | 7/14/2014 | | PASS |
Cody Riddle
|
|
|
Ok per Cody 7-14-14 CDM
|
Routing - PLAN CHECK | 7/14/2014 | | 7/14/2014 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/14/2014 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/14/2014 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/14/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 7/14/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan resubmittals received | | | 7/11/2014 | | DONE |
Tisha Gallop
|
|
|
received reponse letter, structural calcs and two copies of gazeebo specs.
|
1st review completed | | | 6/27/2014 | | FAIL |
|
|
|
Failed: Planning, Plan Check
|
Routing - FIRE | 6/26/2014 | | 6/27/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-27-14
|
Routing - PLAN CHECK | 6/24/2014 | | 6/26/2014 | | FAIL |
Carl D Madsen
|
|
|
See the plan review report
|
Routing - PLANNING | 6/24/2014 | | 6/24/2014 | | FAIL |
Sarah Schafer
|
|
|
Spoke with Cody Riddle. An administrative level Conditional Use Permit modification is needed for the reduction in unit count. With the construction of the gazebo and the previously approved lot consolidation, there is a reduction in two residential units on the R-1C property within the previously approved PUD. I have left a message with David McKinnon at ###-#### to call me so I can explain.
|
Routing - Erosion and Sediment | 6/16/2014 | | 6/17/2014 | | PASS |
Evan Jenkins
|
|
|
Minimal work for Gazeebo:
|
Routing - PUBLIC WORKS | 6/13/2014 | | 6/16/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 6/16/2014 | | 6/16/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING Land Div | 6/13/2014 | | 6/13/2014 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 6/13/2014 | | 6/13/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/13/2014 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/13/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/13/2014 | | PASS |
Sam Zahorka
|
|
|
|
Pending Assignment by JCB | 6/13/2014 | | 6/13/2014 | | DONE |
Jason Blais
|
|
|
per Jason - Assign to CDM
|
Routing Walk-In (Zoning) | 5/28/2014 | 5/28/2014 | 5/28/2014 | P | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 5/28/2014 | 5/28/2014 | 5/28/2014 | P | FAIL |
Perry Paine
|
|
|
need more information THIS IS TO BE A COMMERCIAL PROJECT
|
Telephone call | | | 5/28/2014 | | DONE |
|
|
|
Called contractor...This is a commercial project. Not for individual residence but a homeowners association public use structure.
|
1st review completed | | | 5/28/2014 | | FAIL |
|
|
|
|
Application received | | 5/28/2014 | | | |
|
|
|
First review completed
|