Print Statement | | | 5/15/2015 | | DONE |
|
|
|
|
First Notice | | 4/19/2015 | 5/4/2015 | | DONE |
Candy A. Nichols
|
|
|
mailed first notice 5-4-15
|
BLD-Final | 4/9/2015 | 4/9/2015 | 4/9/2015 | P | PASS |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 4/9/2015 | | DONE |
|
|
|
|
Permanent Occupancy | | | 4/9/2015 | | DONE |
|
|
|
|
Temporary Occupancy | 3/27/2015 | 6/25/2015 | 3/27/2015 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 3/25/2015 | 3/26/2015 | 3/26/2015 | P | PART |
Mike Jordan
|
|
|
tom Phone #: ###-####. ok for temp occ. Will be ok for perm occ. once elec. signs perm.
|
PubWorks Occupancy Approval | 3/26/2015 | 3/26/2015 | 3/26/2015 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 3/25/2015 | 3/25/2015 | 3/25/2015 | P | NR |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Needs public works.
|
FIRE-Final Inspection | 3/25/2015 | 3/25/2015 | 3/25/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Zoning Approval | 3/24/2015 | 3/24/2015 | 3/24/2015 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Ceiling Grid Inspection | 2/23/2015 | 2/24/2015 | 2/24/2015 | A | PART |
Mike Jordan
|
|
|
Tom Phone #: ###-####. East half of grid ok, pending eelctrical and mech. rough in inspections.
|
BLD-Ceiling Grid Inspection | 2/5/2015 | 2/6/2015 | 2/6/2015 | P | PASS |
Mike Jordan
|
|
|
Tom Phone #: ###-####. West half only.
|
BLD-Framing/Rough-in | 1/29/2015 | 1/29/2015 | 1/29/2015 | P | PASS |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Extrior steel soffit framing for front canopy.
|
BLD-Framing/Rough-in | 1/16/2015 | 1/16/2015 | 1/16/2015 | P | PASS |
Mike Jordan
|
|
|
barrell roof metal framing - Tom Phone #: ###-####. Barrell roof framing ok to cover.
|
BLD-Framing/Rough-in | 1/14/2015 | 1/15/2015 | 1/15/2015 | A | PART |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Barrell vault framing. Contractor to provide aditional framing details from architect approving in place construction.
|
BLD-Framing/Rough-in | 1/5/2015 | 1/6/2015 | 1/6/2015 | A | PART |
Mike Jordan
|
|
|
Tom Phone #: ###-####. interior steel stud framed wall and shear walls, east half ok, pend. elec.
|
BLD-Energy code compliance | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | PART |
Mike Jordan
|
|
|
Tom Phone #: ###-####. East wall at main entry, and west soffit ok to one side for barrell vault.
|
BLD-Energy code compliance | 12/3/2014 | 12/3/2014 | 12/3/2014 | P | PASS |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Exterior walls from gridlines B to D.
|
BLD-Framing/Rough-in | 12/3/2014 | 12/3/2014 | 12/3/2014 | P | PASS |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Interior steel stud framed walls from gridlines B to D.
|
BLD-Framing/Rough-in | 11/13/2014 | 11/18/2014 | 11/18/2014 | A | NR |
Mike Jordan
|
|
|
Dave Phone #: ###-#### (or tom ###-####). Needs electrical and plumbing rough in for interior walls, exterior walls ok.
|
FIRE-Conference | 11/7/2014 | 11/7/2014 | 11/7/2014 | P | DONE |
Troy Cobbley
|
|
|
Tom and I discussed fire dept access signage for the project.
|
BLD-Wall Bracing | 11/6/2014 | 11/7/2014 | 11/7/2014 | A | PASS |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Exterior and interior shear walls ok.
|
BLD-Other | 11/3/2014 | 11/4/2014 | 11/4/2014 | A | PART |
Mike Jordan
|
|
|
welding// Tom Phone #: ###-####. Work in progress on roof deck and light guage weldin at shear wall locations.
|
BLD-Final | 10/31/2014 | 10/31/2014 | 10/31/2014 | P | CANC |
Mike Jordan
|
|
|
tom Phone #: ###-####
|
BLD-Framing/Rough-in | 10/31/2014 | 10/31/2014 | 10/31/2014 | P | PASS |
Mike Jordan
|
|
|
tom Phone #: ###-####. west half roof ok to coveer.
|
BLD-Framing/Rough-in | 10/27/2014 | 10/27/2014 | 10/27/2014 | P | PART |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Exterior steel stud framed walls, west half only. Ok to cover pending special inspection on light guage steel welding.
|
BLD-Other | 10/14/2014 | 10/14/2014 | 10/14/2014 | P | PART |
Mike Jordan
|
|
|
welding, MTI will be out between 9-10am // Tom Phone #: ###-####. reviewed all special inspection reports to date.
|
BLD-Footing | 8/14/2014 | 8/15/2014 | 8/15/2014 | A | PART |
Mike Jordan
|
|
|
Footing Inspection for East portion of Building. MTI Scheduled for inspection @ 2 pm, concrete placement at 2:30 pm. Phone #: ###-#### Inspection requested via web by Rob Holtz. Work in progress on installing #10 vertical reinforcement for canopy, pending special inspection. Also reviewed all special inspection reports to date, ok.
|
BLD-Footing | 8/12/2014 | 8/13/2014 | 8/13/2014 | A | PASS |
Phil Shearer
|
|
|
Rob Phone #: ###-#### Footings north,south and west sides of the building
|
Issue PAID IN FULL permit | | | 8/1/2014 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/1/2014 | | DONE |
|
|
|
|
OVERRIDE | | | 7/31/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 7/31/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 7/28/2014 | | 7/29/2014 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/29/2014 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 6/18/2014 | | 7/29/2014 | | PASS |
John Menard
|
|
|
1st Review Complete 7/3/2014
|
Routing Off Site - STRUCTURAL | 7/28/2014 | | 7/28/2014 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 7/16/2014 | | 7/23/2014 | | PASS |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 7/16/2014 | | 7/21/2014 | | FAIL |
John Menard
|
|
|
|
Routing - PLANNING Land Div | 7/16/2014 | | 7/17/2014 | | PASS |
Dave Abo
|
|
|
Lot 4, Block 1 of EmeraldStation Subdivision
|
Routing - Design Review | 7/16/2014 | | 7/16/2014 | | PASS |
Andrea Tuning
|
|
|
*This plan has been redlined to require the light poles to be shifted so they will not interfere with the tree canopy located within the parking lot planter.
|
1st review completed | | | 7/3/2014 | | DONE |
John Menard
|
|
|
|
Routing - PLAN CHECK | 6/18/2014 | | 7/3/2014 | | FAIL |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 6/18/2014 | | 7/2/2014 | | FAIL |
John Menard
|
|
|
|
Routing PW Drainage | 7/2/2014 | | 7/2/2014 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Environmental | 6/18/2014 | | 7/1/2014 | | PASS |
Rick Christenson
|
|
|
No issues for Pretreatment.
|
Routing - FIRE | 6/18/2014 | 6/18/2014 | 6/25/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-25-14
|
Routing PW Solid Waste | 6/18/2014 | | 6/23/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Route to Impact Fee Review | 6/18/2014 | 6/23/2014 | 6/19/2014 | | PASS |
Cindy M. Gould
|
|
|
this building is on the same lot as the West Junior High Demolished in 2009(+-) with sq ft of 64,985.
|
Routing PW Sewer Rating | 6/18/2014 | | 6/19/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Street Lights | 6/18/2014 | | 6/19/2014 | | PASS |
Mike D Hedge
|
|
|
Reviewed and approved by Rob Bousfield
|
Intake Approval | | | 6/18/2014 | | PASS |
John Menard
|
|
|
|
Pending Assignment by JCM | 6/18/2014 | | 6/18/2014 | | DONE |
John Menard
|
|
|
|
Routing - PLUMBING | 6/18/2014 | | 6/18/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PLANNING Land Div | 6/18/2014 | | 6/18/2014 | | FAIL |
Dave Abo
|
|
|
Prior to issuance of a building permit, the final plat of the EmeraldStation Subdivision No. 1 must be recorded.
|
Routing - Addressing | 6/18/2014 | | 6/18/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 6/18/2014 | | 6/18/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 6/18/2014 | | 6/18/2014 | | PASS |
Evan Jenkins
|
|
|
|
Routing - Design Review | 6/18/2014 | | 6/18/2014 | | FAIL |
Andrea Tuning
|
|
|
The proposed parcel configuration does not match the existing parcel lines.
|
Intake Approval | | | 6/6/2014 | | FAIL |
John Menard
|
|
|
1. Verification of a Legal Lot is required. Jason Blais has determined, on the advise of Dave Abo, not to accept this application until the subdivision plat has been signed by the City Engineer and the plat has been submitted to the County. After the plat has been submitted to the County, the application can be submitted with a Hold Harmless Letter. You can request a Hold Harmless Letter template from Jason Blais.
2. Please go back through the plans and verify that all plan sheets have the required space in the lower right hand corner for the City approval stamp.
|
Application received | | | 6/3/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 3 2014 11:04AM
|