First Notice | | 10/31/2014 | 7/2/2015 | | DONE |
|
|
|
This permit finaled on the web by Jeremy Amar
|
Permanent Occupancy | | | 10/21/2014 | | DONE |
|
|
|
|
BLD-Final | 10/17/2014 | 10/17/2014 | 10/17/2014 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 10/16/2014 | 10/17/2014 | 10/17/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Zoning Approval | 10/17/2014 | 10/17/2014 | 10/17/2014 | | PASS |
Josh Wilson
|
|
|
|
BLD-Other | 9/10/2014 | 9/10/2014 | 9/10/2014 | P | PASS |
Mike Jordan
|
|
|
Pat- RC one channel Phone #: ###-####
|
BLD-Energy code compliance | 9/4/2014 | 9/4/2014 | 9/4/2014 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: 9###-####
|
BLD-Framing/Rough-in | 9/2/2014 | 9/2/2014 | 9/2/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 8/29/2014 | 9/2/2014 | 9/2/2014 | A | NR |
Mike Jordan
|
|
|
Pat Palmer Phone #: ###-#### Inspection requested via web by Greg Wilstead. Needs fire sprinkler rough in.
|
BLD-Wall Bracing | 8/21/2014 | 8/21/2014 | 8/21/2014 | P | PASS |
Jim Sly
|
|
|
Pat Phone #: ###-####
|
BLD-Wall Bracing | 8/15/2014 | 8/15/2014 | 8/15/2014 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Foundation | 7/16/2014 | 7/17/2014 | 7/17/2014 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Foundation | 7/15/2014 | 7/16/2014 | 7/16/2014 | P | CANC |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Footing | 7/15/2014 | 7/16/2014 | 7/16/2014 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
Permit Ready to Issue | | | 7/14/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 7/14/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 7/14/2014 | | DONE |
Christina Prado
|
|
|
|
Route to Impact Fee Review | 6/20/2014 | 6/25/2014 | 7/11/2014 | | PASS |
|
|
|
|
Plan assigned to (SRZ) | 6/20/2014 | 6/20/2014 | 7/11/2014 | | PASS |
Sam Zahorka
|
|
|
1st review completed.
|
Routing - Design Review | 6/20/2014 | | 7/11/2014 | | PASS |
Josh Wilson
|
|
|
|
Routing - Erosion and Sediment | 6/20/2014 | | 7/11/2014 | | PASS |
Evan Jenkins
|
|
|
|
Routing - PLAN CHECK | 7/11/2014 | | 7/11/2014 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2014 | | DONE |
Sam Zahorka
|
|
|
|
1st review completed | | | 7/8/2014 | | DONE |
Sam Zahorka
|
|
|
Failed Building Plan Review
|
Routing - PLAN CHECK | 6/20/2014 | | 7/8/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - PLANNING Land Div | 6/20/2014 | | 7/2/2014 | | PASS |
Dave Abo
|
|
|
|
Routing - PUBLIC WORKS | 6/20/2014 | | 7/1/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - MECHANICAL | 6/20/2014 | | 7/1/2014 | | PASS |
Troy James
|
|
|
See bld14-01507 for approved manual j report
|
Routing - PLUMBING | 6/20/2014 | | 6/30/2014 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - PLANNING | 6/20/2014 | | 6/30/2014 | | PASS |
Josh Wilson
|
|
|
|
Routing - FIRE | | | 6/30/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-30-14
|
Routing - Addressing | 6/20/2014 | | 6/30/2014 | | PASS |
Emily Dixon
|
|
|
|
Application received | | | 6/4/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 4 2014 8:37AM
|