First Notice | | 12/22/2014 | 7/2/2015 | | DONE |
|
|
|
This permit finaled on the web by Jeremy Amar
|
BLD-Final | 12/12/2014 | 12/12/2014 | 12/12/2014 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 12/12/2014 | 12/12/2014 | 12/12/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Zoning Approval | 12/12/2014 | 12/12/2014 | 12/12/2014 | | PASS |
Josh Wilson
|
|
|
|
Permanent Occupancy | | | 12/12/2014 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 12/10/2014 | 12/11/2014 | 12/11/2014 | P | CANC |
Troy Cobbley
|
|
|
Not ready for life safety final
|
BLD-Other | 10/23/2014 | 10/24/2014 | 10/24/2014 | A | PASS |
Mike Jordan
|
|
|
Pat-RC 1 channel Phone #: ###-####
|
BLD-Energy code compliance | 10/20/2014 | 10/21/2014 | 10/21/2014 | A | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Energy code compliance | 10/17/2014 | 10/20/2014 | 10/20/2014 | A | NR |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 10/15/2014 | 10/16/2014 | 10/16/2014 | A | PASS |
Mike Jordan
|
|
|
Patrick Phone #: ###-####
|
BLD-Wall Bracing | 9/26/2014 | 9/29/2014 | 9/29/2014 | A | PASS |
Mike Jordan
|
|
|
pat Phone #: ###-####
|
BLD-Wall Bracing | 9/26/2014 | 9/26/2014 | 9/26/2014 | P | DEFR |
Dave Hannah
|
|
|
pat Phone #: ###-#### out of time
|
BLD-Footing | 7/31/2014 | 8/1/2014 | 8/1/2014 | P | PASS |
Phil Shearer
|
|
|
Early PM; Phone #: John #: ###-####
|
BLD-Footing | 7/30/2014 | 7/31/2014 | 7/31/2014 | P | CANC |
Phil Shearer
|
|
|
John Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/30/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 7/30/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (SRZ) | 6/20/2014 | 6/20/2014 | 7/21/2014 | | PASS |
Sam Zahorka
|
|
|
1st review completed.
|
Routing - Design Review | 6/20/2014 | | 7/21/2014 | | PASS |
Josh Wilson
|
|
|
Signed off in ePlanReview
|
Routing - Erosion and Sediment | 6/20/2014 | | 7/21/2014 | | PASS |
Evan Jenkins
|
|
|
Signed off in ePlanReview
|
Routing - PLAN CHECK | 7/21/2014 | | 7/21/2014 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/21/2014 | | DONE |
Sam Zahorka
|
|
|
|
Permit Ready to Issue | | | 7/21/2014 | | DONE |
Christina Prado
|
|
|
|
Route to Impact Fee Review | 6/20/2014 | 6/25/2014 | 7/11/2014 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 7/8/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 6/20/2014 | | 7/8/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - PLANNING Land Div | 6/20/2014 | | 7/2/2014 | | PASS |
Dave Abo
|
|
|
|
Routing - MECHANICAL | 6/20/2014 | | 7/1/2014 | | PASS |
Troy James
|
|
|
see bld14-01509 for approved manual j report
|
Routing - PUBLIC WORKS | 6/20/2014 | | 7/1/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - FIRE | | | 6/30/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-30-14
|
Routing - PLUMBING | 6/20/2014 | | 6/30/2014 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - PLANNING | 6/20/2014 | | 6/30/2014 | | PASS |
Josh Wilson
|
|
|
|
Routing - Addressing | 6/20/2014 | | 6/30/2014 | | PASS |
Emily Dixon
|
|
|
|
Application received | | | 6/4/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 4 2014 8:44AM
|