Third Notice | | 4/17/2016 | 5/11/2016 | | DONE |
|
|
|
|
Second Notice | | 2/22/2016 | 4/12/2016 | | DONE |
|
|
|
Mailed 4-13-16
|
First Notice | | 2/7/2016 | 2/12/2016 | | DONE |
|
|
|
sent with mail 2-16-16
|
Print Occupancy Form | | | 1/28/2016 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/28/2016 | | DONE |
|
|
|
|
Zoning Approval | 1/25/2016 | 1/25/2016 | 1/25/2016 | | PASS |
Josh Wilson
|
|
|
|
Telephone call | | | 1/25/2016 | | DONE |
|
|
|
called Brad @ ###-#### to let know someone needs to come pick up perm c of o-talked to his assistant
|
BLD-Final | 1/21/2016 | 1/21/2016 | 1/21/2016 | P | DONE |
Mike Jordan
|
|
|
having a hard time contacting owner-can you please go by and see if they are ready for the final? Candy. Building portion ios completed. Need zonong to sign off.
|
Telephone call | | | 11/17/2015 | | DONE |
|
|
|
called Bradly to let know the temp is expired and he needs to contact Jason B asap
|
BLD-Aging Inspection | 10/16/2015 | 10/16/2015 | 10/16/2015 | | PASS |
Mike Jordan
|
|
|
|
Telephone call | | | 10/12/2015 | | DONE |
|
|
|
called Bradly to let know temp c of o is expired and that someone needs to get a hold of me as soon as possible for the final inspections-told him that Mike with STS Contractors-left message
|
Telephone call | | | 9/29/2015 | | DONE |
|
|
|
called sts Contractors-they will have Mike call me (CAN) and let me know what's going on. STS says they did not finish the job
|
Telephone call | | | 9/17/2015 | | |
|
|
|
called Mike to see if they
|
Telephone call | | | 9/17/2015 | | DONE |
|
|
|
called Mike who will talk to Latan and see if the final is ready to be called in. He will get back to me
|
Temporary Occupancy | 6/19/2015 | 9/17/2015 | 6/19/2015 | | DONE |
Brittany Hill
|
|
|
|
PubWorks Occupancy Approval | 6/19/2015 | 6/19/2015 | 6/19/2015 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 6/16/2015 | 6/18/2015 | 6/18/2015 | P | PART |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Will be ok for perm occ. once zoning and public works signs perm.
|
BLD-Final | 5/13/2015 | 5/13/2015 | 5/14/2015 | P | NR |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Needs public works final.
|
PubWorks Occupancy Approval | 5/14/2015 | 5/14/2015 | 5/14/2015 | | DONE |
Jason C. Taylor
|
|
|
*TEMPORARY OCCUPANCY APPROVED** URBAN FILTERS NEEDED. Jason Taylor ###-####.
|
FIRE-Final Inspection | 5/12/2015 | 5/13/2015 | 5/13/2015 | A | PASS |
Katie Marron
|
|
|
Fire life safety pass.
|
Zoning Approval Temp | 5/13/2015 | 5/13/2015 | 5/13/2015 | | PASS |
Josh Wilson
|
|
|
90-day temp occ. landscape bond is in place. JGW 5-13-15
|
PubWorks Occupancy Approval | 5/13/2015 | 5/13/2015 | 5/13/2015 | | FAIL |
Jason C. Taylor
|
|
|
*NO OCCUPANCY APPROVAL**RESUBMITTAL REQUIRED** Jason Taylor ###-####.
|
FIRE-Final Inspection | 5/11/2015 | 5/11/2015 | 5/11/2015 | P | CANC |
Katie Marron
|
|
|
Not ready for life safety inspection per phone call.
|
FIRE-Final Inspection | 5/8/2015 | 5/8/2015 | 5/8/2015 | P | NR |
Katie Marron
|
|
|
Not ready for life safety. Meant to call in fire permit final.
|
BLD-Other | 4/20/2015 | 4/20/2015 | 4/20/2015 | P | PASS |
Mike Jordan
|
|
|
Roof decking // Mike Phone #: ###-####
|
BLD-Foundation | 3/18/2015 | 3/19/2015 | 3/19/2015 | A | PASS |
Mike Jordan
|
|
|
Rebar // Mike Phone #: ###-####. Slab on grade reinforcement for wash bay ok.
|
BLD-Footing | 2/13/2015 | 2/13/2015 | 2/13/2015 | P | PART |
Mike Jordan
|
|
|
Pouring at 1///Rebar - Mike Phone #: ###-####. Work in progress. Pending special inspection.
|
BLD-Footing | 10/15/2014 | 10/16/2014 | 10/16/2014 | A | DEFR |
Mike Jordan
|
|
|
South parking lot light pole base - Mike Phone #: ###-####
|
BLD-Footing | 10/9/2014 | 10/10/2014 | 10/10/2014 | P | PART |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Work in progress. Will have special inspection.
|
Issue PAID IN FULL permit | | | 9/29/2014 | | DONE |
Cheryl Baumgartner
|
|
|
|
Print Occupancy Form | | | 9/29/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 9/26/2014 | | DONE |
Candy A. Nichols
|
|
|
called Mike ###-####-told him we have everything that is needed-he can come sign the permits when issued.
|
Telephone call | | | 8/21/2014 | | DONE |
Tisha Gallop
|
|
|
per Jeanne Gage at ACHD wash bay addition and parking lot are not yet approved.
|
Telephone call | | | 8/19/2014 | | DONE |
Candy A. Nichols
|
|
|
called Mike Jeffries to let know we received check in mail and he could come sign the issued permit-(left message on his phone ###-####-7361) Receipt is in drawer
|
OVERRIDE | | | 8/4/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 8/4/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 7/28/2014 | | 7/28/2014 | | PASS |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 7/28/2014 | | 7/28/2014 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2014 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 6/10/2014 | | 7/28/2014 | | PASS |
John Menard
|
|
|
1st Review Complete 6/19/2014
|
Routing - PLAN CHECK | 7/15/2014 | | 7/23/2014 | | PASS |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 7/15/2014 | | 7/19/2014 | | FAIL |
John Menard
|
|
|
|
Routing PW Environmental | 7/15/2014 | | 7/15/2014 | | PASS |
Terry Alber
|
|
|
Corrections to exposed drains approved.
|
Routing PW Environmental | 7/23/2014 | | 7/15/2014 | | PASS |
Terry Alber
|
|
|
|
Routing - PUBLIC WORKS | 7/15/2014 | | 7/15/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PUBLIC WORKS | 6/10/2014 | | 7/15/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 6/10/2014 | | 6/20/2014 | | PASS |
Brian Murphy
|
|
|
|
1st review completed | | | 6/20/2014 | | DONE |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 6/10/2014 | | 6/19/2014 | | FAIL |
John Menard
|
|
|
|
Routing - PLAN CHECK | 6/10/2014 | | 6/19/2014 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 6/10/2014 | 6/10/2014 | 6/17/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-17-14
|
Routing - PLUMBING | 6/10/2014 | | 6/16/2014 | | PASS |
Daryl Spivey
|
|
|
|
Routing - Design Review | 6/10/2014 | | 6/16/2014 | | PASS |
Josh Wilson
|
|
|
|
Routing - Erosion and Sediment | 6/10/2014 | | 6/12/2014 | | PASS |
Evan Jenkins
|
|
|
|
Routing PW Environmental | 6/10/2014 | | 6/12/2014 | | FAIL |
Rick Christenson
|
|
|
Cover area or disconnect drain. Any sanitary sewer connected drains at entrance or exit of wash-tunnel must be covered and the pad sloped to preclude storm water/roof runoff from entering drain. Wastewater from any pre-rinse or pre-wash activities at tunnel entrance must be routed to sanitary sewer system.
|
Route to Impact Fee Review | 6/10/2014 | 6/13/2014 | 6/11/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Sewer Rating | 6/10/2014 | | 6/10/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING Land Div | 6/10/2014 | | 6/10/2014 | | PASS |
Dave Abo
|
|
|
|
Routing - Addressing | 6/10/2014 | | 6/10/2014 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 6/10/2014 | | PASS |
John Menard
|
|
|
2nd plan intake review
|
Pending Assignment by JCM | 6/10/2014 | | 6/10/2014 | | DONE |
John Menard
|
|
|
|
Intake Approval | | | 6/9/2014 | | FAIL |
|
|
|
(6-9-14) Please refer to the circled items on the plan intake checklist and resolve them as specified. CJW
|
Application received | | | 6/5/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 5 2014 3:38PM
|