Second Notice | | 5/14/2015 | 6/3/2015 | | DONE |
|
|
|
This permit finaled on the web by Cecyle Brock
|
First Notice | | 4/30/2015 | 5/4/2015 | | DONE |
Candy A. Nichols
|
|
|
mailed first notice 5-4-15
|
BLD-Final | 4/17/2015 | 4/20/2015 | 4/20/2015 | A | PASS |
Jim Storey
|
|
|
Tony Phone #: ###-#### please call to meet
|
Permanent Occupancy | | | 4/20/2015 | | DONE |
|
|
|
|
Permanent Occupancy | | | 4/20/2015 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/15/2015 | 4/15/2015 | 4/15/2015 | P | PASS |
Katie Marron
|
|
|
Remainder of scope of work completed, building numbers have been posted final life safety approved.
|
Zoning Approval | 4/15/2015 | 4/15/2015 | 4/15/2015 | | PASS |
Josh Wilson
|
|
|
Landscaping complete. Bond can be released.
|
BLD-Final | 3/4/2015 | 3/5/2015 | 3/5/2015 | A | PART |
Jim Storey
|
|
|
Rick Phone #: ###-#### final ok pending temp sign offs
|
Temporary Occupancy | 3/5/2015 | 5/25/2015 | 3/5/2015 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 3/4/2015 | 3/4/2015 | 3/4/2015 | P | PART |
Forrest France
|
|
|
Final pending completion of elevator and related control equipment. Remainder of fire life safety inspection items completed. Need to post missing building address numbers.
|
Zoning Approval Temp | 2/24/2015 | 2/24/2015 | 2/24/2015 | | PASS |
Josh Wilson
|
|
|
90 day bond in place for landscaping. JGW 2-24-15
|
BLD-Ceiling Grid Inspection | 2/17/2015 | 2/18/2015 | 2/18/2015 | A | PASS |
Mike Jordan
|
|
|
Rick Phone #: ###-####
|
BLD-Framing/Rough-in | 1/7/2015 | 1/8/2015 | 1/8/2015 | A | PASS |
Jim Storey
|
|
|
Rick Phone #: ###-####
|
Case Summary (BLD) | | | 12/29/2014 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 12/23/2014 | 12/24/2014 | 12/24/2014 | A | PASS |
Jim Storey
|
|
|
Rick Phone #: ###-####
|
BLD-Energy code compliance | 12/18/2014 | 12/19/2014 | 12/19/2014 | A | PASS |
Jim Storey
|
|
|
Rick Phone #: ###-#### ok to cover exterior walls
|
BLD-Framing/Rough-in | 11/18/2014 | 11/20/2014 | 11/20/2014 | A | PASS |
Jim Storey
|
|
|
Rick Phone #: ###-#### 2nd floor ok to place
|
BLD-Framing/Rough-in | 11/18/2014 | 11/19/2014 | 11/18/2014 | P | CANC |
Jim Storey
|
|
|
rick Phone #: ###-#### Inspection cancelled from web by: Kristal Soland
|
Routing - Addressing | 11/10/2014 | | 11/10/2014 | | PASS |
Jason C. Taylor
|
|
|
New address added at owners request. JCT
|
BLD-Conference | 11/5/2014 | 11/6/2014 | 11/6/2014 | A | PASS |
Jim Storey
|
|
|
Rick// please call 30 min before Phone #: ###-#### reviewed 1 hr wall westside.ok
|
BLD-Framing/Rough-in | 10/28/2014 | 10/28/2014 | 10/28/2014 | P | PASS |
Dave Hannah
|
|
|
Rick Phone #: ###-#### exterior walls
|
BLD-Foundation | 9/4/2014 | 9/4/2014 | 9/4/2014 | P | PASS |
Jim Storey
|
|
|
Rick Phone #: ###-####
|
BLD-Footing | 9/2/2014 | 9/3/2014 | 9/4/2014 | P | PASS |
Jim Storey
|
|
|
Rick Phone #: ###-####placed w si
|
BLD-Footing | 8/28/2014 | 9/2/2014 | 9/2/2014 | P | PASS |
Jim Storey
|
|
|
Rick Phone #: ###-#### east and north ft ok pending si report.
|
Issue PAID IN FULL permit | | | 8/27/2014 | | DONE |
Candy A. Nichols
|
|
|
|
OVERRIDE | | | 8/26/2014 | | |
|
|
|
|
Telephone call | | | 8/26/2014 | | DONE |
Candy A. Nichols
|
|
|
called Megan and told her the permits were ready and how much is owed. Also told her we need the GC and RP
|
Routing - PLAN CHECK | 8/26/2014 | | 8/26/2014 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2014 | | DONE |
John Menard
|
|
|
|
Print Occupancy Form | | | 8/26/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 8/26/2014 | | DONE |
Candy A. Nichols
|
|
|
need RP and GC
|
Plan assigned to (JCM) | 6/10/2014 | | 8/26/2014 | | PASS |
John Menard
|
|
|
1st Review Complete 6/25/2014 - Campbell Company Shell
|
Plan resubmittals received | | | 8/25/2014 | | DONE |
Christina Prado
|
|
|
received two sets of revised plan sheets marked a2.11, a2.12, a2.31, a2.32, a4.21 & a6.11 as well as one response letter; Plans inserted by arch rep and taken back to John for review
|
Routing - PLAN CHECK | 8/13/2014 | | 8/22/2014 | | FAIL |
John Menard
|
|
|
|
Plan resubmittals requested | | | 8/22/2014 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 8/6/2014 | | 8/14/2014 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 8/8/2014 | | 8/13/2014 | | PASS |
|
|
|
See Red Line comments on Fire Plan Review Mod 08-13-14
|
Routing - Design Review | 8/7/2014 | | 8/8/2014 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLUMBING | 8/6/2014 | | 8/7/2014 | | PASS |
Daryl Spivey
|
|
|
|
Routing - PUBLIC WORKS | 8/6/2014 | | 8/6/2014 | | PASS |
Beverly Mountain
|
|
|
For Beverly Mountain
|
Permit Ready to Issue | | | 8/6/2014 | | |
|
|
|
|
Routing PW Sewer Rating | 8/6/2014 | | 8/6/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLAN CHECK | 6/27/2014 | | 8/6/2014 | | |
John Menard
|
|
|
|
Plan resubmittals received | | | 8/5/2014 | | |
|
|
|
Received 1 cover transmittal, 1 response letter dated 8/1/14 from Megan Burke, 1 comments letter from AHJ, 3 copies of amended structural calculations, 3 copies of structural design data, 4 new complete sets of plans and all taken over to John Menards desk
|
1st review completed | | | 6/27/2014 | | FAIL |
|
|
|
Failed: Plan Check, Structural, Plumbing
|
Routing - FIRE | 6/25/2014 | | 6/27/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-27-14
|
Routing Off Site - STRUCTURAL | 6/10/2014 | | 6/25/2014 | | FAIL |
John Menard
|
|
|
Received letter from consulting structural engineer requesting revisions. JCM
|
Routing - PLAN CHECK | 6/16/2014 | | 6/25/2014 | | FAIL |
John Menard
|
|
|
|
Plan resubmittals requested | | | 6/25/2014 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review requesting revisions. JCM
|
Plan resubmittals requested | | | 6/25/2014 | | |
John Menard
|
|
|
E-mailed the archtiect a copy of the plan review requesting revisions. JCM
|
Route to Impact Fee Review | 6/10/2014 | 6/13/2014 | 6/20/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 6/13/2014 | | 6/16/2014 | | PASS |
Josh Wilson
|
|
|
DRH14-00134 Josh Wilson
|
Routing - PLUMBING | 6/12/2014 | | 6/13/2014 | | FAIL |
Bill VanDegrift
|
|
|
Provide secondary roof drain system for cold shell.
|
Routing - Erosion and Sediment | 6/11/2014 | | 6/12/2014 | | PASS |
Evan Jenkins
|
|
|
ref ESC14-00499
|
Routing - Addressing | 6/10/2014 | | 6/11/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 6/11/2014 | | 6/11/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 6/11/2014 | | 6/11/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 6/11/2014 | | 6/11/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Application received | | 6/9/2014 | 6/10/2014 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/10/2014 | | DONE |
Tisha Gallop
|
|
|
received three copies of updated structural sheets s2.11 & s3.11; taken to John Menard.
|
Telephone call | | | 6/10/2014 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up
|
Pending Assignment by JCM | 6/10/2014 | | 6/10/2014 | | DONE |
John Menard
|
|
|
|
Routing - PLANNING Land Div | 6/10/2014 | | 6/10/2014 | | PASS |
Dave Abo
|
|
|
Lot 3, Block 1 of Empress Romona Subdivision
|
Intake Approval | | | 6/10/2014 | | PASS |
John Menard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/9/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/9/2014 | | DONE |
Tisha Gallop
|
|
|
|