Permit Information
Permit NumberBLD14-01582
StatusFinaled
Name JAYO CONSTRUCTION
Site Address 479 W TERRA COTTA LN
Project Name 
Customer Number 
ePlanReviewNo
Description
WUI Zone A, Class A Roof, Permit for the construction of a new 2218 sq. ft., one story single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 308 sq. ft. of covered patio/porch and a 617 sq. ft. attached garage per the approved plans, Rescheck, plan review report and any notations. R-1B zoning and setbacks per planning.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Blower Door Test Results1/23/20151/26/20151/26/2015APASS
DetailsTony Young
Lift garage door to open Phone #: ###-#### Inspection requested via web by Stephanie Anthony,, 3.7
BLD-Final1/22/20151/23/20151/23/2015APASS
DetailsTony Young
Lift garage door to open Phone #: ###-#### Inspection requested via web by Stephanie Anthony
DOC - Permit Finaled1/23/20151/23/20151/23/2015PPASS
DetailsTony Young
c of o issued
BLD-Final1/22/20151/23/20151/22/2015ACANC
DetailsTony Young
Garage code 5296 Phone #: ###-#### >> Inspection requested via web by Stephanie Anthony Inspection cancelled from web by: Stephanie Anthony
BLD-Final1/21/20151/22/20151/22/2015PCANC
DetailsPhil Shearer
Phone #: ###-#### Inspection requested via web by SHANE JAYO
PubWorks Occupancy Approval1/21/20151/21/20151/21/2015 DEFR
DetailsJason C. Taylor
Publis Works has reviewed the rear rock swale that was built for the subdivision draiange. The draiange system has not been encroached upon and is functional. Public Works Hillside has no comment on the resident draiange as this was not a hillside subdivision. Occupancy may be granted when the Building Department is ready. Jason Taylor ###-####.
BLD-Energy code compliance10/29/201410/29/201410/29/2014PPASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by SHANE JAYO
BLD-Framing/Rough-in10/20/201410/20/201410/21/2014PNR
DetailsTony Young
Phone #: ###-#### Inspection requested via web by SHANE JAYO,, re nail shear
BLD-Framing/Rough-in10/17/201410/20/201410/20/2014APART
DetailsTony Young
Phone #: ###-#### Inspection requested via web by SHANE JAYO,, correction notice posted
Plan Modification Accepted  10/1/2014 DONE
new manual j
Routing - MECHANICAL10/1/2014 10/1/2014 PASS
DetailsTroy James
resubmitted manual j report
CHANGE STATUS TO (ISS)  8/28/2014 DONE
DetailsTisha Gallop
picked up and paid for plan mod
Plan assigned to (JG) 8/27/20148/27/2014 PASS
DetailsJavier Guzman
Plan Mod
Routing - PLAN CHECK  8/27/2014 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  8/27/2014 DONE
CHANGE STATUS TO (RDY)  8/27/2014 DONE
DetailsCandy A. Nichols
Telephone call  8/27/2014 DONE
DetailsCandy A. Nichols
called Stephanieto let know permit is ready and how much is owed - plans are in the walk in drawer
Plan Modification Accepted  8/27/2014 DONE
DetailsChristina Prado
Plan mod taken in for changes to exterior retaining wall.
BLD-Foundation8/18/20148/19/20148/19/2014APASS
DetailsPhil Shearer
pat ###-####
BLD-Foundation8/18/20148/18/20148/18/2014PPART
DetailsTony Young
pat ###-####,, work in progress
Issue PAID IN FULL permit  8/18/2014 DONE
BLD-Footing8/14/20148/14/20148/14/2014PPART
DetailsTony Young
PubWorks Subgrade Approval8/13/20148/13/20148/13/2014 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
PLANS/APPL TAKEN TO FRONT DESK  6/30/2014 DONE
Inspection Record Card- Bld  6/30/2014 DONE
DetailsChristina Prado
Permit Ready to Issue  6/30/2014 DONE
DetailsCandy A. Nichols
Telephone call  6/30/2014 DONE
DetailsCandy A. Nichols
left message w/Shane-permit is ready & told him the amount that was due
Routing - PLAN CHECK6/27/2014 6/30/2014 PASS
DetailsJavier Guzman
Routing - Erosion and Sediment6/27/2014 6/27/2014 PASS
DetailsAndy J. Long
ESC plan approved. Valid RP and PD designated.
Routing - PLAN CHECK6/27/2014 6/27/2014 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  6/27/2014 DONE
Plan assigned to (JG)6/9/20146/9/20146/26/2014 PASS
DetailsJavier Guzman
Due 6/26 TH L1 Hillside*
Routing - PLAN CHECK6/18/2014 6/26/2014 PASS
DetailsJavier Guzman
1st review completed  6/26/2014 DONE
DetailsJavier Guzman
Case Summary (BLD)  6/26/2014 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  6/26/2014 DONE
Routing - MECHANICAL6/11/2014 6/18/2014 PASS
DetailsTroy James
Routing - FIRE6/18/2014 6/18/2014 PASS
DetailsScott Arellano
Approved.
Route to Impact Fee Review6/9/20146/12/20146/11/2014 PASS
DetailsCindy M. Gould
Routing - PUBLIC WORKS6/11/2014 6/11/2014 PASS
DetailsConnie Baumgartner
Routing PW Grading-Hillside  6/11/2014 PASS
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
Routing - PLANNING6/11/2014 6/11/2014 PASS
DetailsSusan Riggs
Application received 6/9/20146/9/2014 DONE
Plans ACCEPTED BY PLAN TECH  6/9/2014 DONE
Intake Approval  6/9/2014 PASS