BLD-Blower Door Test Results | 1/23/2015 | 1/26/2015 | 1/26/2015 | A | PASS |
Tony Young
|
|
|
Lift garage door to open Phone #: ###-#### Inspection requested via web by Stephanie Anthony,, 3.7
|
BLD-Final | 1/22/2015 | 1/23/2015 | 1/23/2015 | A | PASS |
Tony Young
|
|
|
Lift garage door to open Phone #: ###-#### Inspection requested via web by Stephanie Anthony
|
DOC - Permit Finaled | 1/23/2015 | 1/23/2015 | 1/23/2015 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 1/22/2015 | 1/23/2015 | 1/22/2015 | A | CANC |
Tony Young
|
|
|
Garage code 5296 Phone #: ###-#### >> Inspection requested via web by Stephanie Anthony Inspection cancelled from web by: Stephanie Anthony
|
BLD-Final | 1/21/2015 | 1/22/2015 | 1/22/2015 | P | CANC |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by SHANE JAYO
|
PubWorks Occupancy Approval | 1/21/2015 | 1/21/2015 | 1/21/2015 | | DEFR |
Jason C. Taylor
|
|
|
Publis Works has reviewed the rear rock swale that was built for the subdivision draiange. The draiange system has not been encroached upon and is functional. Public Works Hillside has no comment on the resident draiange as this was not a hillside subdivision. Occupancy may be granted when the Building Department is ready. Jason Taylor ###-####.
|
BLD-Energy code compliance | 10/29/2014 | 10/29/2014 | 10/29/2014 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by SHANE JAYO
|
BLD-Framing/Rough-in | 10/20/2014 | 10/20/2014 | 10/21/2014 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by SHANE JAYO,, re nail shear
|
BLD-Framing/Rough-in | 10/17/2014 | 10/20/2014 | 10/20/2014 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by SHANE JAYO,, correction notice posted
|
Plan Modification Accepted | | | 10/1/2014 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 10/1/2014 | | 10/1/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
CHANGE STATUS TO (ISS) | | | 8/28/2014 | | DONE |
Tisha Gallop
|
|
|
picked up and paid for plan mod
|
Plan assigned to (JG) | | 8/27/2014 | 8/27/2014 | | PASS |
Javier Guzman
|
|
|
Plan Mod
|
Routing - PLAN CHECK | | | 8/27/2014 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/27/2014 | | DONE |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 8/27/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 8/27/2014 | | DONE |
Candy A. Nichols
|
|
|
called Stephanieto let know permit is ready and how much is owed - plans are in the walk in drawer
|
Plan Modification Accepted | | | 8/27/2014 | | DONE |
Christina Prado
|
|
|
Plan mod taken in for changes to exterior retaining wall.
|
BLD-Foundation | 8/18/2014 | 8/19/2014 | 8/19/2014 | A | PASS |
Phil Shearer
|
|
|
pat ###-####
|
BLD-Foundation | 8/18/2014 | 8/18/2014 | 8/18/2014 | P | PART |
Tony Young
|
|
|
pat ###-####,, work in progress
|
Issue PAID IN FULL permit | | | 8/18/2014 | | DONE |
|
|
|
|
BLD-Footing | 8/14/2014 | 8/14/2014 | 8/14/2014 | P | PART |
Tony Young
|
|
|
|
PubWorks Subgrade Approval | 8/13/2014 | 8/13/2014 | 8/13/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/30/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 6/30/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 6/30/2014 | | DONE |
Candy A. Nichols
|
|
|
left message w/Shane-permit is ready & told him the amount that was due
|
Routing - PLAN CHECK | 6/27/2014 | | 6/30/2014 | | PASS |
Javier Guzman
|
|
|
|
Routing - Erosion and Sediment | 6/27/2014 | | 6/27/2014 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Valid RP and PD designated.
|
Routing - PLAN CHECK | 6/27/2014 | | 6/27/2014 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2014 | | DONE |
|
|
|
|
Plan assigned to (JG) | 6/9/2014 | 6/9/2014 | 6/26/2014 | | PASS |
Javier Guzman
|
|
|
Due 6/26 TH L1 Hillside*
|
Routing - PLAN CHECK | 6/18/2014 | | 6/26/2014 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 6/26/2014 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 6/26/2014 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/26/2014 | | DONE |
|
|
|
|
Routing - MECHANICAL | 6/11/2014 | | 6/18/2014 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 6/18/2014 | | 6/18/2014 | | PASS |
Scott Arellano
|
|
|
Approved.
|
Route to Impact Fee Review | 6/9/2014 | 6/12/2014 | 6/11/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PUBLIC WORKS | 6/11/2014 | | 6/11/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | | | 6/11/2014 | | PASS |
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PLANNING | 6/11/2014 | | 6/11/2014 | | PASS |
Susan Riggs
|
|
|
|
Application received | | 6/9/2014 | 6/9/2014 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/9/2014 | | DONE |
|
|
|
|
Intake Approval | | | 6/9/2014 | | PASS |
|
|
|
|