BLD-Final | 10/14/2014 | 10/14/2014 | 10/14/2014 | P | FAIL |
Tony Young
|
|
|
Ken Phone #: ###-####,, need to meet barrier requirements
|
BLD-Footing | 8/20/2014 | 8/20/2014 | 8/20/2014 | P | PASS |
Tony Young
|
|
|
Ken; Phone #: ###-####
|
BLD-Footing | 8/19/2014 | 8/20/2014 | 8/20/2014 | A | NR |
Tony Young
|
|
|
Ken; Phone #: ###-####,, needs elec 1st
|
BLD-Footing | 8/19/2014 | 8/19/2014 | 8/20/2014 | P | NR |
Tony Young
|
|
|
need electrical 1st
|
BLD-Foundation | 8/19/2014 | 8/19/2014 | 8/19/2014 | P | CANC |
Tony Young
|
|
|
|
PubWorks Subgrade Approval | 8/11/2014 | 8/11/2014 | 8/11/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 7/29/2014 | | |
|
|
|
|
Routing Walk-In (PW Hillside) | 7/29/2014 | 7/29/2014 | 7/29/2014 | A | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing Walk-In (BLD) | 7/29/2014 | 7/29/2014 | 7/29/2014 | A | FAIL |
Perry Paine
|
|
|
need ESC Waiver or plan
|
Routing Walk-In (Erosion) | 7/29/2014 | 7/29/2014 | 7/29/2014 | A | PASS |
Andy J. Long
|
|
|
Plan Waiver Request. Waiver approved. Valid RP designated.
|
Telephone call | | | 7/29/2014 | | DONE |
Christina Prado
|
|
|
called Ken to advise permit is ready and gave fees due
|
Inspection Record Card- Bld | | | 7/29/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 7/29/2014 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/29/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/29/2014 | | DONE |
Christina Prado
|
|
|
|
Routing Walk-In (PW Hillside) | 7/10/2014 | 7/10/2014 | 7/10/2014 | P | FAIL |
Jason C. Taylor
|
|
|
Need 6' retaining wall structrual design submitted for building permit prior to approval of this application. Will also need engineering for pool and geotechnical enginnering for setback distance for pool and wall. Jason Taylor ###-####
|
Plan resubmittals received | | | 7/10/2014 | | DONE |
Candy A. Nichols
|
|
|
resubmitted 3 sets (8 1/2 x 10)of grading & drainage plans w/vicinity plan and 3 sheets of grading & drainage-took to Jason Taylor
|
Routing Walk-In (PW Hillside) | 6/16/2014 | 6/16/2014 | 6/16/2014 | A | FAIL |
Jason C. Taylor
|
|
|
Need engineering
|
Routing Walk-In (Zoning) | 6/16/2014 | 6/16/2014 | 6/16/2014 | A | PASS |
Colleen T Carroll
|
|
|
|
1st review completed | | | 6/16/2014 | | FAIL |
|
|
|
need ESC approval
|
Application received | | 6/16/2014 | | | |
|
|
|
|