Third Notice | | 6/14/2015 | 6/17/2015 | | DONE |
|
|
|
This permit finaled on the web by Penny Dennis
|
Second Notice | | 5/14/2015 | 6/9/2015 | | DONE |
|
|
|
sent in mail
|
First Notice | | 3/20/2015 | 5/4/2015 | | DONE |
Candy A. Nichols
|
|
|
mailed first notice 5-4-15
|
Case Summary (BLD) | | | 3/30/2015 | | DONE |
|
|
|
|
Permanent Occupancy | | | 3/10/2015 | | DONE |
|
|
|
|
Zoning Approval | 3/5/2015 | 3/5/2015 | 3/5/2015 | | PASS |
Josh Wilson
|
|
|
Ok for final on this building. Landscaping must be completed prior to occupancy sign off of office building.
|
BLD-Final | 3/3/2015 | 3/4/2015 | 3/4/2015 | A | PASS |
Phil Shearer
|
|
|
Shop blg Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
FIRE-Final Inspection | 3/2/2015 | 3/2/2015 | 3/3/2015 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
OVERRIDE | | | 2/27/2015 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/27/2015 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 2/27/2015 | | DONE |
Christina Prado
|
|
|
|
Routing PW Sewer Rating | 2/20/2015 | | 2/27/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLAN CHECK | 2/27/2015 | | 2/27/2015 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/27/2015 | | DONE |
John Menard
|
|
|
|
Permit Ready to Issue | | | 2/27/2015 | | DONE |
Christina Prado
|
|
|
****DO NOT RE-ISSUE****
All requirements met, fees need to be paid to change status back to ISS
|
Plan assigned to (JCM) | 2/10/2015 | | 2/27/2015 | | PASS |
John Menard
|
|
|
Plan Modification
|
Routing - PLAN CHECK | 2/20/2015 | | 2/27/2015 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 2/20/2015 | | 2/26/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing Off Site - STRUCTURAL | 2/20/2015 | | 2/23/2015 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 2/10/2015 | | 2/18/2015 | | PASS |
Scott Arellano
|
|
|
No change from previous review.
|
Routing - PLAN CHECK | 2/10/2015 | | 2/11/2015 | | FAIL |
John Menard
|
|
|
|
BLD-Wall cover | 2/5/2015 | 2/5/2015 | 2/5/2015 | P | PASS |
Phil Shearer
|
|
|
Hard lid and wall cover @ Mezzanine in Shop- building #2 Phone #: ###-#### Inspection requested via web by Philip Allen Pending HVAC inspection
|
Plan Modification Accepted | | | 2/3/2015 | | DONE |
|
|
|
Work flow started for plan mod from 2B to 5B construction
|
BLD-Framing/Rough-in | 1/28/2015 | 1/29/2015 | 1/29/2015 | A | PART |
Jim Sly
|
|
|
Shop building framing for demising wall and mezzanine. Phone #: ###-#### Inspection requested via web by Philip Allen Appears OK Note 1hr walls at stairs and riser room........walk thru ......OK to 1 side Need all trade rough-in approvals.
|
BLD-Concrete | 1/7/2015 | 1/8/2015 | 1/8/2015 | P | PASS |
Phil Shearer
|
|
|
Pre- concrete rebar for Slab on Deck for Mezzanine @ Shop Phone #: ###-#### Inspection requested via web by Philip Allen. Per MTI inspection.
|
BLD-Concrete | 12/5/2014 | 12/8/2014 | 12/8/2014 | A | PASS |
Phil Shearer
|
|
|
Pre- concrete for shop. Phone #: ###-#### Inspection requested via web by Philip Allen
|
BLD-Foundation | 10/17/2014 | 10/20/2014 | 10/20/2014 | A | PART |
Jim Storey
|
|
|
Concrete at 2:30 Phone #: ###-#### Inspection requested via web by Kevin Honeycutt wip si to verify rebar.
|
BLD-Foundation | 10/8/2014 | 10/9/2014 | 10/9/2014 | P | PASS |
Phil Shearer
|
|
|
OK per MTI's approval
|
Issue PAID IN FULL permit | | | 9/24/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 9/24/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 9/23/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 9/23/2014 | | DONE |
Candy A. Nichols
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/12/2014 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 7/10/2014 | | 9/12/2014 | | PASS |
John Menard
|
|
|
1st Review Complete 7/28/2014
|
Routing - PLAN CHECK | 9/10/2014 | | 9/12/2014 | | PASS |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 9/10/2014 | | 9/11/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing Off Site - STRUCTURAL | 9/10/2014 | | 9/11/2014 | | PASS |
John Menard
|
|
|
|
Routing PW Street Lights | 9/10/2014 | | 9/11/2014 | | PASS |
Mike D Hedge
|
|
|
|
Plan resubmittals requested | | | 9/4/2014 | | DONE |
John Menard
|
|
|
E-mailed the applicant a copy of the structural review requesting revisions. JCM
|
Routing - PLAN CHECK | 8/25/2014 | | 9/4/2014 | | PASS |
John Menard
|
|
|
|
Routing PW Sewer Design | 8/25/2014 | | 9/2/2014 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing Off Site - STRUCTURAL | 8/25/2014 | | 9/2/2014 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 8/25/2014 | | 8/29/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 08-29-14
|
Routing PW Drainage | 8/25/2014 | | 8/27/2014 | | CANC |
Brian Murphy
|
|
|
Project approved under Permit BLD14-02138 (ODI-3324) JCT.
|
Routing PW Street Lights | 8/25/2014 | | 8/27/2014 | | FAIL |
Mike D Hedge
|
|
|
|
Routing - PUBLIC WORKS | 8/25/2014 | | 8/25/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLAN CHECK | 7/10/2014 | | 7/29/2014 | | FAIL |
John Menard
|
|
|
|
1st review completed | | | 7/28/2014 | | DONE |
John Menard
|
|
|
|
Routing - Design Review | 7/10/2014 | | 7/22/2014 | | PASS |
Josh Wilson
|
|
|
Ok per revised sheet L1.0 received 7-22-14
|
Routing - FIRE | 7/10/2014 | 7/10/2014 | 7/18/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 07-18-14
|
Routing Off Site - STRUCTURAL | 7/10/2014 | | 7/18/2014 | | FAIL |
John Menard
|
|
|
|
Routing PW Sewer Design | 7/10/2014 | | 7/17/2014 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Utilize existing 8" sewer stub if possible. If not:
Contact April Wing at Boise Public Works to obtain manhole number for new public manhole. New manhole required to have a precast base per SD-501A. Contact Public Works 48 hours prior to sewer work in public R/W and obtain tap permit. Existing sewer line must be Re-CCTV'd up and down stream of new manhole and video submitted to Boise Public Works. Show all inverts for SSMH#1, match crowns of different sized pipe.
|
Routing PW Drainage | 7/10/2014 | | 7/15/2014 | | FAIL |
Brian Murphy
|
|
|
roof bld 3 , no no construction note
|
Routing PW Solid Waste | 7/10/2014 | | 7/14/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Environmental | 7/10/2014 | | 7/14/2014 | | PASS |
Rick Christenson
|
|
|
|
Route to Impact Fee Review | 7/10/2014 | 7/15/2014 | 7/11/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING Land Div | 7/10/2014 | | 7/11/2014 | | PASS |
Dave Abo
|
|
|
|
Routing - Addressing | 7/10/2014 | | 7/10/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 7/10/2014 | | 7/10/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 7/10/2014 | | 7/10/2014 | | PASS |
Evan Jenkins
|
|
|
|
Routing PW Street Lights | 7/10/2014 | | 7/10/2014 | | FAIL |
Mike D Hedge
|
|
|
Required street lighting missing from drawings.
|
Routing - PLUMBING | 7/10/2014 | | 7/10/2014 | | PASS |
Daryl Spivey
|
|
|
3" min. vent through roof
|
Intake Approval | | | 7/10/2014 | | PASS |
John Menard
|
|
|
|
Pending Assignment by JCM | 7/10/2014 | | 7/10/2014 | | DONE |
John Menard
|
|
|
|
Routing PW Sewer Rating | 7/10/2014 | | 7/10/2014 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 6/30/2014 | | FAIL |
|
|
|
(6-30-14) More information required. Refer to the circled items on the plan intake checklist. CJW
|
Application received | | | 6/16/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 16 2014 1:11PM
|