Permit Information
Permit NumberBLD14-01680
StatusFinaled
Name THE RUSSELL CORPORATION
Site Address 8455 W WESTPARK ST
Project Name 
Customer Number 
ePlanReviewYes
Description
(DEMOLITION FOR WARHOUSE DIVISION - NO TENANT) Fire sprinklers used for building area increase. To perform interior non-structural demolition, to demolish interior mezzanines in their entirety, and to demolish an enclosed link between two portions of the building in its entirety. Interior demolition work includes removing a suspended acoustical ceiling grid and the removal of an access floor structure. The work is being done to prepare for dividing this building by a property line so that the separate buildings can be sold to different owners. Fire-resistance-rated fire walls, party walls, and property line walls will be created under a future permit. New work is not authorized under this permit. This permit does not establish a Certificate of Occupancy for any tenant. The fire sprinkler system is required to be maintained operational and compliant as required by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice1/15/20161/15/20162/12/2016 DONE
DetailsMike Jordan
demo work only for future TI's
BLD-Final1/14/20161/15/20161/15/2016PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Bob Thornton
DOC - Permit Finaled1/15/20161/15/20161/15/2016PPASS
DetailsMike Jordan
FIRE-Final Inspection1/14/20161/15/20161/15/2016APASS
DetailsTroy Cobbley
Life safety passed
BLD-Final2/7/20152/9/20152/9/2015PNR
DetailsMike Jordan
Final out the demo permit. Please call when you are on your way. Phone #: ###-#### Inspection requested via web by Bob Thornton
FIRE-Final Inspection2/7/20152/9/20152/9/2015ACANC
DetailsTroy Cobbley
Wrong permit scheduled
OVERRIDE  7/17/2014  
Issue PAID IN FULL permit  7/17/2014 DONE
DetailsBarbara Stitt
Inspection Record Card- Bld  7/17/2014 DONE
DetailsBarbara Stitt
Permit Ready to Issue  7/17/2014 DONE
DetailsBarbara Stitt
Plan assigned to (CJW)6/24/20146/24/20147/15/2014 PASS
DetailsCarl Westfall
DEMOLITION FOR WAREHOUSE DIVISION - NO TENANT - Level 3 TI - ePlanReview - (15 days - July 14)
Routing - Erosion and Sediment7/15/2014 7/15/2014 PASS
DetailsAndy J. Long
ESC plan and narrative submitted. Valid RP and PD designated.
PLANS/APPL TAKEN TO FRONT DESK  7/15/2014 PASS
DetailsJason Blais
For Carl Westfall.
1st review completed  7/11/2014 FAIL
failed ESC
Routing - PLAN CHECK6/24/2014 7/11/2014 PASS
DetailsCarl Westfall
Routing - FIRE6/24/20146/24/20146/30/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review 06-30-14
Routing - Design Review6/24/2014 6/26/2014 PASS
DetailsSarah Schafer
Sarah Schafer - Partial exterior demo of link on north side
Routing - Erosion and Sediment6/24/2014 6/25/2014 FAIL
DetailsAndy J. Long
No ESC plan waiver submitted in ePlan documents as stated in the TI checklist. Requested resubmittal.
Routing - Addressing6/24/2014 6/25/2014 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS6/24/2014 6/25/2014 PASS
DetailsBeverly Mountain
Intake Approval  6/24/2014 PASS
DetailsJason Blais
Prescreen approved by Tim Woodard on 6/18/14. Plan review fees paid on 6/24/14.
Pending Assignment by JCB6/24/2014 6/24/2014 DONE
DetailsJason Blais
Application received  6/17/2014 DONE
Application submitted via PDS Online on Jun 17 2014 3:04PM