First Notice | 8/29/2014 | 9/8/2014 | 10/6/2014 | | DONE |
Phil Shearer
|
|
|
mailed 10-7-14
|
BLD-Final | 8/27/2014 | 8/29/2014 | 8/29/2014 | P | PASS |
Phil Shearer
|
|
|
Chris Phone #: ###-####
|
DOC - Permit Finaled | 8/29/2014 | 8/29/2014 | 8/29/2014 | P | PASS |
Phil Shearer
|
|
|
|
FIRE-Final Inspection | 8/29/2014 | 8/29/2014 | 8/29/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Permanent Occupancy | | | 8/29/2014 | | DONE |
Candy A. Nichols
|
|
|
|
FIRE-Final Inspection | 8/27/2014 | 8/28/2014 | 8/28/2014 | A | FAIL |
Troy Cobbley
|
|
|
Finish installing the exit signs/emergency lights and test, provide sticker at the keyed exit, mount and tag fire extinguishers as discussed and install all door hardware for ADA compliance verification
|
BLD-Ceiling Grid Inspection | 8/26/2014 | 8/27/2014 | 8/27/2014 | A | PASS |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|
Issue & PRINT permit | | | 8/26/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Print Occupancy Form | | | 8/26/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Routing - PLAN CHECK | 8/12/2014 | | 8/12/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
plan modification 1 hour
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/12/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/12/2014 | | DONE |
Tisha Gallop
|
|
|
plan mod approved and batch stamped, fee due.
|
BLD-Framing/Rough-in | 8/6/2014 | 8/8/2014 | 8/8/2014 | P | CANC |
Mike Jordan
|
|
|
Phone #: 2088699235 >> Inspection requested via mobile web by Chris Downey
|
BLD-Framing/Rough-in | 8/5/2014 | 8/8/2014 | 8/8/2014 | A | PART |
Mike Jordan
|
|
|
Phone #: 2088699235 >> Inspection requested via mobile web by Chris Downey. Interior steel stud framed walls only. No grid. pending electrical rough in inspection. Also noted the owner wants to split off the office portion for a state farm office, which would need a seperate permit. Contractor noted that the owner has been in contact with the city to work through the issues. Contacted plan reviewer, waiting for call back, to see if they are aware of the issues.
|
CHANGE ISSUED DATE | | | 7/28/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/28/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 7/28/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 7/28/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 6/26/2014 | 6/26/2014 | 7/24/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 7/9 Dirty Paw
|
Routing - PLAN CHECK | 7/17/2014 | | 7/24/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2014 | | DONE |
|
|
|
|
Routing - PLUMBING | 7/17/2014 | | 7/21/2014 | | PASS |
Bill VanDegrift
|
|
|
additional cross connection protection may be required.
|
Routing - Erosion and Sediment | 7/17/2014 | | 7/17/2014 | | PASS |
Andy J. Long
|
|
|
Minor interior TI, no excavation or change in building footprint. No ESC necessary.
|
Routing - MECHANICAL | 7/17/2014 | | 7/17/2014 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 7/3/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 6/26/2014 | | 7/3/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLUMBING | 6/26/2014 | | 6/30/2014 | | FAIL |
Bill VanDegrift
|
|
|
engineered plans required for the plumbing system
|
Routing - PLANNING | 6/30/2014 | | 6/30/2014 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 6/26/2014 | | 6/26/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 6/26/2014 | | 6/26/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 6/26/2014 | | 6/26/2014 | | CANC |
|
|
|
No Review Necessary
|
Routing - MECHANICAL | 6/26/2014 | | 6/26/2014 | | FAIL |
Troy James
|
|
|
eplan
|
Intake Approval | | | 6/26/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 6/19/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 19 2014 12:00PM
|