BLD-Aging Inspection | 1/29/2016 | 1/29/2016 | 2/1/2016 | | PEND |
Dave Hannah
|
|
|
|
BLD-Final | 9/16/2015 | 9/17/2015 | 9/17/2015 | P | PART |
Jim Storey
|
|
|
would like call ahead; Jeff Phone #: ###-#### up stair area ok
|
BLD-Framing/Rough-in | 3/10/2015 | 3/10/2015 | 3/10/2015 | A | PASS |
Dave Hannah
|
|
|
upstairs only // Wayne Phone #: ###-####
|
BLD-Framing/Rough-in | 3/6/2015 | 3/9/2015 | 3/10/2015 | P | DEFR |
Dave Hannah
|
|
|
upstairs only // Wayne Phone #: ###-####
|
Routing - MECHANICAL | 2/20/2015 | | 2/20/2015 | | PASS |
Troy James
|
|
|
|
BLD-Framing/Rough-in | 1/27/2015 | 1/27/2015 | 1/28/2015 | P | PART |
Dave Hannah
|
|
|
Wayne Phone #: ###-#### ok to insulate rim in basement only
|
BLD-Footing | 11/3/2014 | 11/4/2014 | 11/4/2014 | A | PASS |
Dave Hannah
|
|
|
Andy Phone #: ###-####
|
BLD-Foundation | 9/26/2014 | 9/29/2014 | 9/29/2014 | A | PASS |
Dave Hannah
|
|
|
Andy Phone #: ###-####
|
OVERRIDE | | | 9/24/2014 | | |
|
|
|
|
Routing Walk-In (BLD) | 9/24/2014 | 9/24/2014 | 9/24/2014 | A | DONE |
Perry Paine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2014 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/24/2014 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/24/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 9/24/2014 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 9/24/2014 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/24/2014 | | DONE |
Christina Prado
|
|
|
|
Routing Walk-In (BLD) | 9/23/2014 | 9/23/2014 | 9/23/2014 | P | PASS |
Javier Guzman
|
|
|
applicant Mr. Swanson brought in floor plans for Perry
|
BLD-Footing | 9/18/2014 | 9/19/2014 | 9/19/2014 | A | PASS |
Dave Hannah
|
|
|
early - Andy Phone #: ###-####
|
Routing Walk-In (BLD) | 9/18/2014 | 9/18/2014 | 9/18/2014 | A | PASS |
Perry Paine
|
|
|
accepted resubmitted engineering for a10" basement wall from the original 12 inches
|
OVERRIDE | | | 7/16/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/16/2014 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 7/16/2014 | | DONE |
Christina Prado
|
|
|
called Wayne to advise permit is ready for pick up pending RP recert., bond of $8600, sewer cap, liability ins & bond worksheet filled out and gave fees due
|
Permit Ready to Issue | | | 7/16/2014 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/15/2014 | | DONE |
|
|
|
ok to issue at recpt. of bond
|
Inspection Record Card- Bld | | | 7/8/2014 | | |
|
|
|
|
Routing Walk-In (BLD) | 7/2/2014 | 7/2/2014 | 7/2/2014 | P | CANC |
Perry Paine
|
|
|
working on review while applicant is procuring bond.
|
Routing Walk-In (Zoning) | 6/23/2014 | 6/23/2014 | 6/23/2014 | P | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 6/23/2014 | 6/23/2014 | 6/23/2014 | P | FAIL |
Javier Guzman
|
|
|
Need engineering of the basement wall
|
1st review completed | | | 6/23/2014 | | FAIL |
Javier Guzman
|
|
|
|
Application received | | 6/23/2014 | | | |
|
|
|
|