BLD-Final | 7/26/2017 | 7/26/2017 | 7/26/2017 | P | PASS |
Mike Jordan
|
|
|
Ted Phone #: ###-####
|
DOC - Permit Finaled | 7/26/2017 | 7/26/2017 | 7/26/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 7/10/2017 | 7/10/2017 | 7/10/2017 | P | NR |
Mike Jordan
|
|
|
Ted Phone #: ###-####. Needs to install handrail.
|
BLD-Framing/Rough-in | 7/10/2017 | 7/10/2017 | 7/10/2017 | P | PASS |
Mike Jordan
|
|
|
Ted Phone #: ###-####
|
BLD-Footing | 5/25/2017 | 5/25/2017 | 5/25/2017 | P | PASS |
Mike Jordan
|
|
|
footing insp for deck // Ted Mason Phone #: ###-####
|
Change Expiration Date Only | | | 5/22/2017 | | DONE |
Jason Blais
|
|
|
|
BLD - Request for Extension | 5/18/2017 | 5/18/2017 | 5/18/2017 | P | PEND |
Mike Jordan
|
|
|
Ted Mason Phone #: ###-####. Called and left message for Ted. Noted that he needs to send a letter to B.O. for extension request.
|
BLD-Framing/Rough-in | 12/5/2016 | 12/5/2016 | 12/5/2016 | P | CANC |
Mike Jordan
|
|
|
would like call ahead; Ted Phone #: ###-####
|
BLD-Final | 12/5/2016 | 12/5/2016 | 12/5/2016 | P | PART |
Mike Jordan
|
|
|
would like call ahead; Ted Phone #: ###-####. Addition is completed and is ok. Needs to complete exterior 2nd. floor deck. Per homeowner should begin this spring.
|
BLD-Conference | 7/8/2016 | 7/11/2016 | 7/11/2016 | P | PASS |
Phil Shearer
|
|
|
Ted Phone #: ###-####
|
BLD-Conference | 9/29/2015 | 9/29/2015 | 9/29/2015 | P | PASS |
Jim Sly
|
|
|
Ted (husband) Phone #: ###-####
|
BLD-Conference | 6/11/2015 | 6/12/2015 | 6/12/2015 | A | DONE |
Jim Sly
|
|
|
Ted Phone #: ###-#### WIP
|
BLD-Framing/Rough-in | 12/12/2014 | 12/15/2014 | 12/15/2014 | P | PASS |
Jim Sly
|
|
|
Ted Phone #: ###-####
|
BLD-Other | 9/10/2014 | 9/11/2014 | 9/11/2014 | A | PART |
Jim Sly
|
|
|
Rob- rebar insp Phone #: ###-#### First story..........OK
|
BLD-Framing/Rough-in | 8/21/2014 | 8/21/2014 | 8/22/2014 | P | CANC |
Dave Hannah
|
|
|
Ted Mason Phone #: ###-####
|
BLD-Framing/Rough-in | 8/22/2014 | 8/22/2014 | 8/22/2014 | A | PART |
Jim Sly
|
|
|
Ted Mason Phone #: ###-#### please call befor Continuing inspection on concrete wall system.
|
Routing - MECHANICAL | 8/8/2014 | | 8/8/2014 | | PASS |
Troy James
|
|
|
resubmitted acca report
|
BLD-Foundation | 8/6/2014 | 8/7/2014 | 8/7/2014 | A | PASS |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 8/5/2014 | 8/5/2014 | 8/5/2014 | P | PASS |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/3/2014 | | DONE |
Barbara Stitt
|
|
|
|
OVERRIDE | | | 7/2/2014 | | |
|
|
|
|
Plan assigned to (PEP) | 6/30/2014 | 6/30/2014 | 7/2/2014 | | PASS |
Perry Paine
|
|
|
|
1st review completed | | | 7/2/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/2/2014 | | |
|
|
|
|
Telephone call | | | 7/2/2014 | | DONE |
Christina Prado
|
|
|
called Ted to advise permit is ready for pick up and gave fees due
|
Permit Ready to Issue | | | 7/2/2014 | | DONE |
Christina Prado
|
|
|
|
Routing Walk-In (BLD) | 6/25/2014 | 6/25/2014 | 7/1/2014 | A | FAIL |
Javier Guzman
|
|
|
need ACCA
|
Routing - MECHANICAL | 7/1/2014 | | 7/1/2014 | | PASS |
Troy James
|
|
|
|
Routing Walk-In (Zoning) | 6/25/2014 | 6/25/2014 | 6/25/2014 | A | DONE |
Sue Cummings
|
|
|
|
Application received | | 6/25/2014 | | | |
|
|
|
|