Permanent Occupancy | | | 7/25/2014 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 7/15/2014 | 7/16/2014 | 7/16/2014 | A | PASS |
Jim Sly
|
|
|
Taylor Phone #: ###-####
|
FIRE-Final Inspection | 7/15/2014 | 7/16/2014 | 7/16/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Replacement main exit hardware is still incorrect. I'm deferring it to the building inspector to verify at building final.
|
FIRE-Final Inspection | 7/8/2014 | 7/9/2014 | 7/9/2014 | A | FAIL |
Forrest France
|
|
|
Provide approved door hardware at the main entry/exit per discussion, post and provide current certification for the fire extinguisher. Refer to permit documents items number 2 and 4 for details.
|
Issue PAID IN FULL permit | | | 7/8/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 7/1/2014 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 7/1/2014 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 7/1/2014 | | DONE |
Tisha Gallop
|
|
|
Called Taylor Jensen and left vm permit is ready for pick up.
|
Plan assigned to (CDM) | 6/26/2014 | 6/26/2014 | 6/30/2014 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/26/2014 | | 6/30/2014 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 6/30/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/2014 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/30/2014 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/26/2014 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | 6/25/2014 | 6/25/2014 | | DONE |
Barbara Stitt
|
|
|
|
First Notice | | 8/4/2014 | | | |
|
|
|
|