Information based on query as of Saturday, June 22, 2024.
Permit Information
Permit NumberBLD14-01818
StatusFinaled
Name ESI
Site Address 501 E PARKCENTER BLVD
Project NameThe District at Parkcenter
Customer NumberBLD14-01818 - BLD14-01832
ePlanReviewYes
Description
(THE DISTRICT AT PARKCENTER - CLUB BUILDING) (TOTAL OF 15 PERMITS ARE ASSOCIATED WITH THE DRAWINGS FILED UNDER THIS PERMIT IN EPLANREVIEW) (11-4-16 PLAN MODIFICATION TO ELIMINATE WHAT WAS CALLED A 2-HR FIRE WALL IN THE CLUB BUILDING AND TO PROVIDE A NON-RATED WALL INSTEAD.) (10-11-16 PLAN MODIFICATION TO RELOCATE THE ATTIC ACCESS HATCHES FOR THE IN-TOWN BUILDINGS TO THE WALLS OF THE MECHANICAL ACCESS SHAFTS, TO CREATE A BIKE STORAGE ROOM, TO CREATE A BIKE MAINTENANCE ROOM, ETC.) (9-6-16 PLAN MODIFICATION TO INSTALL FOUR (4) PULL-DOWN ATTIC ACCESS DOORS WITH LADDERS IN THE CORRIDOR CEILINGS ON THE 3RD STORY OF THE INTOWN BUILDINGS TO PROVIDE ACCESS TO THE ROOF TOP MECHANICAL EQUIPMENT. SINCE THE ACCESS "SHAFT" MAINTAINS THE CEILING MEMBRANE OF THE 1-HR ROOF-CEILING ASSEMBLY, THE DOORS ARE NOT REQUIRED TO BE TESTED IN ACCORDANCE WITH ASTM E119 OR UL 263 AS A 1-HR HORIZONTAL ASSEMBLY.) (8-9-16 PLAN MODIFICATION TO TURN THE FORMER JANITOR’S CLOSET IN THE FITNESS BUILDING TO A POOL EQUIPMENT ROOM WITH DIRECT ACCESS FROM THE OUTSIDE. A STORAGE ROOM WILL BE CHANGED TO A JANITOR’S CLOSET WITH A SERVICE SINK. DRAWINGS WERE REVISED TO BE COMPATIBLE WITH THE DRAWINGS APPROVED UNDER THE SWIMMING POOL PERMIT. FOR THE CLUB BUILDING, SCUPPERS WERE REPLACED WITH ROOF PRIMARY DRAINS AND OVERFLOW DRAINS.) (3-4-16 DEFERRED SUBMITTAL OF GLU-LAM BEAM AND COLUMN DESIGN SUBMITTED) (12-14-15 PLAN MODIFICATION TO MODIFY THE STRUCTURAL DESIGN OF THE EXTERIOR WALL PARAPETS OF THE CLUB BUILDING.) This building does NOT have a fire sprinkler system. To construct a new 3,969 square foot one story building to be used as a club building for the apartment occupants on this site. Work is to include 2 restrooms accessible to the disabled, “high” and “low” drinking fountains, interior nonbearing walls, interior windows and doors, exterior windows and doors, insulated exterior walls, exterior siding, exterior manufactured stone, standing seam metal roof coverings, single ply roof coverings, continuous foam plastic insulation installed on top of the roof decks, suspended gypsum board ceilings, millwork, and finishes. Structural work includes concrete footings, concrete stem walls, concrete floor slabs on grade with thickened footings at interior bearing walls, glu-lam beams, glu-lam columns, roof trusses, roof joists, bearing walls, wood columns, wood beams, and shear walls. Special inspection is required for soils, concrete, and wood. A separate permit is required for the swimming pool and the barrier around it. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 5/20/20176/13/2017 DONE
sent in mail 6-14-17
First Notice 4/16/20175/10/2017 DONE
sent in mail 5-11-17
BLD-Final4/5/20174/6/20174/6/2017APASS
DetailsJim Storey
Matt ###-####
Permanent Occupancy  4/6/2017 DONE
BLD-Final3/30/20173/31/20174/5/2017ADEFR
DetailsJim Storey
Matt ###-####
Zoning Approval4/3/20174/3/20174/3/2017 PASS
DetailsSarah Schafer
BLD-Final3/22/20173/30/20173/31/2017PDEFR
DetailsJim Storey
Matt ###-####
Telephone call  3/30/2017 DONE
emailed Sarah Schafer-customer says she did the inspection but there is nothing in Tidemark-i asked her to sign off if the inspection passed
FIRE-Final Inspection3/22/20173/29/20173/29/2017APASS
DetailsJim Page
Exit discharge to pool area is complete, final life fire safety inspection passed/complete.
PubWorks Occupancy Approval3/14/20173/14/20173/14/2017 DONE
DetailsTiffany Lowery
BLD-Framing/Rough-in3/6/20173/7/20173/7/2017APASS
DetailsJim Storey
Corey Phone #: ###-####
Temporary Occupancy1/31/20175/1/20171/31/2017 DONE
DetailsKristal Soland
CHANGE STATUS TO (ISS)  1/31/2017 DONE
FIRE-Final Inspection1/26/20171/30/20171/30/2017ACANC
DetailsJim Page
BLD-Final1/24/20171/27/20171/27/2017APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Corey Hockersmith
FIRE-Conference1/25/20171/26/20171/26/2017PDONE
DetailsJim Page
Fire conference complete
FIRE-Final Inspection1/18/20171/20/20171/20/2017APART
DetailsJim Page
Partial final inspection for life fire safety complete, no fire sprinklers, fire alarm inspection is complete, fire extinguishers are in place with current inspection tags, knox box will be mounted in discussed location. Life safety will not be completed until pool area is complete and the life safety inspection for that permit is complete.
FIRE-Conference1/13/20171/13/20171/13/2017PDONE
DetailsJim Page
Fire conference complete
OVERRIDE  11/7/2016  
CHANGE STATUS TO (ISS)  11/7/2016 DONE
Plan Mod
(F) Reprint permit  11/7/2016 DONE
Permit Ready to Issue  11/7/2016 DONE
DO NOT RE ISSUE PLAN MOD
Plan assigned to (CJW)11/3/201611/3/201611/4/2016 PASS
DetailsCarl Westfall
Routing - PLAN CHECK11/3/2016 11/4/2016 PASS
DetailsCarl Westfall
Plan mod completed - no charge)
PLANS/APPL TAKEN TO FRONT DESK  11/4/2016 DONE
Plan mod completed - no charge
Plan Modification Accepted  11/3/2016 DONE
plan mod accepted in e plan
BLD-Wall cover10/25/201610/26/201610/26/2016APASS
DetailsJim Storey
Insulation inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith truss with in 6 inches bearing aproved by truss mfg.
BLD-Framing/Rough-in10/20/201610/21/201610/21/2016APART
DetailsJim Storey
Club House Framing Phone #: ###-#### Inspection requested via web by Corey Hockersmith truss bearing at restarm/ header at hvac duct/ ok to insulate
BLD-Framing/Rough-in10/20/201610/20/201610/20/2016PNR
DetailsJim Storey
Club House Framing Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Framing/Rough-in10/17/201610/18/201610/18/2016AFAIL
DetailsJim Storey
Club House Framing Phone #: ###-#### Inspection requested via web by Corey Hockersmith c/n
(F) Reprint permit  10/17/2016 DONE
CHANGE STATUS TO (ISS)  10/17/2016 DONE
OVERRIDE  10/12/2016  
Permit Ready to Issue  10/12/2016 DONE
PLAN MOD DO NOT RE-ISSUE
Plan assigned to (CJW)10/7/201610/7/201610/11/2016 PASS
DetailsCarl Westfall
Plan Modification Accepted  10/11/2016 DONE
Upload completed
Routing - PLAN CHECK10/11/2016 10/11/2016 PASS
DetailsCarl Westfall
7th plan mod approved
PLANS/APPL TAKEN TO FRONT DESK  10/11/2016 DONE
Plan Reviewer's activity  10/10/2016 DONE
Jamie had not uploaded all revised drawings. Returned the workflow back to him so that he could finish.
CHANGE STATUS TO (ISS)  10/7/2016 DONE
(F) Reprint permit  10/7/2016 DONE
Plan Modification Accepted  10/7/2016 DONE
Plan modification as requested by Architect, I have several ASI’s I’m uploading this morning. These represent changes the owner requested as well as changes due to inspector comments.
The last couple of drawings I uploaded for review were the changes to the Club House and the pull down rated attic stair in all In-Town Buildings.
This next set of changes have to do with…

Final coordination with electrical and pool design. (minor changes to coordinate electrical switches, outlets, etc… from our electrical drawings and the final approved pool drawings)

Bike storage and maintenance rooms. (This was added by the owner as another amenity for the residence, since the clientele is going to be the young, active, outdoors type. We are playing “catch up” with the drawings.)

Lighting package. (Our Electrical drawings updated their fixture schedule to match the lighting fixtures selected and installed by the Interior Designer.)

Mechanical corrections. (Transfer grills were added in all bedrooms, fire damper was added at mechanical room at the In-Town corridors per inspector’s comments. Our mechanical drawings have been updated.)

Attic Hatch Change. (Per our discussion a few days ago, we are locating the rated attic access hatch into the wall of the flat roof access way)
OVERRIDE  9/7/2016  
Permit Ready to Issue  9/7/2016 DONE
plan mod fees due - DO NOT RE-ISSUE
Plan assigned to (CJW)8/29/20168/29/20169/6/2016 PASS
DetailsCarl Westfall
Routing - PLAN CHECK8/29/2016 9/6/2016 PASS
DetailsCarl Westfall
6th plan mod
Routing - MECHANICAL8/31/2016 9/6/2016 PASS
DetailsTroy James
Routing PW Drainage9/6/2016 9/6/2016 PASS
DetailsBrian Murphy
Looks like a change to the storm water
Routing - PUBLIC WORKS9/6/2016 9/6/2016 PASS
DetailsRachael Beierle
For drainage to review plan mod
PLANS/APPL TAKEN TO FRONT DESK  9/6/2016 DONE
Routing - Design Review8/31/2016 9/1/2016 PASS
DetailsSarah Schafer
Plan Modification Accepted  8/29/2016 DONE
DetailsChristina Prado
changes from the last couple of weeks, parts of ASI 55, 56, and 57.
The last ASI 57 is very critical, sheets A3.4, A3.5 and A6.5 have a new detail for a rated pull-down attic access ladder as required by the mechanical inspector. This is critical for receiving a TCO.
CHANGE STATUS TO (ISS)  8/16/2016 DONE
Plan Mod
(F) Reprint permit  8/16/2016 DONE
OVERRIDE  8/9/2016  
Plan assigned to (CJW)7/27/20167/27/20168/9/2016 PASS
DetailsCarl Westfall
Routing - PLAN CHECK8/1/2016 8/9/2016 PASS
DetailsCarl Westfall
PLANS/APPL TAKEN TO FRONT DESK  8/9/2016 DONE
Permit Ready to Issue  8/9/2016 DONE
plan mod fees due - DO NOT RE-ISSUE
Routing - PLUMBING8/1/2016 8/2/2016 PASS
DetailsDaryl Spivey
vent required on sink trap
Plan Modification Accepted  7/27/2016 DONE
DetailsChristina Prado
As requested by Jamie to update pluming shhets to match pool submittal
(F) Reprint permit  7/11/2016 DONE
CHANGE STATUS TO (ISS)  7/11/2016 DONE
plan mod fees paid
OVERRIDE  7/5/2016  
PLANS/APPL TAKEN TO FRONT DESK  7/5/2016 DONE
Permit Ready to Issue  7/5/2016 DONE
DetailsChristina Prado
Plan Mod fees due, DO NOT RE-ISSUE
Plan assigned to (CJW)5/16/2016 7/5/2016 PASS
DetailsCarl Westfall
(May 24 - 5 days) plan mod
Routing Off Site - STRUCTURAL6/28/2016 7/1/2016 PASS
DetailsCarl Westfall
(Jan Welch was the Consultant Structural Engineer) A plan mod was submitted to create a large opening in the exterior wall between the swimming pool and the club building. Sliding door panels were to be placed in the large opening. Drawings for the structural changes were reviewed by the Consultant Structural Engineer and by the IBC Plans Examiner and the required corrections were noted. It was determined that doors in a pool enclosure are requried to be self closing and self latching. The exterior wall between the club building and the swimming pool was determined to be part of the pool enclosure. Since the sliding wall panels were not allowed, the design went back to what was originally approved. CJW
Plan resubmittals received  6/28/2016 DONE
Overhead doors and sliding doors were not allowed in the building exterior walls between the building and the swimming pool. Such exterior walls are part of the pool enclosure and doors must be self-closing and self-latching. Design reverted back to the original.
Routing - PLAN CHECK6/28/2016 6/28/2016 PASS
DetailsCarl Westfall
Overhead doors and sliding doors were not allowed in the building exterior walls between the building and the swimming pool. Such exterior walls are part of the pool enclosure and doors must be self-closing and self-latching. Design changed back to the original.
Routing - PLAN CHECK5/17/2016 6/6/2016 FAIL
DetailsCarl Westfall
Provide self-closing and self-latching doors in the pool enclosure that is also the building exterior wall located between the buildings and the pool.
Plan resubmittals requested  6/6/2016 DONE
Routing Off Site - STRUCTURAL5/18/2016 5/25/2016 FAIL
DetailsCarl Westfall
Routing - Design Review5/18/2016 5/19/2016 PASS
DetailsSarah Schafer
Plan Modification Accepted  5/17/2016 DONE
Workflow in ePlanReview received
Plan Modification Accepted  5/16/2016 DONE
DetailsChristina Prado
For structural updates to the Clubhouse, to create a new opening onto pool.
OVERRIDE  3/4/2016  
CHANGE STATUS TO (ISS)  3/4/2016 DONE
DetailsChristina Prado
Deferred submittal approved, plans changes to ISS status
Routing - PLAN CHECK2/29/2016 3/4/2016 PASS
DetailsCarl Westfall
(3-1-16) Applicant asked that the plan modification review be on hold until further notice.
(3-3-16) Structural calculations to support the glu-lam beam and colum design were requested via Email.
(3-4-16) Turned out to be a deferred submittal for the glu-lam beam and column design at the clubhouse and fitness buildings. Application approved.
PLANS/APPL TAKEN TO FRONT DESK  3/4/2016 DONE
Permit Ready to Issue  3/4/2016 DONE
DetailsChristina Prado
Deferred submittal approved, plans changes to ISS status
Plan assigned to (CJW)2/29/2016 3/4/2016 PASS
DetailsCarl Westfall
Plan Mod.
Plan Modification Accepted  3/2/2016 DONE
Revised sheets uploaded and now ready for routing
Plan Modification Accepted  2/29/2016 DONE
Workflow in ePlanReview received
Plan Modification Accepted  2/23/2016 DONE
started workflow
BLD-Aging Inspection2/16/20162/16/20162/16/2016 NR
DetailsJim Storey
BLD-Aging Inspection2/15/20162/15/20162/16/2016 NR
DetailsJim Storey
CHANGE STATUS TO (ISS)  1/20/2016 DONE
all fees paid
(F) Reprint permit  1/20/2016 DONE
OVERRIDE  12/14/2015  
Routing - PLAN CHECK11/20/2015 12/14/2015 PASS
DetailsCarl Westfall
Routing completed
Plan assigned to (CJW)11/17/2015 12/14/2015 PASS
DetailsCarl Westfall
PLANS/APPL TAKEN TO FRONT DESK  12/14/2015 DONE
Permit Ready to Issue  12/14/2015 DONE
DetailsChristina Prado
DO NOT RE-ISSUE!!!!

Plan Mod only
Routing Off Site - STRUCTURAL11/20/2015 12/11/2015 PASS
DetailsCarl Westfall
Jan Welch
Plan Modification Accepted  11/17/2015 DONE
The 3 structural sheets would not load properly. Something wrong with the files. Spent a lot of time trying to figure out how to get them to load.
BLD-Conference10/23/201510/23/201510/23/2015APASS
DetailsJim Storey
CHANGE STATUS TO (ISS)  9/2/2015 DONE
OVERRIDE  8/25/2015  
Plan assigned to (CJW)8/21/20158/21/20158/25/2015 PASS
DetailsCarl Westfall
Plan Mod - ePlanReview - The District Club Building
Routing - PLAN CHECK8/21/2015 8/25/2015 PASS
DetailsCarl Westfall
Drawings not versioned correctly and oriented wrong.

(8-25-15) Plan modification to provide exterior expanded polystyrene foundation insulation in compliance with shallow foundation standards at locations where the bottom of the footings will be less than 24 inches below finished grade. The intent is to prevent frost heave. The plan mod only involved the following buildings:

Intown Building A - #1 (537 E. Parkcenter Blvd.) (BLD14-01826 / BLD14-01827)
Intown Building A - #2 (509 E. Parkcenter Blvd.) (BLD14-01828 / BLD14-01829)
Intown Building B - #1 (533 E. Parkcenter Blvd.) (BLD14-01830 / BLD14-01831)
PLANS/APPL TAKEN TO FRONT DESK  8/25/2015 DONE
Permit Ready to Issue  8/25/2015 DONE
plan mod fees need to be paid- DO NOT re-issue (6 other permits need status change along with this one; see attached)
Plan Modification Accepted  8/21/2015 DONE
DetailsChristina Prado
Per Jamie - Plan mod accepted for minor changes to footing details, perimiter insulation & civil elevations
Print Occupancy Form  4/2/2015 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  4/2/2015 DONE
OVERRIDE  4/1/2015  
Permit Ready to Issue  4/1/2015 DONE
need gc form, updated values, ACHD receipt, RP
Routing - PLAN CHECK2/25/2015 3/31/2015 PASS
DetailsCarl Westfall
All agencies approved
PLANS/APPL TAKEN TO FRONT DESK  3/31/2015 DONE
Plan assigned to (CJW)7/22/2014 3/31/2015 PASS
DetailsCarl Westfall
CLUB BUILDING (1st review done) (30 days - Sept 1)
Routing Off Site - STRUCTURAL2/26/2015 3/30/2015 PASS
DetailsCarl Westfall
Jan Welch
Routing PW Flood Plain2/26/2015 3/30/2015 PASS
DetailsJim Wyllie
Routing - MECHANICAL3/10/2015 3/10/2015 PASS
DetailsTroy James
Routing - MECHANICAL2/26/2015 2/27/2015 FAIL
DetailsTroy James
Troy
Routing - Design Review2/26/2015 2/27/2015 PASS
DetailsSarah Schafer
Sarah - Approved per DRH12-00038 and DRH15-00030.
Routing - PLAN CHECK2/25/2015 2/26/2015  
DetailsCarl Westfall
Fixed file names for correct versioning. Several needed to be fixed. Waiting for approval from Structural.
Plan resubmittals received  2/25/2015 DONE
Routing - PLAN CHECK1/23/2015 2/11/2015 FAIL
DetailsCarl Westfall
Failed structural
Routing Off Site - STRUCTURAL1/26/2015 2/11/2015 FAIL
DetailsCarl Westfall
Jan Welch
Plan resubmittals requested  2/11/2015 DONE
Routing - Design Review1/26/2015 1/30/2015 FAIL
DetailsSarah Schafer
Design Review Modification required. Applicant and their attorney have been notified.
Routing - MECHANICAL1/26/2015 1/27/2015 FAIL
DetailsTroy James
Routing - PLANNING1/26/2015 1/26/2015 PASS
DetailsCody Riddle
Plan resubmittals received  1/23/2015 DONE
Routing Off Site - STRUCTURAL12/9/2014 12/29/2014 FAIL
DetailsCarl Westfall
Jan Welch
Routing - PLAN CHECK12/13/2014 12/29/2014 FAIL
DetailsCarl Westfall
Waiting for the resolution of the structural issues.
Plan resubmittals requested  12/29/2014 DONE
DetailsCarl Westfall
Routing - PLAN CHECK12/9/2014 12/13/2014 PASS
DetailsCarl Westfall
For the building review, the structural issues have not been resolved.
Plan resubmittals received  12/11/2014 DONE
More revised drawings were Emailed to me. I uploaded them. The revisions appeared to be minor.
Routing - MECHANICAL12/9/2014 12/10/2014 FAIL
DetailsTroy James
Routing PW Street Lights12/9/2014 12/10/2014 PASS
DetailsMike D Hedge
Routing - Design Review12/9/2014 12/10/2014 FAIL
DetailsSarah Schafer
The elevations don't match those approved under the Design Review application. A modification must be processed for the building permit to move forward.
Routing - PLANNING12/9/2014 12/9/2014 FAIL
DetailsCody Riddle
One outstanding condition of approval:

Condition #22-The Army Corps required an updated wetland delineation. (We need final written approval from the Corps before we can issue the permit)

Emailed applicant today.
Plan resubmittals received  12/8/2014 DONE
Routing Off Site - STRUCTURAL10/22/2014 11/7/2014 FAIL
DetailsCarl Westfall
Jan Welch
Plan resubmittals requested  11/7/2014 DONE
Routing PW Drainage10/22/2014 10/29/2014 PASS
DetailsBrian Murphy
Routing - FIRE10/22/2014 10/28/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 1 10-28-14
Routing - PLAN CHECK10/16/2014 10/23/2014 FAIL
DetailsCarl Westfall
Some issues not resolved
Routing - Erosion and Sediment10/22/2014 10/22/2014 PASS
DetailsEvan Jenkins
(CLUB BUILDING) (TOTAL OF 15 PERMITS ARE ASSOCIATED WITH THE DRAWINGS FILED UNDER THIS PERMIT IN EPLANREVIEW) This building does NOT have a fire sprinkler system. To construct a new 3,969 square foot one story building to be used as a club building for the apartment occupants on this site. Work is to include 2 restrooms accessible to the disabled, “high” and “low” drinking fountains, interior nonbearing walls, interior windows and doors, exterior windows and doors, insulated exterior walls, exterior siding, exterior thin-cut stone, standing seam metal roof coverings, single ply roof coverings, continuous foam plastic insulation installed on top of the roof decks, suspended gypsum board ceilings, millwork, and finishes. Structural work includes concrete footings, concrete stem walls, concrete floor slabs on grade with thickened footings at interior bearing walls, glu-lam beams, glu-lam columns, roof trusses, roof joists, bearing walls, wood columns, wood beams, and shear walls. Special inspection is required for soils, concrete, and wood. A separate permit is required for the swimming pool and the barrier around it. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances.
Routing PW Street Lights10/22/2014 10/22/2014 FAIL
DetailsMike D Hedge
Street lights required, no lighting indicated on drawings.
Routing - Design Review10/22/2014 10/22/2014 FAIL
DetailsSarah Schafer
A design review modification is required. An e-mail has been sent to Taylor and copied to Chris Stephens with the requirements.
Routing - PLANNING10/22/2014 10/22/2014 FAIL
DetailsCody Riddle
Two outstanding issues with conditions of approval. Emailed applicant today;

Condition #15-All amenities shall be constructed or bonded for prior to issuance of building permits. (We need the bond before I can sign-off on the permit)

Condition #22-The Army Corps required an updated wetland delineation. (We need final written approval from the Corps before we can issue the permit)
Routing - MECHANICAL10/22/2014 10/22/2014 FAIL
DetailsTroy James
comments have not been addressed
Plan resubmittals received  10/16/2014 DONE
Significant issues with the resubmittal. Several hours spent getting the drawings ready to route.
Routing Off Site - STRUCTURAL7/22/2014 8/27/2014 FAIL
DetailsCarl Westfall
Since the submittal was incomplete, a structural review could not be done.
Routing - MECHANICAL8/11/2014 8/14/2014 FAIL
DetailsTroy James
Routing - FIRE7/22/2014 8/12/2014 FAIL
DetailsCraig D. Hanson
Fire Plan Review 08-12-14
1st review completed  8/5/2014 FAIL
Plan resubmittals requested  8/5/2014 DONE
Routing - PLAN CHECK7/22/2014 8/5/2014 FAIL
DetailsCarl Westfall
Revised drawings required
Route to Impact Fee Review7/22/20147/25/20148/1/2014 PASS
DetailsCindy M. Gould
No impact fees
Routing PW Drainage7/22/2014 7/29/2014 FAIL
DetailsBrian Murphy
need c 33 sand
Routing - PLUMBING7/22/2014 7/28/2014 PASS
DetailsDaryl Spivey
1) 120 degree max. hot water to public lavs.
2) bathroon ceiling plenum, use approved materials.
3) Change R.P.'s on water services to DCVA
4) all water services require a DCVA.
Routing - PLANNING7/22/2014 7/24/2014 FAIL
DetailsCody Riddle
Condition #6-A 4’ tall fence shall be installed on the south side of the access easement as it abuts the Logger’s creek riparian area…..(The fence is required on the west side of the bridge, up to the property line. This is not reflected on the plans.)

Condition #13-The plans do not identify 25% covered bicycle parking. (Perhaps these are located in the garages for the cottage buildings? This should be identified.)

Condition #15-All amenities shall be constructed or bonded for prior to issuance of building permits. (We need the bond before I can sign-off on the permit)

Condition #22-The Army Corps required an updated wetland delineation. (We need final written approval from the Corps before we can issue the permit)
Routing - Design Review7/22/2014 7/24/2014 FAIL
DetailsSarah Schafer
An administrative level Design Review modification is needed for the exterior changes to the buildings. The modification should also reflect compliance with the conditions of approval listed in the July 3, 2014 letter.
Routing - Addressing7/22/2014 7/24/2014 PASS
DetailsEmily Dixon
Routing PW Solid Waste7/22/2014 7/24/2014 PASS
DetailsPeter J. McCullough
Routing PW Sewer Design7/22/2014 7/24/2014 PASS
DetailsKyle S. Rosenmeyer
Private Sewer System
Routing PW Sewer Rating7/22/2014 7/23/2014 PASS
DetailsBeverly Mountain
Routing - Erosion and Sediment7/22/2014 7/23/2014 FAIL
DetailsEvan Jenkins
Full ESC Narrative Required
Routing PW Street Lights7/22/2014 7/23/2014 FAIL
DetailsMike D Hedge
No street lighting drawings submitted, street lights are required.
Routing - PLANNING Land Div7/22/2014 7/23/2014 PASS
DetailsDave Abo
Intake Approval  7/22/2014 PASS
DetailsJohn Menard
Pending Assignment by JCM7/22/2014 7/22/2014 DONE
DetailsJohn Menard
Routing - PUBLIC WORKS7/22/2014 7/22/2014 PASS
DetailsBeverly Mountain
Intake Approval  7/2/2014 FAIL
DetailsTim L. Woodard
Taylor,

Attached is the changes needed to your submittal prior to acceptance of the plans for review. All items circled on checklist need uploaded or revised. Please call with any questions.

Best regards,

Tim Woodard
Plans Examiner II / City of Boise
###-####
twoodard@cityofboise.org
Application received  6/30/2014 DONE
Application submitted via PDS Online on Jun 30 2014 6:44AM