Permit Information
Permit NumberBLD14-01819
StatusFinaled
Name ESI
Site Address 529 E PARKCENTER BLVD
Project NameThe District at Parkcenter
Customer NumberBLD14-01818 FOR DRAWNGS
ePlanReviewYes
Description
(THE DISTRICT AT PARKCENTER - COTTAGE BUILDING A - #1) (7-1-16 PLAN MODIFICATION TO RE-DESIGN THE STRUCTURAL SYSTEM FROM THE FOUNDATION UP. REVISED STRUCTURAL DRAWINGS ARE FILED UNDER BLD14-01819 IN EPLANREVIEW.) (The drawings are filed under permit BLD14-01818 in ePlanReview) To construct a 10 dwelling unit two story apartment building with each unit having its own garage (i.e. 10 garages). The total floor area of this building is about 14,708 square feet (8,374 square feet 1st story and 6,334 square feet 2nd story). All ground floor units are required to comply as Type B units. Two of those ground floor units within Cottage Building A - #2 are required to comply as Type A units. Work is to include interior nonbearing walls, 1-hr bearing walls, 1-hr roof-ceiling assemblies, 1-hr floor-ceiling assemblies, 1-hr dwelling unit separations, attic insulation, interior doors, exterior windows and doors, insulated exterior walls, “Hardi-board” exterior siding, exterior manufactured stone wainscot, composition roof shingles, common stairways within a 1-hr corridor, private interior stairways, garages, garage overhead doors, millwork, and finishes. Structural work includes concrete footings, concrete stem walls, concrete floor slabs on grade with thickened footings at interior bearing walls, wood floor trusses, wood roof trusses, wood columns, wood beams, and shear walls. Special inspection is required for soils, concrete, and wood. The designs for the roof trusses and floor trusses are deferred submittal items. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13R as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Zoning Approval1/31/20171/31/20171/31/2017 DONE
DetailsSarah Schafer
Permanent Occupancy  1/31/2017 DONE
BLD-Final1/27/20171/30/20171/30/2017PPASS
DetailsJim Storey
cory Phone #: ###-####
BLD-Final1/30/20171/30/20171/30/2017PPASS
DetailsJim Storey
FIRE-Final Inspection1/30/20171/30/20171/30/2017PPASS
DetailsJim Page
Final life fire safety inspection passed/complete
Temporary Occupancy1/23/20174/23/20171/23/2017 DONE
DetailsCandy A. Nichols
as per Jason Blais-temp c of o extension request was approved good thru 3/31/17
Telephone call  1/20/2017 DONE
1/20/17-called Corey-he will contact Carmen for an extension rquest to Jason B for the Temp C of O
Temporary Occupancy1/4/20174/4/20171/4/2017 DONE
DetailsCandy A. Nichols
not sure why this temp c of o was issued for 30 plus days so changed it to match the other 4 that ESI have on Parkcenter
BLD-Final11/28/201611/30/201611/30/2016APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Corey Hockersmith
Temporary Occupancy11/30/201612/31/201611/30/2016 DONE
DetailsCarlos Velazquez
as per planning/landscape approval - timeline is set for 30 days
Zoning Approval Temp11/30/201611/30/201611/30/2016 DONE
DetailsJason C. Taylor
Tamporary approval until December 31, 2016 to match the approved bond dates.
FIRE-Final Inspection11/28/201611/29/201611/29/2016PPART
DetailsJim Page
Partial final life fire safety complete, final fire sprinkler inspection is complete, final fire alarm inspection is complete, fire extinguishers are in place with current inspection tags. Building fire sub-panel reports to clubhouse main fire panel, life fire safety will be a partial pass until clubhouse is done and the inspection is finaled/passed.
BLD-Other9/28/20169/29/20169/29/2016PPASS
DetailsPhil Shearer
Bathroom ceiling drops Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Ceiling Grid Inspection8/25/20168/26/20168/26/2016APASS
DetailsJim Storey
RC inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Ceiling Grid Inspection8/24/20168/25/20168/25/2016PDEFR
DetailsJim Storey
RC inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Wall cover8/17/20168/23/20168/23/2016APASS
DetailsJim Storey
Insulation Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Framing/Rough-in8/15/20168/16/20168/16/2016APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Corey Hockersmith
(F) Reprint permit  7/11/2016 DONE
CHANGE STATUS TO (ISS)  7/11/2016 DONE
plan mod fees paid
Plan assigned to (CJW)6/13/20166/13/20167/1/2016 PASS
DetailsCarl Westfall
plan mod
Routing - PLAN CHECK6/20/2016 7/1/2016 PASS
DetailsCarl Westfall
Routing Off Site - STRUCTURAL6/20/2016 7/1/2016 PASS
DetailsCarl Westfall
Jan Welch
PLANS/APPL TAKEN TO FRONT DESK  7/1/2016 DONE
Permit Ready to Issue  7/1/2016 DONE



Plan Mod fees due, DO NOT RE-ISSUE
Plan Modification Accepted  6/20/2016 DONE
Drawings uploaded in ePlanReview
Plan Modification Accepted  6/13/2016 DONE
Per CJW for changes to the structural footings and foundations
BLD-Wall Bracing5/26/20165/26/20165/26/2016PPASS
DetailsJim Storey
Wall and roof sheer Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Aging Inspection2/16/20162/16/20162/16/2016 NR
DetailsJim Storey
BLD-Aging Inspection2/15/20162/15/20162/16/2016 NR
DetailsJim Storey
Print Occupancy Form  4/2/2015 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  4/2/2015 DONE
Permit Ready to Issue  4/1/2015 DONE
need gc form, updated values, ACHD receipt, RP
Routing - PLAN CHECK2/25/2015 3/31/2015 PASS
DetailsCarl Westfall
All agencies approved
PLANS/APPL TAKEN TO FRONT DESK  3/31/2015 DONE
Plan assigned to (CJW)7/22/2014 3/31/2015 PASS
DetailsCarl Westfall
COTTAGE BUILDING A - #1 (1st review done)
Routing Off Site - STRUCTURAL2/26/2015 3/30/2015 PASS
DetailsCarl Westfall
Routing PW Flood Plain2/26/2015 3/30/2015 PASS
DetailsJim Wyllie
Routing - MECHANICAL3/10/2015 3/10/2015 PASS
DetailsTroy James
Routing - MECHANICAL2/26/2015 2/27/2015 FAIL
DetailsTroy James
Routing - Design Review2/26/2015 2/27/2015 PASS
DetailsSarah Schafer
Sarah - Approved per DRH12-00038 and DRH15-00030.
Routing - PLAN CHECK2/25/2015 2/26/2015  
DetailsCarl Westfall
Plan resubmittals received  2/25/2015 DONE
Routing - PLAN CHECK1/23/2015 2/11/2015 FAIL
DetailsCarl Westfall
Routing Off Site - STRUCTURAL1/26/2015 2/11/2015 FAIL
DetailsCarl Westfall
Plan resubmittals requested  2/11/2015 DONE
Routing - MECHANICAL1/26/2015 1/30/2015 FAIL
DetailsSarah Schafer
Routing - MECHANICAL1/26/2015 1/27/2015 FAIL
DetailsTroy James
Routing - PLANNING1/26/2015 1/26/2015 PASS
DetailsCody Riddle
Plan resubmittals received  1/23/2015 DONE
Routing Off Site - STRUCTURAL12/9/2014 12/29/2014 FAIL
DetailsCarl Westfall
Jan Welch
Routing - PLAN CHECK12/13/2014 12/29/2014 FAIL
DetailsCarl Westfall
Waiting for the resolution of the structural issues.
Plan resubmittals requested  12/29/2014 DONE
DetailsCarl Westfall
Routing - PLAN CHECK12/9/2014 12/13/2014 PASS
DetailsCarl Westfall
For the building review, the structural issues have not been resolved.
Plan resubmittals received  12/11/2014 DONE
DetailsCarl Westfall
Routing PW Street Lights12/9/2014 12/10/2014 PASS
DetailsMike D Hedge
Routing - MECHANICAL12/9/2014 12/10/2014 FAIL
DetailsTroy James
Routing - Design Review12/9/2014 12/10/2014 FAIL
DetailsSarah Schafer
Routing - PLANNING10/22/2014 12/9/2014 FAIL
DetailsCody Riddle
One outstanding condition of approval:

Condition #22-The Army Corps required an updated wetland delineation. (We need final written approval from the Corps before we can issue the permit)

Emailed applicant today. (Note: I updated activity from the master permit BLD14-01818.)
Plan resubmittals received  12/8/2014 DONE
DetailsCarl Westfall
Plan resubmittals requested  11/7/2014 DONE
Routing Off Site - STRUCTURAL10/22/2014 11/7/2014 FAIL
DetailsCarl Westfall
Jan Welch
Routing PW Drainage10/22/2014 10/29/2014 PASS
DetailsBrian Murphy
Routing - FIRE10/22/2014 10/28/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 1 10-28-14
Routing - PLAN CHECK10/16/2014 10/27/2014 FAIL
DetailsCarl Westfall
Some issues not resolved
Routing - MECHANICAL10/22/2014 10/22/2014 FAIL
DetailsTroy James
Routing - Erosion and Sediment10/22/2014 10/22/2014 PASS
DetailsEvan Jenkins
Routing PW Street Lights10/22/2014 10/22/2014 FAIL
DetailsMike D Hedge
Routing - Design Review10/22/2014 10/22/2014 FAIL
DetailsSarah Schafer
Routing - PLANNING12/22/2014 10/22/2014 FAIL
DetailsCody Riddle
Plan resubmittals received  10/16/2014  
Routing Off Site - STRUCTURAL7/22/2014 8/27/2014 FAIL
DetailsCarl Westfall
Since the submittal was incomplete, a structural review could not be done.
Routing - MECHANICAL8/11/2014 8/14/2014 FAIL
DetailsTroy James
1st review completed  8/12/2014 FAIL
Plan resubmittals requested  8/12/2014 DONE
Routing - FIRE7/29/20147/29/20148/11/2014 FAIL
DetailsCraig D. Hanson
See Fire Plan Review 08-11-14
Routing - PLAN CHECK7/22/2014 8/11/2014 FAIL
DetailsCarl Westfall
Revised drawings required
Route to Impact Fee Review7/22/2014 8/1/2014 PASS
DetailsCindy M. Gould
Routing PW Drainage7/22/2014 7/29/2014 FAIL
DetailsBrian Murphy
Routing - PLUMBING7/22/2014 7/28/2014 PASS
DetailsDaryl Spivey
Routing - Addressing7/24/2014 7/24/2014 PASS
DetailsEmily Dixon
Routing PW Sewer Design7/24/2014 7/24/2014 PASS
DetailsKyle S. Rosenmeyer
Private Sewer System
Routing PW Solid Waste7/22/2014 7/24/2014 PASS
DetailsPeter J. McCullough
Routing - Design Review7/22/2014 7/24/2014 FAIL
DetailsSarah Schafer
Routing - PLANNING7/22/2014 7/24/2014 FAIL
DetailsCody Riddle
Routing - Erosion and Sediment7/22/2014 7/23/2014 FAIL
DetailsEvan Jenkins
Routing - PLANNING Land Div7/22/2014 7/23/2014 PASS
DetailsDave Abo
Routing PW Street Lights7/22/2014 7/23/2014 FAIL
DetailsMike D Hedge
Routing PW Sewer Rating7/22/2014 7/23/2014 PASS
DetailsBeverly Mountain
Routing - PUBLIC WORKS7/23/2014 7/23/2014 PASS
DetailsBeverly Mountain
Intake Approval  7/22/2014 PASS
DetailsJohn Menard
Pending Assignment by JCM7/22/2014 7/22/2014 DONE
DetailsJohn Menard
Routing - PUBLIC WORKS7/22/2014 7/22/2014 PASS
DetailsBeverly Mountain
Application received  6/30/2014 DONE
Application submitted via PDS Online on Jun 30 2014 6:44AM