Permanent Occupancy | | | 1/31/2017 | | DONE |
|
|
|
|
BLD-Final | 1/27/2017 | 1/30/2017 | 1/30/2017 | P | PASS |
Jim Storey
|
|
|
cory Phone #: ###-####
|
FIRE-Final Inspection | 1/30/2017 | 1/30/2017 | 1/30/2017 | A | PASS |
Jim Page
|
|
|
Final life fire safety inspection passed/complete
|
BLD-Final | 12/13/2016 | 12/14/2016 | 12/14/2016 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Corey Hockersmithtemp ok
|
FIRE-Final Inspection | 12/14/2016 | 12/14/2016 | 12/14/2016 | A | PART |
Jim Page
|
|
|
Partial final life fire safety inspection complete, final fire sprinkler inspection is complete, partial final fire alarm inspection is complete (fire alarm inspection complete for occupancy requested area's), knox box is in place, fire extinguishers are in place with current inspection tags. Building fire sub-panel reports to clubhouse main fire panel, life fire safety will be a partial pass until clubhouse is done as well as completion of fire alarm inspection for remaining area's of builiding including water damaged area's.
|
Temporary Occupancy | 12/14/2016 | 3/14/2017 | 12/14/2016 | | DONE |
Candy A. Nichols
|
|
|
pending all permit finals
|
BLD-Final | 12/9/2016 | 12/14/2016 | 12/13/2016 | A | DEFR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Corey Hockersmith pm
|
FIRE-Final Inspection | 12/9/2016 | 12/13/2016 | 12/13/2016 | P | CANC |
Jim Page
|
|
|
Area of building being requested for occupancy is not ready for occupancy, inspection request will need to be rescheduled when work is complete.
|
FIRE-Final Inspection | 12/9/2016 | 12/9/2016 | 12/9/2016 | P | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by Corey Hockersmith Inspection cancelled from web by: Corey Hockersmith
|
BLD-Other | 8/24/2016 | 8/25/2016 | 8/25/2016 | A | PASS |
Jim Storey
|
|
|
Third floor bathroom ceilings Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
BLD-Other | 8/24/2016 | 8/24/2016 | 8/24/2016 | A | PART |
Jim Storey
|
|
|
Third floor bathroom cilings Phone #: ###-#### Inspection requested via web by Corey Hockersmith c/n posted
|
BLD-Other | 8/10/2016 | 8/10/2016 | 8/10/2016 | P | PASS |
Jim Storey
|
|
|
Second floor bathroom ceilings Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
BLD-Ceiling Grid Inspection | 8/4/2016 | 8/5/2016 | 8/5/2016 | A | PASS |
Jim Storey
|
|
|
First floor bathroom ceilings Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
BLD-Ceiling Grid Inspection | 7/21/2016 | 7/22/2016 | 7/22/2016 | P | PASS |
Jim Storey
|
|
|
Third floor RC ceiling inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
BLD-Ceiling Grid Inspection | 7/18/2016 | 7/19/2016 | 7/19/2016 | A | PASS |
Jim Storey
|
|
|
Second floor RC inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
BLD-Ceiling Grid Inspection | 7/18/2016 | 7/18/2016 | 7/18/2016 | P | DEFR |
Jim Storey
|
|
|
Second floor RC inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith. out of time
|
BLD-Wall cover | 7/15/2016 | 7/15/2016 | 7/15/2016 | P | NR |
Jim Storey
|
|
|
Second floor RC Inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
BLD-Framing/Rough-in | 7/14/2016 | 7/15/2016 | 7/15/2016 | A | PART |
Jim Storey
|
|
|
Third floor framing inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith ok to insulate
|
BLD-Ceiling Grid Inspection | 7/11/2016 | 7/11/2016 | 7/11/2016 | P | PASS |
Jim Storey
|
|
|
First floor RC inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
BLD-Framing/Rough-in | 7/7/2016 | 7/8/2016 | 7/8/2016 | A | PART |
Jim Storey
|
|
|
Third floor framing inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmithc/n
|
BLD-Framing/Rough-in | 7/6/2016 | 7/6/2016 | 7/6/2016 | P | PASS |
Phil Shearer
|
|
|
Second floor reinsection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
BLD-Framing/Rough-in | 6/29/2016 | 7/1/2016 | 7/1/2016 | A | PART |
Jim Storey
|
|
|
First and second floor framing Phone #: ###-#### Inspection requested via web by Corey Hockersmith 1st ok to insulate/c/n posted
|
BLD-Framing/Rough-in | 6/27/2016 | 6/29/2016 | 6/29/2016 | P | PART |
Jim Storey
|
|
|
1st floor framing Phone #: ###-#### Inspection requested via web by Corey Hockersmithc/n
|
BLD-Wall Bracing | 5/9/2016 | 5/10/2016 | 5/10/2016 | A | PASS |
Jim Storey
|
|
|
Fire rated plywood inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
BLD-Wall Bracing | 5/6/2016 | 5/9/2016 | 5/9/2016 | A | PASS |
Jim Storey
|
|
|
Roof sheer inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
BLD-Wall cover | 5/5/2016 | 5/5/2016 | 5/5/2016 | P | NR |
Jim Storey
|
|
|
Roof nailing and strapping inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
BLD-Wall Bracing | 5/4/2016 | 5/5/2016 | 5/5/2016 | A | NR |
Jim Storey
|
|
|
Roof nailing and strapping inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
BLD-Aging Inspection | 2/16/2016 | 2/16/2016 | 2/16/2016 | | NR |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 2/15/2016 | 2/15/2016 | 2/16/2016 | | NR |
Jim Storey
|
|
|
|
BLD-Conference | 10/23/2015 | 10/26/2015 | 10/26/2015 | A | PASS |
Jim Storey
|
|
|
Meeting with Jim Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
CHANGE STATUS TO (ISS) | | | 9/2/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/21/2015 | | 8/25/2015 | | PASS |
Carl Westfall
|
|
|
Plan mod approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/25/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/25/2015 | | DONE |
|
|
|
Plan mod fees on BLD14-01818 need to be paid- DO NOT re-issue
|
Plan Modification Accepted | | | 8/21/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/2/2015 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 4/2/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/1/2015 | | DONE |
|
|
|
need gc form, updated values, ACHD receipt, RP
|
Routing - PLAN CHECK | 2/25/2015 | | 3/31/2015 | | PASS |
Carl Westfall
|
|
|
All agencies approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/31/2015 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 7/22/2014 | | 3/31/2015 | | PASS |
Carl Westfall
|
|
|
INTOWN BUILDING A - #1 (1st review done)
|
Routing Off Site - STRUCTURAL | 2/26/2015 | | 3/30/2015 | | PASS |
Carl Westfall
|
|
|
|
Routing PW Flood Plain | 2/26/2015 | | 3/30/2015 | | PASS |
Jim Wyllie
|
|
|
|
Routing - MECHANICAL | 3/10/2015 | | 3/10/2015 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 2/26/2015 | | 2/27/2015 | | FAIL |
Troy James
|
|
|
|
Routing - Design Review | 1/26/2015 | | 2/27/2015 | | PASS |
Sarah Schafer
|
|
|
Sarah - Approved per DRH12-00038 and DRH15-00030.
|
Routing - PLAN CHECK | 2/25/2015 | | 2/26/2015 | | |
Carl Westfall
|
|
|
|
Plan resubmittals received | | | 2/25/2015 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 2/11/2015 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 1/26/2015 | | 2/11/2015 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
Routing - PLAN CHECK | 1/23/2015 | | 2/11/2015 | | FAIL |
Carl Westfall
|
|
|
|
Routing - Design Review | 1/26/2015 | | 1/30/2015 | | FAIL |
Sarah Schafer
|
|
|
|
Routing - MECHANICAL | 1/26/2015 | | 1/27/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLANNING | 1/26/2015 | | 1/26/2015 | | PASS |
Cody Riddle
|
|
|
|
Plan resubmittals received | | | 1/23/2015 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 12/9/2014 | | 12/29/2014 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
Routing - PLAN CHECK | 12/13/2014 | | 12/29/2014 | | FAIL |
Carl Westfall
|
|
|
Waiting for the resolution of the structural issues.
|
Plan resubmittals requested | | | 12/29/2014 | | DONE |
Carl Westfall
|
|
|
|
Routing - PLAN CHECK | 12/9/2014 | | 12/13/2014 | | PASS |
Carl Westfall
|
|
|
For the building review, the structural issues have not been resolved.
|
Plan resubmittals received | | | 12/11/2014 | | DONE |
Carl Westfall
|
|
|
|
Routing - PLANNING | 12/9/2014 | | 12/10/2014 | | FAIL |
Cody Riddle
|
|
|
One outstanding condition of approval:
Condition #22-The Army Corps required an updated wetland delineation. (We need final written approval from the Corps before we can issue the permit)
Emailed applicant today. (Note: I updated activity from the master permit BLD14-01818.)
|
Routing PW Street Lights | 12/9/2014 | | 12/10/2014 | | PASS |
Mike D Hedge
|
|
|
|
Routing - MECHANICAL | 12/9/2014 | | 12/10/2014 | | FAIL |
Troy James
|
|
|
|
Routing - Design Review | 12/9/2014 | | 12/10/2014 | | FAIL |
Sarah Schafer
|
|
|
|
Plan resubmittals received | | | 12/8/2014 | | DONE |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 10/22/2014 | | 11/7/2014 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
Plan resubmittals requested | | | 11/7/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/16/2014 | | 10/31/2014 | | FAIL |
Carl Westfall
|
|
|
Some items not resolved
|
Routing PW Drainage | 10/22/2014 | | 10/29/2014 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 10/22/2014 | | 10/28/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 10-29-14
|
Routing - Design Review | 10/22/2014 | | 10/22/2014 | | FAIL |
Sarah Schafer
|
|
|
|
Routing - MECHANICAL | 10/22/2014 | | 10/22/2014 | | FAIL |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 10/22/2014 | | 10/22/2014 | | PASS |
Evan Jenkins
|
|
|
|
Routing - PLANNING | 10/22/2014 | | 10/22/2014 | | FAIL |
Cody Riddle
|
|
|
|
Routing PW Street Lights | 10/22/2014 | | 10/22/2014 | | FAIL |
Mike D Hedge
|
|
|
|
Plan resubmittals received | | | 10/16/2014 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/22/2014 | | 8/27/2014 | | FAIL |
Carl Westfall
|
|
|
Since the submittal was incomplete, a structural review could not be done.
|
1st review completed | | | 8/23/2014 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 8/23/2014 | | DONE |
|
|
|
|
Routing - MECHANICAL | 8/11/2014 | | 8/14/2014 | | FAIL |
Troy James
|
|
|
|
Routing - FIRE | 7/29/2014 | 7/29/2014 | 8/12/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 08-12-14
|
Routing - PLAN CHECK | 7/22/2014 | | 8/5/2014 | | FAIL |
Carl Westfall
|
|
|
|
Route to Impact Fee Review | 7/22/2014 | 7/25/2014 | 8/1/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Drainage | 7/22/2014 | | 7/29/2014 | | FAIL |
Brian Murphy
|
|
|
|
Routing - PLUMBING | 7/22/2014 | | 7/28/2014 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - Design Review | 7/22/2014 | | 7/24/2014 | | FAIL |
Sarah Schafer
|
|
|
|
Routing - PLANNING | 7/22/2014 | | 7/24/2014 | | FAIL |
Cody Riddle
|
|
|
|
Routing - Addressing | 7/24/2014 | | 7/24/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing PW Sewer Design | 7/24/2014 | | 7/24/2014 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Private Sewer System
|
Routing PW Solid Waste | 7/22/2014 | | 7/24/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Sewer Rating | 7/22/2014 | | 7/23/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PUBLIC WORKS | 7/23/2014 | | 7/23/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 7/22/2014 | | 7/23/2014 | | FAIL |
Evan Jenkins
|
|
|
|
Routing - PLANNING Land Div | 7/22/2014 | | 7/23/2014 | | PASS |
Dave Abo
|
|
|
|
Routing PW Street Lights | 7/22/2014 | | 7/23/2014 | | FAIL |
Mike D Hedge
|
|
|
|
Intake Approval | | | 7/22/2014 | | PASS |
John Menard
|
|
|
|
Pending Assignment by JCM | 7/22/2014 | | 7/22/2014 | | DONE |
John Menard
|
|
|
|
Intake Approval | | | 7/2/2014 | | FAIL |
Tim L. Woodard
|
|
|
|
Application received | | | 6/30/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 30 2014 6:44AM
|
First Notice | | 2/10/2017 | | | |
|
|
|
|