Permit Information
Permit NumberBLD14-01829
StatusFinaled
Name ESI
Site Address 509 E PARKCENTER BLVD
Project NameThe District at Parkcenter
Customer NumberBLD14-01818 FOR DRAWNGS
ePlanReviewNo
Description
(THE DISTRICT AT PARKCENTER - INTOWN BUILDING A - #2) (The drawings are filed under permit BLD14-01818 in ePlanReview) (11-17-15 PLAN MODIFICATION TO RE-DESIGN THE STRUCTURAL SYSTEM FROM THE FOUNDATION UP. REVISED STRUCTURAL DRAWINGS ARE FILED UNDER BLD14-01828 IN EPLANREVIEW.) (8-25-15 PLAN MODIFICATION TO PROVIDE EXTERIOR EXPANDED POLYSTYRENE FOUNDATION INSULATION IN COMPLIANCE WITH SHALLOW FOUNDATION STANDARDS AT LOCATIONS WHERE THE BOTTOM OF THE FOOTINGS WILL BE LESS THAN 24 INCHES BELOW FINISHED GRADE. THE INTENT IS TO PREVENT FROST HEAVE.) Because there is a fire wall in this building, two permits were created. See BLD14-01828 for a full description of the work proposed. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  2/24/2017 DONE
DetailsChristina Prado
BLD-Final2/22/20172/23/20172/23/2017APASS
DetailsJim Storey
Corey Phone #: ###-####
BLD-Final2/21/20172/22/20172/22/2017ACANC
DetailsDave Hannah
Corey Phone #: ###-####
Temporary Occupancy2/17/20175/18/20172/17/2017 DONE
DetailsCandy A. Nichols
Jason Blais ok'd 30 day ext from 2/19/17
Temporary Occupancy2/17/20175/18/20172/17/2017 DONE
DetailsCandy A. Nichols
Jason Blais ok ext for temp c of o for 30 days from 2-19-17
Meeting  2/17/2017 DONE
Jason Blais ok'd extension on Temp C of O from 2/19/17
Telephone call  2/15/2017 DONE
called Samantha-transferred to Heather-had to email that we need the temp c of o extended
BLD-Aging Inspection1/2/20171/2/20171/4/2017 NR
DetailsJim Storey
Temporary Occupancy12/19/20163/19/201712/19/2016 DONE
DetailsBrittany Hill
As per Jason Blais ok to extend for 60 days.
Telephone call  12/16/2016 DONE
called Samatha to let know the Temp C of O expired on the 14th of Dec and that she will need to call in her final or req an extension-left message on her phone
BLD-Aging Inspection10/31/201610/31/201610/31/2016 PASS
DetailsJim Storey
BLD-Final8/30/20168/31/20168/31/2016PPASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Corey Hockersmith
FIRE-Final Inspection8/31/20168/31/20168/31/2016PPART
DetailsJim Page
Club house structure contains main Fire Alarm Control Unit for entire complex (BLD14-01818). When Clubhouse structure is finaled, the remaining builidings can be finaled in the system. Final fire sprinkler inspection complete, final fire sprinkler underground supply inspection complete, final fire alarm inspection complete, fire extinguishers are in place with current inspection tags, final life fire safety inspection passed/complete.
BLD-Conference8/29/20168/30/20168/30/2016APART
DetailsJim Storey
Corey Phone #: ###-#### wip
BLD-Other8/2/20168/2/20168/2/2016APASS
DetailsJim Storey
Electrical penetration fire caulk in bathrooms Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Other7/22/20167/25/20167/25/2016APASS
DetailsJim Storey
Inspect fire extinguisher cabinet openings Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Other5/31/20166/1/20166/1/2016APASS
DetailsJim Storey
Penetrations behind cabinets in bath and kitchen''s all three floors Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Wall cover5/25/20165/26/20165/26/2016PPART
DetailsJim Storey
Bathroom behind cabinets all three floors Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Wall cover5/23/20165/25/20165/25/2016PNR
DetailsJim Storey
Bathroom behind cabinets all three floors Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Ceiling Grid Inspection4/22/20164/22/20164/22/2016PPART
DetailsJim Storey
Bathroom ceiling grid and fire stop Phone #: ###-#### Inspection requested via web by Corey Hockersmith c/n posted
BLD-Wall cover3/16/20163/17/20163/17/2016PPASS
DetailsJim Storey
RC inspection third floor Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Conference3/9/20163/10/20163/10/2016ACANC
DetailsJim Storey
Level 2 RC Phone #: ###-#### Inspection requested via web by Kevin Honeycut pass ok to cover
BLD-Framing/Rough-in3/7/20163/8/20163/8/2016PPASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt c/n made ok framing ok to insulate roof/ truss letter to be on site
BLD-Framing/Rough-in3/4/20163/7/20163/7/2016PPASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt 2nd floor exterior wall insulation/ dryer vent stud bay 5/8 wrap ok
BLD-Energy code compliance3/2/20163/3/20163/3/2016APASS
DetailsJim Storey
RC channel inspection 1st floor west half Phone #: ###-#### Inspection requested via web by Corey Hockersmithok to cover all bur bathrms
BLD-Wall cover2/29/20163/2/20163/2/2016PDEFR
DetailsJim Storey
RC channel inspection 1st floor west half Phone #: ###-#### Inspection requested via web by Corey Hockersmith thur am
BLD-Framing/Rough-in3/1/20163/1/20163/1/2016PPART
DetailsJim Storey
Re inspect second floor west side. Third floor west side. Phone #: ###-#### Inspection requested via web by Corey Hockersmith 2nd ok/ 3rd part c/n issued
BLD-Framing/Rough-in2/26/20162/29/20162/29/2016PPASS
DetailsJim Storey
Second floor re inspection and third floor inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith c/n idems to check on 2nd and corridor north on first. ok to insulate 2nd
BLD-Framing/Rough-in2/24/20162/25/20162/25/2016PPASS
DetailsJim Storey
First floor west side Phone #: ###-#### Inspection requested via web by Corey Hockersmith ok to insulate
BLD-Framing/Rough-in2/23/20162/24/20162/24/2016PNR
DetailsJim Storey
First floor west side Phone #: ###-#### Inspection requested via web by Corey Hockersmith mech c/n
BLD-Framing/Rough-in2/19/20162/22/20162/22/2016ANR
DetailsJim Storey
First floor re inspection. Second floor framing inspection. Phone #: ###-#### Inspection requested via web by Corey Hockersmith 2hr listing pex and fire spk/4 in clean outs
BLD-Framing/Rough-in2/17/20162/18/20162/18/2016ANR
DetailsJim Storey
First floor framing inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Framing/Rough-in2/15/20162/16/20162/16/2016PPART
DetailsJim Storey
West side first floor framing inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith 1 of 2 c/n posted
BLD-Wall Bracing1/7/20161/11/20161/8/2016ACANC
DetailsJim Storey
Roof sheer and strapping Phone #: ###-#### >> Inspection requested via web by Corey Hockersmith Inspection cancelled from web by: Corey Hockersmith
BLD-Wall Bracing12/7/201512/8/201512/8/2015APASS
DetailsJim Storey
First and second floor sheer Phone #: ###-#### Inspection requested via web by Corey Hockersmith first floor exterior sheer ok/ interior need extention of coridor osb installed.
BLD-Wall Bracing12/1/201512/3/201512/3/2015PNR
DetailsJim Sly
First and second floor sheer Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Wall Bracing12/1/201512/3/201512/3/2015ANR
DetailsJim Sly
First and second floor sheer Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Wall Bracing11/30/201512/1/201512/1/2015ANR
DetailsJim Storey
First and second floor sheer Phone #: ###-#### Inspection requested via web by Corey Hockersmith sole plats not pinned/bottom sheathing not nailled to plate south wall/ overdriven nailling/ nailling between sheathing joint
BLD-Wall Bracing11/17/201511/23/201511/19/2015ACANC
DetailsJim Storey
First and second floor sheer Phone #: ###-#### >> Inspection requested via web by Corey Hockersmith Inspection cancelled from web by: Corey Hockersmith
BLD-Concrete9/8/20159/9/20159/9/2015PPASS
DetailsPhil Shearer
Flatwork rebar and wire mesh Phone #: ###-#### Inspection requested via web by Corey Hockersmith. pending MTI inspection
CHANGE STATUS TO (ISS)  9/2/2015 DONE
Routing - PLAN CHECK8/21/2015 8/25/2015 PASS
DetailsCarl Westfall
Plan mod accepted
PLANS/APPL TAKEN TO FRONT DESK  8/25/2015 DONE
Permit Ready to Issue  8/25/2015 DONE
Plan mod fees on BLD14-01818 need to be paid- DO NOT re-issue
Plan Modification Accepted  8/21/2015 DONE
Print Occupancy Form  4/2/2015 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  4/2/2015 DONE
Permit Ready to Issue  4/1/2015 DONE
need gc form, updated values, ACHD receipt, RP
Routing - PLAN CHECK2/25/2015 3/31/2015 PASS
DetailsCarl Westfall
All agencies approved
PLANS/APPL TAKEN TO FRONT DESK  3/31/2015 DONE
Plan assigned to (CJW)7/22/2014 3/31/2015 PASS
DetailsCarl Westfall
INTOWN BUILDING A - #2 (1st review done)
Routing Off Site - STRUCTURAL2/26/2015 3/30/2015 PASS
DetailsCarl Westfall
Routing PW Flood Plain2/26/2015 3/30/2015 PASS
DetailsJim Wyllie
Routing - MECHANICAL3/10/2015 3/10/2015 PASS
DetailsTroy James
Routing - MECHANICAL2/26/2015 2/27/2015 FAIL
DetailsTroy James
Routing - Design Review2/26/2015 2/27/2015 PASS
DetailsSarah Schafer
Sarah - Approved per DRH12-00038 and DRH15-00030.
Routing - PLAN CHECK2/25/2015 2/26/2015  
DetailsCarl Westfall
Plan resubmittals received  2/25/2015 DONE
Plan resubmittals requested  2/11/2015 DONE
Routing Off Site - STRUCTURAL1/26/2015 2/11/2015 FAIL
DetailsCarl Westfall
Jan Welch
Routing - PLAN CHECK1/23/2015 2/11/2015 FAIL
DetailsCarl Westfall
Routing - Design Review1/26/2015 1/30/2015 FAIL
DetailsSarah Schafer
Routing - MECHANICAL1/26/2015 1/27/2015 FAIL
DetailsTroy James
Routing - PLANNING1/26/2015 1/26/2015 PASS
DetailsCody Riddle
Plan resubmittals received  1/23/2015 DONE
Routing Off Site - STRUCTURAL12/9/2014 12/29/2014 FAIL
DetailsCarl Westfall
Jan Welch
Routing - PLAN CHECK12/13/2014 12/29/2014 FAIL
DetailsCarl Westfall
Waiting for the resolution of the structural issues.
Plan resubmittals requested  12/29/2014 DONE
DetailsCarl Westfall
Routing - PLAN CHECK12/9/2014 12/13/2014 PASS
DetailsCarl Westfall
For the building review, the structural issues have not been resolved.
Plan resubmittals received  12/11/2014 DONE
DetailsCarl Westfall
Routing PW Street Lights12/9/2014 12/10/2014 PASS
DetailsMike D Hedge
Routing - MECHANICAL12/9/2014 12/10/2014 FAIL
DetailsTroy James
Routing - Design Review12/9/2014 12/10/2014 FAIL
DetailsSarah Schafer
Routing - PLANNING12/9/2014 12/9/2014 FAIL
DetailsCody Riddle
One outstanding condition of approval:

Condition #22-The Army Corps required an updated wetland delineation. (We need final written approval from the Corps before we can issue the permit)

Emailed applicant today. (Note: I updated activity from the master permit BLD14-01818.)
Plan resubmittals received  12/8/2014 DONE
DetailsCarl Westfall
Plan resubmittals requested  11/7/2014 DONE
Routing Off Site - STRUCTURAL10/22/2014 11/7/2014 FAIL
DetailsCarl Westfall
Jan Welch
Routing - PLAN CHECK10/16/2014 10/31/2014 FAIL
DetailsCarl Westfall
Some items not resolved
Routing PW Drainage10/22/2014 10/29/2014 PASS
DetailsBrian Murphy
Routing - FIRE10/22/2014 10/28/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 1 10-29-14
Routing - Design Review10/22/2014 10/22/2014 FAIL
DetailsSarah Schafer
Routing - PLANNING10/22/2014 10/22/2014 FAIL
DetailsCody Riddle
Routing PW Street Lights10/22/2014 10/22/2014 FAIL
DetailsMike D Hedge
Routing - Erosion and Sediment10/22/2014 10/22/2014 PASS
DetailsEvan Jenkins
Routing - MECHANICAL10/22/2014 10/22/2014 FAIL
DetailsTroy James
Plan resubmittals received  10/16/2014  
Routing Off Site - STRUCTURAL7/22/2014 8/27/2014 FAIL
DetailsCarl Westfall
Since the submittal was incomplete, a structural review could not be done.
1st review completed  8/23/2014 FAIL
Plan resubmittals requested  8/23/2014 DONE
Routing - MECHANICAL8/11/2014 8/14/2014 FAIL
DetailsTroy James
Routing - FIRE7/29/20147/29/20148/12/2014 FAIL
DetailsCraig D. Hanson
See Fire Plan Review 08-12-14
Routing - PLAN CHECK7/22/2014 8/5/2014 FAIL
DetailsCarl Westfall
Route to Impact Fee Review7/22/20147/25/20148/1/2014 PASS
DetailsCindy M. Gould
Routing PW Drainage7/22/2014 7/29/2014 FAIL
DetailsBrian Murphy
Routing - PLUMBING7/22/2014 7/28/2014 PASS
DetailsBill VanDegrift
Routing - Design Review7/22/2014 7/24/2014 FAIL
DetailsSarah Schafer
Routing - PLANNING7/22/2014 7/24/2014 FAIL
DetailsCody Riddle
Routing PW Solid Waste7/22/2014 7/24/2014 PASS
DetailsPeter J. McCullough
Routing - Addressing7/24/2014 7/24/2014 PASS
DetailsEmily Dixon
Routing PW Sewer Design7/24/2014 7/24/2014 PASS
DetailsKyle S. Rosenmeyer
Private Sewer System
Routing - PUBLIC WORKS7/23/2014 7/23/2014 PASS
DetailsBeverly Mountain
Routing PW Sewer Rating7/22/2014 7/23/2014 PASS
DetailsBeverly Mountain
Routing - Erosion and Sediment7/22/2014 7/23/2014 FAIL
DetailsEvan Jenkins
Routing - PLANNING Land Div7/22/2014 7/23/2014 PASS
DetailsDave Abo
Routing PW Street Lights7/22/2014 7/23/2014 FAIL
DetailsMike D Hedge
Intake Approval  7/22/2014 PASS
DetailsJohn Menard
Pending Assignment by JCM7/22/2014 7/22/2014 DONE
DetailsJohn Menard
Intake Approval  7/2/2014 FAIL
DetailsTim L. Woodard
Application received  6/30/2014 DONE
Application submitted via PDS Online on Jun 30 2014 6:44AM
First Notice 3/6/2017   
FIRE-Final Inspection2/24/20172/24/2017 P 
Details
Temporary Occupancy9/15/201612/14/2016