Information based on query as of Friday, June 21, 2024.
Permit Information
Permit NumberBLD14-01831
StatusFinaled
Name ESI
Site Address 533 E PARKCENTER BLVD
Project NameThe District at Parkcenter
Customer NumberBLD14-01818 FOR DRAWNGS
ePlanReviewNo
Description
(THE DISTRICT AT PARKCENTER - INTOWN BUILDING B - #1) (The drawings are filed under permit BLD14-01818 in ePlanReview) (11-17-15 PLAN MODIFICATION TO RE-DESIGN THE STRUCTURAL SYSTEM FROM THE FOUNDATION UP. REVISED STRUCTURAL DRAWINGS ARE FILED UNDER BLD14-01830 IN EPLANREVIEW.) (8-25-15 PLAN MODIFICATION TO PROVIDE EXTERIOR EXPANDED POLYSTYRENE FOUNDATION INSULATION IN COMPLIANCE WITH SHALLOW FOUNDATION STANDARDS AT LOCATIONS WHERE THE BOTTOM OF THE FOOTINGS WILL BE LESS THAN 24 INCHES BELOW FINISHED GRADE. THE INTENT IS TO PREVENT FROST HEAVE.) Because there is a fire wall in this building, two permits were created. See BLD14-01830 for a full description of the work proposed. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  1/31/2017 DONE
BLD-Final1/27/20171/30/20171/30/2017PPASS
DetailsJim Storey
cory Phone #: ###-####
FIRE-Final Inspection1/30/20171/30/20171/30/2017APASS
DetailsJim Page
Final life fire safety inspection passed/complete
Temporary Occupancy1/23/20174/23/20171/23/2017 DONE
DetailsCandy A. Nichols
as per Jason Blais-extesion for temp c of o is good for 60 days from 1/26/17
Telephone call  1/20/2017 DONE
1/20/17-called Corey-he will contact Carmen for an extension rquest to Jason B for the Temp C of O
BLD-Aging Inspection12/27/201612/27/201612/27/2016 DONE
DetailsJim Storey
FIRE-Final Inspection10/27/201610/28/201610/28/2016APART
DetailsJim Page
Final fire sprinkler inspection complete, final fire alarm inspection complete, fire extinguishers are in place with current insepction tags. Partial final for life fire safety complete, permit will stay in issued status until clubhouse FIR permit is complete, all remote fire panels report to clubhouse panel. After clubhouse FIR permit is finalized then this permit can be finalized.
Temporary Occupancy10/28/20161/26/201710/28/2016 DONE
DetailsBrittany Hill
BLD-Final10/25/201610/28/201610/28/2016PDONE
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by Corey Hockersmith
ok temp per jim storey
FIRE-Final Inspection10/25/201610/27/201610/27/2016PCANC
DetailsJim Page
Inspection request rescheduled for 28OCT2016 per conversation with Corey, Phone #: ###-####.
BLD-Wall cover8/3/20168/4/20168/4/2016APART
DetailsJim Storey
First, second and third floor plumbing penetrations in 1 hour fire wall Phone #: ###-#### Inspection requested via web by Corey Hockersmith c/n posted
BLD-Other8/2/20168/3/20168/3/2016PDEFR
DetailsJim Storey
First, second and third floor plumbing penetrations in 1 hour fire wall Phone #: ###-#### Inspection requested via web by Corey Hockersmith rolled to am out of time
BLD-Other6/27/20166/28/20166/28/2016PPASS
DetailsJim Storey
Third floor bathroom ceiling drops Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Ceiling Grid Inspection6/13/20166/14/20166/14/2016APASS
DetailsJim Storey
Third floor bathroom ceiling drops Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Ceiling Grid Inspection5/31/20166/1/20166/1/2016PPASS
DetailsJim Storey
Second floor bathroom ceiling fur downs Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Ceiling Grid Inspection5/24/20165/25/20165/25/2016PFAIL
DetailsJim Storey
RC third floor Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Ceiling Grid Inspection5/24/20165/25/20165/25/2016APASS
DetailsJim Storey
First floor bathroom ceilings Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Ceiling Grid Inspection5/23/20165/24/20165/23/2016ACANC
DetailsJim Storey
First floor bathroom ceiling grid Phone #: ###-#### >> Inspection requested via web by Corey Hockersmith Inspection cancelled from web by: Corey Hockersmith
BLD-Ceiling Grid Inspection5/20/20165/23/20165/23/2016PCANC
DetailsJim Storey
First floor bathroom ceiling lids Phone #: ###-#### >> Inspection requested via web by Corey Hockersmith Inspection cancelled from web by: Corey Hockersmith
BLD-Ceiling Grid Inspection5/18/20165/20/20165/20/2016PCANC
DetailsJim Storey
First floor bathroom ceiling drops Phone #: ###-#### >> Inspection requested via web by Corey Hockersmith Inspection cancelled from web by: Corey Hockersmith
BLD-Wall cover5/11/20165/12/20165/12/2016APASS
DetailsJim Storey
RC ceiling third floor Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Wall cover4/29/20165/2/20165/2/2016APASS
DetailsJim Storey
RC ceiling grid Second and third floor Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Wall cover4/21/20164/21/20164/21/2016PPASS
DetailsJim Storey
First floor RC inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Framing/Rough-in4/20/20164/21/20164/21/2016PPART
DetailsJim Storey
Second and third floor framing Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Conference4/19/20164/20/20164/20/2016APART
DetailsJim Storey
First floor re inspect. Second and Third floor framing inspection. Phone #: ###-#### Inspection requested via web by Corey Hockersmith c/n on site
BLD-Conference4/15/20164/18/20164/18/2016ACANC
DetailsJim Storey
Framing inspection first floor Phone #: ###-#### >> Inspection requested via web by Corey Hockersmith Inspection cancelled from web by: Corey Hockersmith
BLD-Framing/Rough-in4/11/20164/13/20164/13/2016APART
DetailsJim Storey
First floor framing Phone #: ###-#### Inspection requested via web by Corey Hockersmith c/n on site
BLD-Wall Bracing3/10/20163/14/20163/14/2016APASS
DetailsJim Storey
First and second floor sheer both halves. Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Wall Bracing2/4/20162/5/20162/5/2016APASS
DetailsJim Storey
Roof sheer and strap detail Phone #: ###-#### Inspection requested via web by Corey Hockersmith
Plan assigned to (CJW)10/1/201510/1/201510/5/2015 PASS
DetailsCarl Westfall
PLANS/APPL TAKEN TO FRONT DESK  10/5/2015 DONE
Plan mod done under BLD15-1830
Permit Ready to Issue  10/5/2015 DONE
DetailsChristina Prado
All review & additional fees for plan mod under BLD14-01830
CHANGE STATUS TO (ISS)  10/5/2015 DONE
DetailsChristina Prado
All review & plan mod fees placed under BLD15-01830, changing status to ISS
Routing - PLAN CHECK10/1/2015 10/2/2015  
DetailsCarl Westfall
Plan mod done under permit BLD14-01830.
Plan Modification Accepted  10/1/2015 DONE
DetailsChristina Prado
PLan mod requested for changes to plumbing designs so that a dog wash station can be added per Jamie with IKEMIRE ARCHITECTS
CHANGE STATUS TO (ISS)  9/2/2015 DONE
Routing - PLAN CHECK8/21/2015 8/25/2015 PASS
DetailsCarl Westfall
Plan mod approved
PLANS/APPL TAKEN TO FRONT DESK  8/25/2015 DONE
Permit Ready to Issue  8/25/2015 DONE
Plan mod fees on BLD14-01818 need to be paid- DO NOT re-issue
Plan Modification Accepted  8/21/2015 DONE
Print Occupancy Form  4/2/2015 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  4/2/2015 DONE
Permit Ready to Issue  4/1/2015 DONE
need gc form, updated values, ACHD receipt, RP
Routing - PLAN CHECK2/25/2015 3/31/2015 PASS
DetailsCarl Westfall
All agencies approved
PLANS/APPL TAKEN TO FRONT DESK  3/31/2015 DONE
Plan assigned to (CJW)7/22/2014 3/31/2015 PASS
DetailsCarl Westfall
INTOWN BUILDING B - #1 (1st review done)
Routing Off Site - STRUCTURAL2/26/2015 3/30/2015 PASS
DetailsCarl Westfall
Routing PW Flood Plain2/26/2015 3/30/2015 PASS
DetailsJim Wyllie
Routing - MECHANICAL3/10/2015 3/10/2015 PASS
DetailsTroy James
Routing - MECHANICAL2/26/2015 2/27/2015 FAIL
DetailsTroy James
Routing - Design Review2/26/2015 2/27/2015 PASS
DetailsSarah Schafer
Sarah - Approved per DRH12-00038 and DRH15-00030.
Routing - PLAN CHECK2/25/2015 2/26/2015  
DetailsCarl Westfall
Plan resubmittals received  2/25/2015 DONE
Plan resubmittals requested  2/11/2015 DONE
Routing Off Site - STRUCTURAL1/26/2015 2/11/2015 FAIL
DetailsCarl Westfall
Jan Welch
Routing - PLAN CHECK1/23/2015 2/11/2015 FAIL
DetailsCarl Westfall
Routing - Design Review1/26/2015 1/30/2015 FAIL
DetailsSarah Schafer
Routing - MECHANICAL1/26/2015 1/27/2015 FAIL
DetailsTroy James
Routing - PLANNING1/26/2015 1/26/2015 PASS
DetailsCody Riddle
Plan resubmittals received  1/23/2015 DONE
Routing - PLAN CHECK12/13/2014 12/29/2014 FAIL
DetailsCarl Westfall
Waiting for the resolution of the structural issues.
Plan resubmittals requested  12/29/2014 DONE
DetailsCarl Westfall
Routing Off Site - STRUCTURAL12/9/2014 12/29/2014 FAIL
DetailsCarl Westfall
Routing - PLAN CHECK12/9/2014 12/13/2014 PASS
DetailsCarl Westfall
For the building review, the structural issues have not been resolved.
Plan resubmittals received  12/11/2014 DONE
DetailsCarl Westfall
Routing PW Street Lights12/9/2014 12/10/2014 PASS
DetailsMike D Hedge
Routing - MECHANICAL12/9/2014 12/10/2014 FAIL
DetailsTroy James
Routing - Design Review12/9/2014 12/10/2014 FAIL
DetailsSarah Schafer
Routing - PLANNING12/9/2014 12/9/2014 FAIL
DetailsCody Riddle
One outstanding condition of approval:

Condition #22-The Army Corps required an updated wetland delineation. (We need final written approval from the Corps before we can issue the permit)

Emailed applicant today. (Note: I updated activity from the master permit BLD14-01818.)
Plan resubmittals received  12/8/2014 DONE
DetailsCarl Westfall
Plan resubmittals requested  11/7/2014 DONE
Routing Off Site - STRUCTURAL10/22/2014 11/7/2014 FAIL
DetailsCarl Westfall
Jan Welch
Routing - PLAN CHECK10/16/2014 10/31/2014 FAIL
DetailsCarl Westfall
Some items not resolved
Routing PW Drainage10/22/2014 10/29/2014 PASS
DetailsBrian Murphy
Routing - FIRE10/22/2014 10/28/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 1 10-29-14
Routing - Erosion and Sediment10/22/2014 10/22/2014 PASS
DetailsEvan Jenkins
Routing - MECHANICAL10/22/2014 10/22/2014 FAIL
DetailsTroy James
Routing - PLANNING10/22/2014 10/22/2014 FAIL
DetailsCody Riddle
Routing PW Street Lights10/22/2014 10/22/2014 FAIL
DetailsMike D Hedge
Routing - Design Review10/22/2014 10/22/2014 FAIL
DetailsSarah Schafer
Plan resubmittals received  10/16/2014  
Routing Off Site - STRUCTURAL7/22/2014 8/27/2014 FAIL
DetailsCarl Westfall
Since the submittal was incomplete, a structural review could not be done.
1st review completed  8/23/2014 FAIL
Plan resubmittals requested  8/23/2014 DONE
Routing - MECHANICAL8/11/2014 8/14/2014 FAIL
DetailsTroy James
Routing - FIRE7/29/20147/29/20148/12/2014 FAIL
DetailsCraig D. Hanson
See Fire Plan Review 08-12-14
Routing - PLAN CHECK7/22/2014 8/5/2014 FAIL
DetailsCarl Westfall
Route to Impact Fee Review7/22/20147/25/20148/1/2014 PASS
DetailsCindy M. Gould
Routing PW Drainage7/22/2024 7/29/2014 FAIL
DetailsBrian Murphy
Routing - PLUMBING7/22/2014 7/28/2014 PASS
DetailsBill VanDegrift
Routing - Addressing7/24/2014 7/24/2014 PASS
DetailsEmily Dixon
Routing PW Sewer Design7/24/2014 7/24/2014 PASS
DetailsKyle S. Rosenmeyer
Private Sewer System
Routing PW Solid Waste7/22/2014 7/24/2014 PASS
Details
Routing - Design Review7/22/2014 7/24/2014 FAIL
DetailsSarah Schafer
Routing - PLANNING7/22/2014 7/24/2014 FAIL
DetailsCody Riddle
Routing PW Sewer Rating7/22/2014 7/23/2014 PASS
DetailsBeverly Mountain
Routing - Erosion and Sediment7/22/2014 7/23/2014 FAIL
DetailsEvan Jenkins
Routing - PLANNING Land Div7/22/2014 7/23/2014 PASS
DetailsDave Abo
Routing PW Street Lights7/22/2014 7/23/2014 FAIL
DetailsMike D Hedge
Routing - PUBLIC WORKS7/23/2014 7/23/2014 PASS
DetailsBeverly Mountain
Intake Approval  7/22/2014 PASS
DetailsJohn Menard
Pending Assignment by JCM7/22/2014 7/22/2014 DONE
DetailsJohn Menard
Intake Approval  7/2/2014 FAIL
DetailsTim L. Woodard
Application received  6/30/2014 DONE
Application submitted via PDS Online on Jun 30 2014 6:44AM
First Notice 2/10/2017