Second Notice | | 1/12/2015 | 1/13/2015 | | DONE |
|
|
|
This permit finaled on the web by Lisa Owen
|
First Notice | 12/23/2014 | 12/23/2014 | 1/2/2015 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 12/22/2014 | 12/23/2014 | 12/23/2014 | P | PASS |
Dave Hannah
|
|
|
Boyd Phone #: ###-####
|
DOC - Permit Finaled | 12/23/2014 | 12/23/2014 | 12/23/2014 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 12/22/2014 | 12/23/2014 | 12/23/2014 | A | PASS |
Forrest France
|
|
|
Scope of remodel work completed. Fire life safety inspection passed.
|
Zoning Approval | 12/23/2014 | 12/23/2014 | 12/23/2014 | | DONE |
Andrea Tuning
|
|
|
|
Permit Ready to Issue | | | 12/3/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 12/3/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 12/3/2014 | | DONE |
Christina Prado
|
|
|
|
Expiration Notice | 12/2/2014 | 12/23/2014 | 12/2/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 7/24/2014 | | 8/6/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 7/24/2014 | | 8/6/2014 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 8/6/2014 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/6/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - Design Review | 7/24/2014 | | 7/24/2014 | | PASS |
Andrea Tuning
|
|
|
|
Intake Approval | | | 7/23/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 7/18/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Sheet S1.0 does not meet the minimum sheet size for drawings. Please refer to the submittal standards for e plan submittal.
Please upload the completed 310 form for periodic special inspection for the welding shown in the structural details.
|
Application received | | | 6/30/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 30 2014 9:33AM
|