Second Notice | | 5/15/2015 | 5/18/2015 | | DONE |
|
|
|
This permit finaled on the web by Tony O'Neil
|
First Notice | | 4/24/2015 | 5/5/2015 | | DONE |
Candy A. Nichols
|
|
|
mailed 5-5-15
|
Permanent Occupancy | | | 4/14/2015 | | DONE |
|
|
|
|
Permanent Occupancy | | | 4/14/2015 | | DONE |
|
|
|
|
BLD-Final | 4/10/2015 | 4/13/2015 | 4/13/2015 | P | PASS |
Mike Jordan
|
|
|
Doug Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 4/9/2015 | 4/9/2015 | 4/9/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 4/8/2015 | 4/9/2015 | 4/9/2015 | A | FAIL |
Mike Jordan
|
|
|
doug Phone #: ###-####. Need to get shell and core signed off, open mech and fire permits.
|
FIRE-Final Inspection | 4/7/2015 | 4/9/2015 | 4/8/2015 | A | CANC |
Troy Cobbley
|
|
|
Overbooked. Rescheduled for tomorrow morning
|
FIRE-Conference | 3/17/2015 | 3/18/2015 | 3/18/2015 | A | DONE |
Troy Cobbley
|
|
|
Doug and I went over fire dept signage
|
BLD-Other | 3/16/2015 | 3/16/2015 | 3/16/2015 | P | PASS |
Mike Jordan
|
|
|
Sheeting //Doug Phone #: ###-####. Remainder of storefront framing and sheathing (GlassRoc). Ok.
|
BLD-Wall cover | 3/6/2015 | 3/6/2015 | 3/6/2015 | P | PASS |
Phil Shearer
|
|
|
Doug Phone #: ###-####
|
BLD-Energy code compliance | 2/26/2015 | 2/26/2015 | 2/26/2015 | P | PASS |
Mike Jordan
|
|
|
Late PM - Doug Phone #: ###-####
|
FIRE-Conference | 2/25/2015 | 2/25/2015 | 2/25/2015 | P | DONE |
Troy Cobbley
|
|
|
Doug and I talked of options for the exterior soffit such as sprinklers or fire stopping to 160 cubic feet
|
BLD-Framing/Rough-in | 2/24/2015 | 2/25/2015 | 2/25/2015 | A | PASS |
Mike Jordan
|
|
|
Doug Phone #: ###-####. Interior steel stud framed walls ok.
|
Issue PAID IN FULL permit | | | 10/9/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 10/9/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (JCM) | 6/30/2014 | | 10/7/2014 | | PASS |
John Menard
|
|
|
Kid to Kid TI - 1st Review Complete 7/16/2014
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/7/2014 | | DONE |
John Menard
|
|
|
|
Permit Ready to Issue | | | 10/7/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - FIRE | 6/30/2014 | 6/30/2014 | 7/16/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 07-16-14
|
1st review completed | | | 7/16/2014 | | DONE |
John Menard
|
|
|
|
Routing - PLAN CHECK | 6/30/2014 | | 7/16/2014 | | FAIL |
John Menard
|
|
|
|
Route to Impact Fee Review | 6/30/2014 | 7/3/2014 | 7/3/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Design Review | 6/30/2014 | | 7/2/2014 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLUMBING | 6/30/2014 | | 7/2/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PUBLIC WORKS | 6/30/2014 | | 7/1/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 7/1/2014 | | 7/1/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 6/30/2014 | | 6/30/2014 | | PASS |
Andy J. Long
|
|
|
Reference BLD14-01740/ESC14-00553 for ESC site map and ePlan submittals.
|
Routing - Addressing | 6/30/2014 | | 6/30/2014 | | PASS |
Emily Dixon
|
|
|
Suite 100: Kid to Kid
Suite 112: Uptown Cheapskate
|
Intake Approval | | | 6/30/2014 | | PASS |
John Menard
|
|
|
|
Intake Approval | | | 6/30/2014 | | |
|
|
|
|
Pending Assignment by JCM | 6/30/2014 | | 6/30/2014 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 6/30/2014 | | | |
|
|
|
|
Application received | | 6/30/2014 | | | |
|
|
|
|