Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD14-01864
StatusFinaled
Name VERTICAL CORP
Site Address 800 W MAIN ST 1460
Project NameIntelligent Office Suite 1460
Customer Number 
ePlanReviewNo
Description
(INTELLIGENT OFFICE - 8TH & MAIN HIGH-RISE - SUITE 1460) Fire sprinklers used for high rise. To create a 3,505 square foot office tenant space on the 18,300 square foot 14th story of a new high rise building. Work is to include interior nonbearing walls, interior doors and sidelights, card readers, suspended acoustical ceilings, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. Special inspection is required for welding and expansion anchors. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 2/7/20152/17/2015 DONE
This permit finaled on the web by Todd Weltner
Third Notice 1/11/20152/2/2015 DONE
Second Notice 12/13/20141/6/2015 DONE
DetailsCandy A. Nichols
sent in mail 1/6/15
First Notice 11/3/201412/3/2014 DONE
sent 1st n otice in mail 12-3-14 CAN
BLD-Final10/23/201410/24/201410/24/2014APASS
DetailsDave Hannah
call 30 min prior to meet // Aaron Acre Phone #: ###-####
Permanent Occupancy  10/24/2014 DONE
BLD-Final10/14/201410/15/201410/15/2014APART
DetailsDave Hannah
Aaron Baker Phone #: ###-#### ok for temp occ needs to lower break room sink.
FIRE-Final Inspection10/14/201410/14/201410/14/2014PPASS
DetailsCraig D. Hanson
FIRE-Final Inspection10/9/201410/10/201410/10/2014ACANC
DetailsTroy Cobbley
Cancel per Aaron
Phone #: ###-####// please call 30 min prior
BLD-Final10/9/201410/10/201410/10/2014PCANC
DetailsDave Hannah
Aaron// please call 30 min prior Phone #: ###-#### Inspection cancelled from web by: Kristal Soland
BLD-Ceiling Grid Inspection10/1/201410/1/201410/1/2014PPASS
DetailsDave Hannah
Aaron Baker Phone #: ###-####
BLD-Framing/Rough-in8/22/20148/25/20148/26/2014PPASS
DetailsDave Hannah
Aaron Phone #: ###-####
Issue PAID IN FULL permit  8/4/2014 DONE
DetailsBarbara Stitt
Route to Impact Fee Review7/30/20148/2/20147/30/2014 PASS
DetailsCindy M. Gould
Tenant improvement no impact fees
Plan assigned to (CJW)7/1/20147/1/20147/30/2014 PASS
DetailsCarl Westfall
INTELLIGENT OFFICE - Level 3 TI - Paper - 8th & Main (15 days - July 21)
PLANS/APPL TAKEN TO FRONT DESK  7/30/2014 DONE
Print Occupancy Form  7/30/2014  
DetailsCandy A. Nichols
Telephone call  7/30/2014 DONE
DetailsChristina Prado
Called Jason to advise permit is ready pending GC and gave fees due
Permit Ready to Issue  7/30/2014 DONE
DetailsChristina Prado
Routing - PLAN CHECK7/23/2014 7/30/2014 PASS
DetailsCarl Westfall
Drawings approved after the resubmittal review
Plan resubmittals received  7/29/2014 DONE
DetailsTisha Gallop
received two copies of structural calcs and plan sheets G101, A101, A102, A105, A106, A107, S101, M001, M101; taken to Carl Westfall.
1st review completed  7/23/2014 FAIL
Failed: Plan Check
Routing - FIRE7/23/2014 7/23/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review 07-23-14
Routing - PLAN CHECK7/7/2014 7/23/2014 FAIL
DetailsCarl Westfall
Revised drawings required
Plan resubmittals received  7/18/2014  
Received 1 copy of money receipt, 1 copy of addendum response, 2 copies of sheets G101, A101, M001, M201, M302, E001, E101 and taken to Carl Westfall's desk
Routing - MECHANICAL7/2/2014 7/7/2014 PASS
DetailsTroy James
Routing - PLUMBING7/2/2014 7/2/2014 PASS
DetailsBill VanDegrift
No review required.
Routing - Addressing7/1/2014 7/2/2014 PASS
DetailsJason C. Taylor
Routing - PUBLIC WORKS  7/2/2014 PASS
Intake Approval  7/1/2014 PASS
DetailsSam Zahorka
Plans ACCEPTED BY PLAN TECH  7/1/2014 DONE
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  7/1/2014 DONE
DetailsChristina Prado
Pending Assignment by JCB7/1/2014 7/1/2014 DONE
DetailsJason Blais
Application received 7/1/2014