Print Statement | | | 12/12/2016 | | DONE |
|
|
|
|
Second Notice | | 10/20/2016 | 11/15/2016 | | DONE |
|
|
|
Mailed 11-16-16
|
First Notice | | 9/23/2016 | 10/10/2016 | | DONE |
|
|
|
|
Permanent Occupancy | | | 9/13/2016 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/8/2016 | 9/9/2016 | 9/9/2016 | A | PASS |
Jim Page
|
|
|
Previously noted items have been addressed/repaired. Fire sprinkler inspection is complete, no modifications have been made to the fire alarm system, commercial hood fire suppression system as well as fire extinguisher has current inspection tags. Final life fire safety inspection passed/complete.
|
FIRE-Final Inspection | 8/26/2016 | 8/26/2016 | 8/26/2016 | P | FAIL |
Jim Page
|
|
|
Fire plan review documentation was not provided at time of inspection. Fire sprinkler located on the west side of commercial cooking hood is to close, fire sprinkler head needs relocated. Commercial hood fire suppression system did not have a current inspection tag, hood needs to be inspected and tagged. ABC and Class K fire extinguisher needs to be inspected and tagged with current inspection tag, current inspection tags have expired.
|
Print Occupancy Form | | | 8/26/2016 | | DONE |
|
|
|
|
BLD-Final | 8/22/2016 | 8/23/2016 | 8/24/2016 | A | PASS |
Dave Hannah
|
|
|
can be done anytime today except 11:30-12:00 that''s lunch rush-if you could, can you do it later so fire can do theres early
|
FIRE-Final Inspection | 8/22/2016 | 8/23/2016 | 8/23/2016 | A | CANC |
Jim Page
|
|
|
Spoke with people inside at tenant space, none of the individuals I talked to had any information for a final fire inspection request. No phone name or phone number provided for contact information. Inspection request will need to be rescheduled for another day.
|
Routing - Design Review | 8/22/2016 | | 8/22/2016 | | PASS |
Sarah Schafer
|
|
|
Approved with no exterior work being done.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2016 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 8/22/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Guru Donuts has vacated space, new tenant to submit application for occupancy.
|
CHANGE STATUS TO (ISS) | | | 8/22/2016 | | DONE |
|
|
|
No plan mod fee per AJS
|
Plan assigned to (TLW) | 1/14/2015 | | 8/22/2016 | | PASS |
Tim L. Woodard
|
|
|
Plan Mod
|
Routing - Design Review | 4/5/2016 | | 6/28/2016 | | FAIL |
Matthew A Halitsky
|
|
|
The drawings have failed to show compliance with the condition of approval on the Design Review application requiring the wood bulkhead at the base of the windows be maintained and the retractable windows be placed in the smaller opening.
|
Routing - Design Review | 10/19/2015 | | 10/21/2015 | | FAIL |
Matthew A Halitsky
|
|
|
Exterior alterations not approved. Sidewalk cafe not approved.
|
Routing - PLAN CHECK | 7/9/2015 | | 10/19/2015 | | PASS |
Tim L. Woodard
|
|
|
Plan Resubmittals Recieved.
|
Telephone call | | | 10/15/2015 | | DONE |
|
|
|
called Blake to let know that the temp c of o is expired and asked how they were doing on getting the information Tim W needs to complete the review on the plan mod. He is sending an email to me to give to Tim W. I received it and forwarded it to Tim W for his review.
|
Telephone call | | | 10/2/2015 | | DONE |
|
|
|
called Chris to let know the temp c of o is expired and we still have not received the corrections for the plan mod. He is calling Ward today.
|
Telephone call | | | 8/31/2015 | | DONE |
|
|
|
call-left message on Chris's phone-temp c of o expires 9-7-15
|
Telephone call | | | 7/24/2015 | | |
|
|
|
|
Temporary Occupancy | 7/9/2015 | 10/7/2015 | 7/9/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Routing - PLAN CHECK | 1/14/2015 | | 1/23/2015 | | PASS |
Tim L. Woodard
|
|
|
Approved with letter of operations from the owner. TLW
|
Routing - FIRE | 1/14/2015 | | 1/20/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing PW Sewer Rating | 1/14/2015 | | 1/15/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Design Review | 1/14/2015 | | 1/14/2015 | | FAIL |
Matthew A Halitsky
|
|
|
Plan Modification to add area.
Exterior elevations do not reflect Design Review approval.
|
Routing - PUBLIC WORKS | 1/14/2015 | | 1/14/2015 | | PASS |
Jennifer Bruner
|
|
|
Plan Modification to expand into adjacent existing bar. TLW
|
Plan Modification Accepted | | | 1/12/2015 | | DONE |
|
|
|
New M1 sheet with mechanical changes
|
Routing - MECHANICAL | 1/12/2015 | | 1/12/2015 | | PASS |
Troy James
|
|
|
New M1 sheet with changes to the return air at basement being ducted to kitchen and office.
|
Temporary Occupancy | 1/9/2015 | 4/9/2015 | 1/9/2015 | | DONE |
Christina Prado
|
|
|
|
Zoning Approval | 1/9/2015 | 1/9/2015 | 1/9/2015 | | DONE |
Matthew A Halitsky
|
|
|
|
BLD-Final | 1/8/2015 | 1/8/2015 | 1/8/2015 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Eby ok for temp occ
|
FIRE-Final Inspection | 1/8/2015 | 1/8/2015 | 1/8/2015 | P | PART |
Forrest France
|
|
|
Previous C/N items per inspection done 1/6 verified for completion. Temp occupancy approved. Final pending completion of project related FIR trade permit work.
|
BLD-Final | 1/7/2015 | 1/7/2015 | 1/8/2015 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Eby needs other trades to final
|
FIRE-Final Inspection | 1/6/2015 | 1/7/2015 | 1/7/2015 | A | FAIL |
Forrest France
|
|
|
Items noted include; trouble condition at the FACP remote annunciator, missing fire sprinkler coverage at the new beer cooler, overspaced sprinkler coverage adjacent to the new cooler, remove keyed lock deadbolt at the basement kitchen exit door, adjust sprinkler coverage at the basement office due to drop ceiling removal.
|
FIRE-Final Inspection | 1/6/2015 | 1/6/2015 | 1/6/2015 | P | NR |
Forrest France
|
|
|
Need project related fire sprinkler permit work completion and final prior to BLD fire life safety approval.
|
BLD-Conference | 12/28/2014 | 12/29/2014 | 12/29/2014 | A | PASS |
Dave Hannah
|
|
|
Look over the framing and drywall for hood shaft. Phone #: ###-#### Inspection requested via web by Chris Eby
|
BLD-Conference | 12/23/2014 | 12/24/2014 | 12/24/2014 | A | PASS |
Dave Hannah
|
|
|
Look at framing and Sheetrock inside of hood duct shaft. Phone #: ###-#### Inspection requested via web by Chris Eby
|
BLD-Ceiling Grid Inspection | 12/23/2014 | 12/24/2014 | 12/24/2014 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Eby
|
Plan Modification Accepted | | | 12/10/2014 | | DONE |
Christina Prado
|
|
|
Per applicants request
|
BLD-Conference | 12/8/2014 | 12/9/2014 | 12/9/2014 | A | PASS |
Dave Hannah
|
|
|
ADA concrete ramps. Phone #: ###-#### Inspection requested via web by Chris Eby
|
BLD-Other | 12/3/2014 | 12/4/2014 | 12/4/2014 | A | PEND |
Dave Hannah
|
|
|
Inspection for structural steel beams. Phone #: ###-#### Inspection requested via web by Chris Eby need stru engin or spec inspection to sign off
|
BLD-Ceiling Grid Inspection | 12/3/2014 | 12/4/2014 | 12/4/2014 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Eby needs elec rough ins
|
Telephone call | | | 10/13/2014 | | DONE |
Tisha Gallop
|
|
|
e-mailed revised P1 sheet with correct markup on it to Chris Eby/Arbor Finsih Carpentry and told him need to print sheet and replace in plans on site.
|
Routing - PLANNING | 10/8/2014 | | 10/9/2014 | | PASS |
Matthew A Halitsky
|
|
|
The outdoor patio is not approved with the building permit. The applicant must first submit for and obtain approvals through the Clerk's Office.
|
Permit Ready to Issue | | | 10/9/2014 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 10/9/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 10/9/2014 | | DONE |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 7/15/2014 | | 10/8/2014 | | PASS |
Tim L. Woodard
|
|
|
1st Review Completed Boise Fry Company
|
Routing - PLAN CHECK | 8/18/2014 | | 10/6/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLANNING | 10/6/2014 | | 10/6/2014 | | FAIL |
Matthew A Halitsky
|
|
|
Failed in E-Plan. Plans did not match DRH approval conditions. TLW
|
Routing - PLANNING | 8/18/2014 | | 8/27/2014 | | FAIL |
Sarah Schafer
|
|
|
Certificate of Appropriateness required.
|
Routing - MECHANICAL | 8/18/2014 | | 8/21/2014 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 8/18/2014 | 8/18/2014 | 8/20/2014 | | PASS |
Scott Arellano
|
|
|
Attached revised comments to plans.
|
Routing - Addressing | 8/18/2014 | | 8/19/2014 | | PASS |
Jason C. Taylor
|
|
|
Boise Fry Company - Suite 101
Guru Donut - Suite 102
|
Plan resubmittals received | | | 8/18/2014 | | DONE |
|
|
|
|
Route to Impact Fee Review | 8/5/2014 | 8/8/2014 | 8/5/2014 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - FIRE | 7/15/2014 | 7/15/2014 | 7/31/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 07-31-14
|
1st review completed | | | 7/31/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Routing PW Environmental | 7/15/2014 | | 7/30/2014 | | PASS |
Rick Christenson
|
|
|
Approved in E-Plan Review. TLW
|
Routing Off Site - C.D.H | 7/15/2014 | | 7/30/2014 | | PASS |
Tim L. Woodard
|
|
|
Approved in E-Plan Review. TLW
|
Routing - PLAN CHECK | 7/15/2014 | | 7/29/2014 | | FAIL |
Tim L. Woodard
|
|
|
Refer to E-Plan Review. TLW
|
Routing - MECHANICAL | 7/15/2014 | | 7/17/2014 | | FAIL |
Troy James
|
|
|
|
Routing - Design Review | 7/15/2014 | | 7/16/2014 | | FAIL |
Sarah Schafer
|
|
|
Sarah Schafer - DRH14-00241 Still needs Historic Preservation Approval.
|
Routing - Erosion and Sediment | 7/15/2014 | | 7/15/2014 | | PASS |
Andy J. Long
|
|
|
Interior T.I. and remodel - level 3 due to occupancy change. No addition to square footage or exterior excavation. No ESC permit required.
|
Routing - PLUMBING | 7/15/2014 | | 7/15/2014 | | PASS |
Bill VanDegrift
|
|
|
this is for an early start permit, plumbing plans are approved at this time. If changes are required for pretreatment or min. fixture by building review submit changes for review.
|
Routing - Addressing | 7/15/2014 | | 7/15/2014 | | FAIL |
Jason C. Taylor
|
|
|
Two addresses listed for two separate businesses. Jason Taylor ###-####
|
Routing - PUBLIC WORKS | 7/15/2014 | | 7/15/2014 | | PASS |
Beverly Mountain
|
|
|
|
Pending Assignment by JCB | 7/15/2014 | | 7/15/2014 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 7/14/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Madsen and plan review fees paid.
|
Intake Approval | | | 7/8/2014 | | FAIL |
|
|
|
Please provide the following items. Required items are noted on the checklist with a blue arrow.
Central distict health review form and license.
Provide a complete door schedule or call out all sizes on the plans.
Provide a complete door hardware schedule. All door hardware cannot be lever if this is a A-2 occupancy.
Please separate all plan sheets into individual documents. See electronic submittal requirements.
Please provide a plimbing plan. Sheet P-1 is indicated on the checklist but mo P-1 sheet has been uploaded.
|
Application received | | | 7/1/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 1 2014 5:09PM
|
Routing PW Environmental | 1/14/2015 | | | | FAIL |
Rick Christenson
|
|
|
Need plumbing plans to clearly indicate what fixtures are connected to exterior grease interceptor.
|