Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberBLD14-01930
StatusFinaled
Name RCH CONSTRUCTION
Site Address 519 W HAYS ST
Project NameMckibben+Cooper Duplex
Customer Number 
ePlanReviewYes
Description
Permit for the construction of a new 2,160 sq. ft. duplex with attached 504 sq. ft. garage. The first floor unit is 876 sq. ft. with 1 bedrooms, 1 bathroom, and the kitchen will only be roughed in on this unit. The second floor unit is 1,284 sq. ft. with 2 bedrooms, 1 bathroom. All work per the approved plans, plan review report and any notations. L-OHD/CI zoning and setbacks per planning. JG
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/14/20155/15/20155/15/2015PPASS
DetailsTony Young
Call before // Noah Phone #: ###-####
DOC - Permit Finaled5/15/20155/15/20155/15/2015PPASS
DetailsTony Young
c of o issued
Zoning Approval5/14/20155/14/20155/14/2015 DONE
DetailsMatthew A Halitsky
BLD-Final4/3/20154/6/20154/6/2015PNR
DetailsTony Young
Noah Phone #: ###-####,, walk through only
BLD-Energy code compliance1/14/20151/16/20151/16/2015PPASS
DetailsTony Young
Noah Phone #: ###-####
BLD-Framing/Rough-in1/6/20151/7/20151/7/2015APASS
DetailsTony Young
Noah Phone #: ###-####
BLD-Conference12/11/201412/11/201412/11/2014PPART
DetailsTony Young
ASAP please :) Noah Phone #: ###-####,, ok to spray on base layer of 3" of foam on the underside of roof deck / roof joists
BLD-Wall Bracing11/14/201411/18/201411/18/2014APASS
DetailsTony Young
Noah Phone #: ###-####
BLD-Footing9/2/20149/2/20149/2/2014PPASS
DetailsTony Young
Noah Phone #: ###-####,, interior footings ok
BLD-Foundation8/21/20148/22/20148/22/2014APART
DetailsTony Young
Noah Phone #: ###-####,, ok to pour
BLD-Footing8/21/20148/21/20148/21/2014PPASS
DetailsTony Young
Noah Phone #: ###-####
Issue PAID IN FULL permit  8/15/2014 DONE
Inspection Record Card- Bld  8/15/2014 DONE
OVERRIDE  8/13/2014  
Routing PW Sewer Rating8/12/2014 8/13/2014 PASS
DetailsJennifer Bruner
Permit Ready to Issue  8/13/2014 DONE
DetailsCandy A. Nichols
Plan assigned to (PEP)8/6/20148/6/20148/12/2014 PASS
DetailsPerry Paine
1st review completed  8/12/2014 DONE
PLANS/APPL TAKEN TO FRONT DESK  8/12/2014 DONE
Routing - PLAN CHECK8/5/2014 8/11/2014 PASS
DetailsJavier Guzman
ePlan need engineering calcs sealed
Plan assigned to (JG)8/5/20148/5/20148/6/2014 DEFR
DetailsJavier Guzman
L1 ePlan Duplex
Routing - MECHANICAL8/5/2014 8/6/2014 PASS
DetailsTroy James
Routing - PLANNING8/5/2014 8/6/2014 PASS
DetailsJoshua Johnson
Routing - Addressing8/5/2014 8/6/2014 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS8/5/2014 8/5/2014 PASS
DetailsJennifer Bruner
Plans ACCEPTED BY PLAN TECH  8/5/2014 DONE
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  8/5/2014 DONE
DetailsChristina Prado
Intake Approval  8/5/2014 PASS
DetailsJason Blais
Intake Approval  7/23/2014 FAIL
DetailsTisha Gallop
need 1 hr separation detail, garage separation details, stair section
Intake Approval  7/15/2014 FAIL
DetailsChristina Prado
See checklist report in ePlan review
Application received  7/8/2014 DONE
Application submitted via PDS Online on Jul 8 2014 1:56PM