Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD14-01937
StatusFinaled
Name MCALVAIN CONSTRUCTION INC
Site Address 1105 S LA POINTE ST
Project NameWest Sherwood Apartments
Customer NumberBLD14-01936 & BLD14-01938
ePlanReviewNo
Description
VISTA EAST -(formerly known as West Sherwood Apartments) - Building 1 - To construct a 41,670 square foot, three story, wood framed apartment building. This building contains 57 living units. This building is being constructed on a three-hour fire-resistive concrete podium above a one story concrete parking garage building. This apartment building is being divided into three buildings by two fire walls. This building is being sprinklered with an NFPA 13R system. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance/Occupancy  7/22/2016 DONE
Print Statement  12/22/2015 DONE
Permanent Occupancy  10/27/2015 DONE
BLD-Final10/21/201510/22/201510/22/2015APASS
DetailsDave Hannah
Abel Phone #: ###-####
Zoning Approval10/21/201510/21/201510/21/2015 DONE
DetailsAndrea Tuning
BLD-Aging Inspection9/30/20159/30/20159/30/2015 PEND
DetailsDave Hannah
BLD-Conference7/31/20157/31/20157/31/2015PPASS
DetailsDave Hannah
Conference Phone #: ###-#### Inspection requested via web by Julian Lopez
FIRE-Final Inspection7/31/20157/31/20157/31/2015PPART
DetailsThomas Walsh
Inspection of newly added exit signs needed to improve ID of egress to exits - all floors, and the clubhouse. All exit signs are now adequate.
Only pending issues are EVAC signs posted, and final signoff of fire sprinklers and fire alarm system.
Zoning Approval Temp7/31/20157/31/20157/31/2015 DONE
DetailsAndrea Tuning
BND15-00084
Temporary Occupancy UNPAID FEE  7/31/2015 DONE
DetailsChristina Prado
BLD-Conference7/29/20157/29/20157/29/2015ADONE
DetailsBob Archibald
Confirmed with electrical contractor and engineer that the fire alarm system wiring has been extended to a point within the units and is available for upgrade when necessary to sustain visual notification for rooms occupied by hearing impaired tenants. ICC A117.1-2009 section 1006.2 and 1006.3.
FIRE-Final Inspection7/23/20157/24/20157/24/2015APASS
DetailsJim Page
*****10-27-15 as per Scott A. all fire life inspections have passed and ready for perm c of o****Temporary occupancy approved for life fire safety, verbally confirmed with electrical contractor that the fire alarm system has capability to sustain visual notification for rooms occupied by hearing impaired tenants. Electrical contractor needs to provide information on heat tape used on fire sprinkler system before final sign off can occur.
BLD-Final7/23/20157/24/20157/24/2015PPEND
DetailsDave Hannah
Walk building for final. Phone #: ###-#### Inspection requested via web by Julian Lopez. Needs other trades ot go perm occ needs to install perm signage, type A ada units need to meet ansi 117.1 chapter 10 section 1006. ok for temp occ.
BLD-Other7/20/20157/20/20157/21/2015PPEND
DetailsDave Hannah
Life safety. This would be for Tom. Phone #: ###-#### Inspection requested via web by Julian Lopez
FIRE-Final Inspection7/20/20157/20/20157/20/2015PFAIL
DetailsThomas Walsh
Called in for a fire/life-safety inspection. Started with exit signage and emergency egress lighting test, but noted too many units not operating properly, including some exit signs that batteries were not charged, and many EM lights not working. Contractor was asked to pretest all EM lights and exit signs prior to rescheduling another inspection.
Many of the stairs are still under flooring work and many were not accessible.
Print Occupancy Form  7/14/2015 DONE
BLD-Ceiling Grid Inspection6/16/20156/17/20156/17/2015APASS
DetailsDave Hannah
Corridor and ceiling grid Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Energy code compliance5/27/20155/27/20155/27/2015PNR
DetailsMike Jordan
Corridor Fire caulking and grid inspection Phone #: ###-#### Inspection requested via web by Julian Lopez. 2nd floor, west and northcorridors, complete fire caulking and provide UL rated assembly for low voltage exiting the smurf tubes and steel conduits.
BLD-Conference5/8/20155/8/20155/11/2015PPASS
DetailsDave Hannah
Stairwell fire rating. Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Framing/Rough-in4/24/20154/24/20154/24/2015PPASS
DetailsDave Hannah
level 4 fire caulk inspection. Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Other4/23/20154/24/20154/24/2015ANR
DetailsDave Hannah
level 4 fire caulk inspection. Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Energy code compliance4/2/20154/2/20154/3/2015PPASS
DetailsDave Hannah
Level 4 Phone #: ###-#### Inspection requested via web by Julian Lopez
FIRE-Conference4/2/20154/2/20154/2/2015PDONE
DetailsForrest France
Regarding project related fire sprinkler work.
BLD-Energy code compliance3/27/20153/27/20153/27/2015PPASS
DetailsDave Hannah
Area 2 level 3 check fire caulking at soffit. Check stair well drywall. Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Framing/Rough-in3/26/20153/26/20153/27/2015PPART
DetailsDave Hannah
Area 2 level 4 framing Phone #: ###-#### Inspection requested via web by Julian Lopezok to insulate ceiling
BLD-Energy code compliance3/18/20153/18/20153/19/2015PPASS
DetailsDave Hannah
Area 2 level 2 inspect plumbing fire caulking in soffits. Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Energy code compliance3/16/20153/17/20153/17/2015APASS
DetailsDave Hannah
Area 2 lvl 4. rest of lvl 3 inspection. Also inspect lvl 4 shower pan fire caulking. Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Energy code compliance3/12/20153/12/20153/13/2015PPASS
DetailsDave Hannah
Area 2 lvl 3 insulation. Shower pan fire caulk area 2 lvl 4. Area 2 lvl 4 corridor insulation. South west stair wall framing area 2 lvl 4. Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Energy code compliance3/12/20153/12/20153/12/2015APASS
DetailsDave Hannah
BLD-Energy code compliance3/11/20153/11/20153/11/2015APASS
DetailsDave Hannah
Area 2 lvl 3.insulation and check shower pan fire caulking. Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Energy code compliance3/10/20153/10/20153/11/2015APASS
DetailsDave Hannah
Level 3 partial - Julian ###-####
BLD-Framing/Rough-in3/10/20153/10/20153/11/2015APART
DetailsDave Hannah
dywall, taping & fire caulking - Julian Phone #: ###-####
BLD-Framing/Rough-in3/9/20153/9/20153/10/2015PPART
DetailsDave Hannah
dry wall taping & fire wall Julian ###-####
BLD-Framing/Rough-in3/9/20153/9/20153/10/2015APASS
DetailsDave Hannah
Level 4 exterior walls and corridor Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Framing/Rough-in3/6/20153/6/20153/6/2015PCANC
DetailsDave Hannah
Exterior wall framing lvl 4. Corridor fire caulk Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Framing/Rough-in3/4/20153/4/20153/4/2015APASS
DetailsDave Hannah
Level 3 framing Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Framing/Rough-in3/2/20153/3/20153/4/2015APART
DetailsDave Hannah
Framing lvl3 includes corridors. Phone #: ###-#### Inspection requested via web by Julian Lopez ok to insulate ext wall and ceiling only
BLD-Framing/Rough-in2/25/20152/25/20152/26/2015APART
DetailsDave Hannah
Lvl 2 framing
lvl 3 outer walls. Phone #: ###-#### Inspection requested via web by Julian Lopez rooms 221 theu 228 ok to cover.
BLD-Framing/Rough-in2/24/20152/24/20152/25/2015PPART
DetailsDave Hannah
Lvl 2 framing
lvl 3 outer walls. Phone #: ###-#### Inspection requested via web by Julian Lopez 3rd floor ok to insulate ext walls
BLD-Framing/Rough-in2/20/20152/23/20152/24/2015ANR
DetailsDave Hannah
Frame rough in. lvl 2..
Outer walls lvl 3. Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Framing/Rough-in2/19/20152/20/20152/20/2015APART
DetailsJim Storey
Inspect rough frame lvl 2. Inspect drywall on lvl 4. Look at lvl 1 soffit Phone #: ###-#### Inspection requested via web by Julian Lopezinsulation 2nd floor coridor ok gyp 3 layer ok/ interior poduim soffit ok// exterior soffit 3 hr not extending thru soffit. rfi.
BLD-Conference2/17/20152/18/20152/18/2015APART
DetailsDave Hannah
Framing inspection level 2 outer walls. Phone #: ###-#### Inspection requested via web by Julian Lopez ok to insulate ext walls.
BLD-Conference2/17/20152/18/20152/17/2015ACANC
DetailsDave Hannah
Exterior wall framing inspection. Phone #: ###-#### >> Inspection requested via web by Julian Lopez Inspection cancelled from web by: Julian Lopez
BLD-Conference2/10/20152/11/20152/12/2015PPASS
DetailsDave Hannah
Consultation Fire caulking and rating Phone #: ###-#### Inspection requested via web by Julian Lopez
BLD-Framing/Rough-in1/30/20151/30/20151/30/2015PPART
DetailsDave Hannah
Check corridor lvl 4 Phone #: ###-#### Inspection requested via web by Julian Lopez ok to insulate ceiling 4th floor corridor.
BLD-Wall Bracing1/27/20151/27/20151/27/2015APART
DetailsDave Hannah
ok to cover ext
BLD-Conference12/22/201412/23/201412/23/2014ADONE
DetailsDave Hannah
I''m requesting a conference at 10;00 am to discuss fire rated issues and concerns with all the subs on the job.
Thank you. Phone #: ###-#### Inspection requested via web by Tony Inserra
BLD-Other12/16/201412/17/201412/17/2014PNR
DetailsDave Hannah
Requesting a roof sheeting OSB nailing inspection. Thanks Tony. Phone #: ###-#### Inspection requested via web by Tony Inserra
BLD-Framing/Rough-in11/26/201411/26/201411/28/2014PPART
DetailsDave Hannah
We are going to start setting windows they have the vinyl nailing flang, requesting partial sheer nailing inspection.
Thank you. Phone #: ###-#### Inspection requested via web by Tony Inserra first floor ok to set windows
BLD-Conference10/27/201410/28/201410/28/2014APASS
DetailsDave Hannah
Building conference to talk about rated wall assemblies. Phone #: ###-#### Inspection requested via web by Tony Inserra
Permit Ready to Issue  10/3/2014 DONE
DetailsCandy A. Nichols
Issue PAID IN FULL permit  10/3/2014 DONE
DetailsCandy A. Nichols
Print Occupancy Form  10/3/2014 DONE
DetailsCandy A. Nichols
PLANS/APPL TAKEN TO FRONT DESK  10/2/2014 DONE
DetailsJohn Menard
Plan assigned to (JCM)7/14/2014 10/2/2014 PASS
DetailsJohn Menard
1st Review Complete 8/21/2014 - West Sherwood Apartments
Routing PW Sewer Rating9/29/2014 9/29/2014 PASS
DetailsBeverly Mountain
Routing - PLAN CHECK9/3/2014 9/17/2014 FAIL
DetailsJohn Menard
Routing - Design Review9/3/2014 9/5/2014 PASS
DetailsJosh Wilson
Corrected elevations have been uploaded.
Routing PW Street Lights9/3/2014 9/4/2014 FAIL
DetailsMike D Hedge
Routing - MECHANICAL9/3/2014 9/3/2014 PASS
DetailsTroy James
Routing - PLUMBING9/3/2014 9/3/2014 PASS
DetailsBill VanDegrift
Routing - Addressing9/3/2014 9/3/2014 PASS
DetailsEmily Dixon
1st review completed  8/21/2014 DONE
DetailsJohn Menard
Routing - PLAN CHECK7/14/2014 8/21/2014 FAIL
DetailsJohn Menard
Routing - Design Review7/14/2014 8/4/2014 FAIL
DetailsJosh Wilson
Upload new sheets A201 and A202 showing corrugated metal siding
Routing - PLUMBING7/14/2014 7/24/2014 FAIL
DetailsDaryl Spivey
see bld14-01936
Routing - PLANNING7/14/2014 7/21/2014 PASS
DetailsJoshua Johnson
Routing - FIRE7/14/20147/14/20147/18/2014 PASS
DetailsScott Arellano
Attached comments to case.
Routing Off Site - STRUCTURAL7/14/2014 7/18/2014 PASS
DetailsJohn Menard
Routing - PUBLIC WORKS7/14/2014 7/17/2014 PASS
DetailsBeverly Mountain
Routing PW Sewer Rating7/17/2014 7/17/2014 PASS
DetailsBeverly Mountain
Routing - Addressing7/14/2014 7/16/2014 FAIL
DetailsEmily Dixon
Apartment addresses need to be identifed on plans. Room numbers identifed currently do not meet BoiseCity addressing code. Jason Taylor ###-####
Route to Impact Fee Review7/14/20147/17/20147/14/2014 PASS
DetailsCindy M. Gould
Intake Approval  7/14/2014 PASS
DetailsJohn Menard
Pending Assignment by JCM7/14/2014 7/14/2014 DONE
DetailsJohn Menard
Application received  7/8/2014 DONE
Application submitted via PDS Online on Jul 8 2014 2:56PM