Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD14-01951
StatusFinaled
Name BOISE CITY GOVERNMENT BUILDINGS
Site Address 150 N CAPITOL BLVD
Project NameCity Hall Bldg #1 - 4th floor
Customer Number 
ePlanReviewNo
Description
(CITY OF BOISE – 4th Floor Public Works – 11 ft. wall) Permit is to remodel City Hall Building #1 by adding a new 11ft. non-bearing wall on fourth floor in place of a counter. Approval per approved plans on file. Work to include: construction of one wall, demolition of counter, and interior finishes in compliance with chapter 8 of the 2009 IBC. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 12/6/201412/12/2014 DONE
Print Statement  12/12/2014 DONE
Second Notice 11/13/201412/1/2014 DONE
DetailsChristina Prado
First Notice10/15/201410/15/201411/3/2014 DONE
DetailsDave Hannah
interoffice mail to Scott Canning
BLD-Final10/15/201410/15/201410/15/2014PPASS
DetailsDave Hannah
DOC - Permit Finaled10/15/201410/15/201410/15/2014PPASS
DetailsDave Hannah
BLD-Wall cover10/15/201410/15/201410/15/2014PPASS
DetailsDave Hannah
Please call 30min ahead - Keith Phone #: ###-####
FIRE-Final Inspection9/15/20149/15/20149/15/2014PPASS
DetailsForrest France
Fire life safety finaled.
FIRE-Final Inspection9/2/20149/3/20149/3/2014AFAIL
DetailsForrest France
Modifications to existing fire sprinkler coverage will be necessary due to remodel work. Remainder of life safety items appear satisfactory.
BLD-Framing/Rough-in8/8/20148/8/20148/8/2014PPASS
DetailsDave Hannah
Please call ahead to meet - Keith Phone #: ###-####
Issue PAID IN FULL permit  7/16/2014 DONE
DetailsChristina Prado
Plan assigned to (TLW)7/10/2014 7/11/2014 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK7/10/2014 7/11/2014 PASS
DetailsTim L. Woodard
1st review completed  7/11/2014 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  7/11/2014 DONE
DetailsTim L. Woodard
Case Summary (BLD)  7/11/2014 DONE
DetailsTim L. Woodard
Inspection Record Card- Bld  7/11/2014 DONE
DetailsChristina Prado
Permit Ready to Issue  7/11/2014 DONE
DetailsTisha Gallop
Telephone call  7/11/2014 DONE
DetailsTisha Gallop
called Scott Canning and left vm permit is ready, fee due. Need JV info before issue permit.
Plans ACCEPTED BY PLAN TECH  7/10/2014 DONE
DetailsChristina Prado
Intake Approval  7/10/2014 PASS
DetailsTim L. Woodard
Recd Pcfee & Taken To Pln CK  7/10/2014 DONE
DetailsChristina Prado
Application received  7/9/2014 DONE
Application submitted via PDS Online on Jul 9 2014 4:24PM