Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberBLD14-01989
StatusFinaled
Name ARTISAN CUSTOM CARPENTRY AND RENOVA
Site Address 1009 W MAIN ST
Project NameMulligans 2nd Floor Remodel
Customer Number 
ePlanReviewYes
Description
(Mulligans)Remodel former 2nd floor hotel space into event center with bar, new restrooms, elevator, exterior stair and landing, plumbing, upgrade HVAC and electrical, structural upgrades, fire sprinkler and alarm system. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  2/21/2017 DONE
Third Notice 9/19/20159/29/2015 DONE
This permit finaled on the web by Ryan Allen
Third Notice 8/15/20159/14/2015 DONE
Second Notice 7/19/20158/10/2015 DONE
DetailsChristina Prado
mailed 8/11/15
First Notice 6/21/20157/9/2015 DONE
Mailed 7-10-15
BLD-Final6/9/20156/11/20156/11/2015APASS
DetailsJim Sly
Please come as early as possible as the building owners would like to open for business the same evening.
Thank you. Phone #: ###-#### Inspection requested via web by Ryan Allen
OK for Perm Occ.
Permanent Occupancy  6/11/2015 DONE
FIRE-Final Inspection6/9/20156/10/20156/10/2015PPASS
DetailsJim Page
Life fire safety passed/complete
Zoning Approval6/10/20156/10/20156/10/2015 DONE
DetailsAndrea Tuning
BLD-Framing/Rough-in2/24/20152/25/20152/25/2015PPASS
DetailsDave Hannah
Inspection of framing prior to insulation and sheetrock. Phone #: ###-#### Inspection requested via web by Ryan Allen
BLD-Framing/Rough-in2/10/20152/11/20152/12/2015APASS
DetailsDave Hannah
inspection of strapping to go under roofing material. After speaking with the roofers around 10 or 1030 would be perfect. Thank you Phone #: ###-#### Inspection requested via web by Ryan Allen
BLD-Conference1/23/20151/26/20151/26/2015APASS
DetailsDave Hannah
Inspection of exterior of light wells prior to cover. Phone #: ###-#### Inspection requested via web by Ryan Allen
BLD-Framing/Rough-in1/8/20151/8/20151/8/2015APASS
DetailsDave Hannah
BLD-Conference1/7/20151/8/20151/8/2015APASS
DetailsDave Hannah
Last inspection on floor framing prior to covering Phone #: ###-#### Inspection requested via web by Ryan Allen
BLD-Framing/Rough-in12/23/201412/26/201412/26/2014APASS
DetailsJim Storey
Inspection on third portion of floor framing Phone #: ###-#### Inspection requested via web by Ryan Allen
BLD-Framing/Rough-in12/9/201412/9/201412/9/2014PPASS
DetailsDave Hannah
Inspection of 2nd portion of floor framing prior to cover Phone #: ###-#### Inspection requested via web by Ryan Allen
BLD-Framing/Rough-in12/1/201412/2/201412/2/2014APASS
DetailsDave Hannah
Inspection of floor framing for first portion of second floor remodel prior to cover.
Phone #: ###-#### Inspection requested via web by Ryan Allen
BLD-Framing/Rough-in11/11/201411/12/201411/12/2014APART
DetailsDave Hannah
Courtesy inspect on columns installed into basement through existing business. Need to cover ASAP. Thanks you. Phone #: ###-#### Inspection requested via web by Ryan Allen ok to cover four front columns on ground floor
BLD-Conference10/30/201410/31/201410/31/2014APASS
DetailsDave Hannah
Ryan Phone #: ###-####
Print Occupancy Form  10/16/2014 DONE
DetailsTisha Gallop
Reopen Permit (ISS)  10/16/2014 DONE
DetailsTisha Gallop
received ACHD and customer came and picked up permit
OVERRIDE  10/13/2014  
Permit Ready to Issue  10/13/2014 DONE
DetailsTisha Gallop
OVERRIDE  10/9/2014  
Issue PAID IN FULL permit  10/9/2014 DONE
Print Occupancy Form  10/9/2014 DONE
DetailsTisha Gallop
CHANGE STATUS TO (FEE)  10/9/2014 DONE
DetailsTisha Gallop
Permit issued by mistake, still need ACHD
Permit Ready to Issue  10/9/2014 DONE
PLANS/APPL TAKEN TO FRONT DESK  10/6/2014 DONE
Routing Off Site - STRUCTURAL9/4/2014 10/6/2014 PASS
DetailsCarl D Madsen
Plan assigned to (CDM)7/22/2014 10/6/2014 PASS
DetailsCarl D Madsen
Mulligan's First review completed.
Routing Off Site - STRUCTURAL9/18/2014 10/3/2014  
DetailsCarl D Madsen
Routing - PLAN CHECK9/4/2014 9/19/2014 PASS
DetailsCarl D Madsen
Routing - Design Review9/18/2014 9/18/2014 PASS
DetailsAndrea Tuning
Routing - Design Review9/4/2014 9/4/2014 FAIL
DetailsAndrea Tuning
The elevations sheet should be modified to have aluminum clad windows as opposed to vinyl windows.
Route to Impact Fee Review8/18/20148/21/20148/21/2014 PASS
DetailsDonna Wolf
Deleted fees under $50.00
1st review completed  8/11/2014 FAIL
Routing - PLAN CHECK7/22/2014 8/11/2014 FAIL
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL7/22/2014 8/11/2014 FAIL
DetailsCarl D Madsen
Routing - FIRE7/22/2014 7/29/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review 07-29-14
Routing - PLUMBING7/22/2014 7/24/2014 PASS
DetailsDaryl Spivey
Install a RPBP on filtered water system.
Routing - PLANNING Land Div7/22/2014 7/23/2014 PASS
DetailsDave Abo
Routing - Erosion and Sediment7/22/2014 7/23/2014 PASS
DetailsEvan Jenkins
Routing PW Sewer Rating7/22/2014 7/23/2014 PASS
DetailsJennifer Bruner
Routing - PUBLIC WORKS7/22/2014 7/22/2014 PASS
DetailsBeverly Mountain
Routing - Design Review7/22/2014 7/22/2014 FAIL
DetailsAndrea Tuning
The windows located on the second floor on the Main Street elevation shall not be vinyl. The may be constructed of aluminum, aluminum clad or wood.
Intake Approval  7/22/2014 PASS
DetailsJohn Menard
Intake Approval  7/17/2014 FAIL
DetailsAdele J Schaffeld-Griffin
7/14/14-Please see the revised mark up's on the check list of the items that are still outstanding.

7/16/14-Please see the mark up's on the check list and submit the additional information.
Plan Reviewer's activity  7/16/2014 DONE
DetailsAdele J Schaffeld-Griffin
DR ok with intake per Sarah S.
Intake Approval  7/16/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Please see the mark up's on the check list and submit the additional information.
Application received  7/11/2014 DONE
Application submitted via PDS Online on Jul 11 2014 4:54PM
Pending Assignment by JCM7/22/2014    
DetailsJohn Menard