BLD-Final | 3/20/2015 | 3/23/2015 | 3/23/2015 | A | PASS |
Tony Young
|
|
|
Jeremy Phone #: ###-####
|
DOC - Permit Finaled | 3/23/2015 | 3/23/2015 | 3/23/2015 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 3/19/2015 | 3/20/2015 | 3/20/2015 | P | PART |
Tony Young
|
|
|
Jeremy Phone #: ###-####,, ok pending hillside
|
PubWorks Occupancy Approval | 3/20/2015 | 3/20/2015 | 3/20/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Energy code compliance | 12/30/2014 | 12/31/2014 | 12/31/2014 | A | PASS |
Tony Young
|
|
|
Jeremy-call 1 hr prior for access Phone #: ###-####
|
BLD-Framing/Rough-in | 12/29/2014 | 12/30/2014 | 12/30/2014 | P | PART |
Tony Young
|
|
|
Jeremy-call 1 hr prior for access Phone #: ###-####,, need sprinkler approval
|
BLD-Framing/Rough-in | 12/30/2014 | 12/30/2014 | 12/30/2014 | A | PASS |
Tony Young
|
|
|
Jeremy-call 1 hr prior for access Phone #: ###-####,, ok to insulate,, needs one more sprinkler inspection
|
BLD-Framing/Rough-in | 12/23/2014 | 12/24/2014 | 12/24/2014 | A | PART |
Tony Young
|
|
|
Jeremy-please call 1 hr prior to meet Phone #: ###-####,, will need final approval from fire for sprinkler cover,, will be putting in a fire place also,, ok to insulate
|
BLD-Other | 12/17/2014 | 12/18/2014 | 12/18/2014 | A | PASS |
Jim Sly
|
|
|
fire soffit - Jeremy Phone #: ###-#### All openings protected at fire rated soffits.
|
BLD-Wall Bracing | 12/10/2014 | 12/11/2014 | 12/11/2014 | A | DONE |
Tony Young
|
|
|
sheer//Lauren Phone #: ###-####,, wrong address called in
|
Plan Modification Accepted | | | 12/5/2014 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 12/5/2014 | | 12/5/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Wall Bracing | 11/20/2014 | 11/21/2014 | 11/21/2014 | A | PART |
Tony Young
|
|
|
Jeremy Phone #: ###-####,, work in progress,, ok
|
BLD-Footing | 9/24/2014 | 9/24/2014 | 9/24/2014 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ben Sears,, side retaining ftg and wall ok,, foundation ok also
|
BLD-Footing | 9/23/2014 | 9/24/2014 | 9/24/2014 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ben Sears,, need modification and subgrade report
|
BLD-Foundation | 9/23/2014 | 9/23/2014 | 9/23/2014 | P | CANC |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ben Sears
|
BLD-Footing | 9/18/2014 | 9/18/2014 | 9/18/2014 | P | PASS |
Phil Shearer
|
|
|
Ben Phone #: ###-####
|
PubWorks Subgrade Approval | 9/16/2014 | 9/16/2014 | 9/16/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
(F) Reprint permit | | | 9/3/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue PAID IN FULL permit | | | 9/3/2014 | | DONE |
Candy A. Nichols
|
|
|
|
OVERRIDE | | | 9/2/2014 | | |
|
|
|
|
Plan assigned to (AJS) | 8/13/2014 | 8/13/2014 | 9/2/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed 8/21 TH L2 Hilside ePlan**
|
Routing - PLAN CHECK | 8/28/2014 | | 9/2/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/2/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/2/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/2/2014 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 8/28/2014 | | 8/29/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
1st review completed | | | 8/21/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 8/13/2014 | | 8/21/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see change marks in e plan
|
Routing - FIRE | 8/13/2014 | | 8/18/2014 | | PASS |
Scott Arellano
|
|
|
This structure is required to be fire sprinklered in accordance with NFPA 13D; a separate permit is required. This structure is also subject to the WUI provisions regarding defensible space. Refer to BMC 7-01-69 section 4920 for details.
|
Routing PW Grading-Hillside | 8/13/2014 | | 8/14/2014 | | FAIL |
Jason C. Taylor
|
|
|
Need grading plan signed by engineer.
|
Routing - Erosion and Sediment | 8/13/2014 | | 8/13/2014 | | PASS |
Evan Jenkins
|
|
|
Site Prep Inspection Required Prior to Earth Disturbance
|
Plan assigned to (JG) | 8/4/2014 | | 8/13/2014 | | DEFR |
Javier Guzman
|
|
|
8/21 TH L2 Hilside ePlan**
|
Routing - Addressing | 8/4/2014 | | 8/4/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/1/2014 | | 8/4/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - MECHANICAL | 8/4/2014 | | 8/4/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/4/2014 | | 8/4/2014 | | PASS |
Sue Cummings
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/4/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 8/4/2014 | | PASS |
Jason Blais
|
|
|
|
Intake Approval | | | 7/30/2014 | | FAIL |
Christina Prado
|
|
|
|
Application received | | | 7/23/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 23 2014 11:56AM
|