Permit Information
Permit NumberBLD14-02138
StatusFinaled
Name ESI
Site Address 2755 S BEVERLY ST
Project NameProject Beverly - Shop
Customer Number 
ePlanReviewYes
Description
(BEVERLY STREET PROJECT)Permit to grub, clean, excavate, grade, import and compact site earth materials in preparation for the future construction of new buildings. To install curb, gutter and paving in accordance with the grading and drainage plans approved by the Public Works Department. Related underground site utilities included in this scope of work. NO CONSTRUCTION IS ALLOWED UNDER THIS PERMIT. Reference DRH14-00158 for planning approval.///C_P
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval4/26/20164/26/20164/26/2016 DONE
DetailsTiffany Lowery
Case Summary (BLD)  3/30/2015 DONE
BLD-Final3/26/20153/27/20153/27/2015APASS
DetailsPhil Shearer
Kurtis Phone #: ###-####
FIRE-Final Inspection3/26/20153/27/20153/27/2015APASS
DetailsTroy Cobbley
LIfe safety passed
DOC - Permit Finaled  3/27/2015 DONE
BLD-Conference3/26/20153/26/20153/26/2015PDONE
DetailsPhil Shearer
Curtis Phone #: ###-####
BLD-Concrete11/5/201411/6/201411/6/2014PPASS
DetailsPhil Shearer
Rebar inspection- North side of office bldg. Phone #: ###-#### Inspection requested via web by Philip Allen
BLD-Concrete11/4/201411/5/201411/5/2014PPASS
DetailsPhil Shearer
Slab on Grade rebar Phone #: ###-#### Inspection requested via web by Philip Allen
OVERRIDE  8/19/2014  
Inspection Record Card- Bld  8/19/2014 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  8/19/2014 DONE
DetailsChristina Prado
Routing - PLAN CHECK8/18/2014 8/19/2014 PASS
DetailsTisha Gallop
PLANS/APPL TAKEN TO FRONT DESK  8/19/2014 DONE
DetailsTisha Gallop
Permit Ready to Issue  8/19/2014 DONE
DetailsChristina Prado
Plan assigned to Christina7/29/2014 8/19/2014 DEFR
DetailsChristina Prado
deferred to Tisha Gallop
Plan assigned to (LEG) Tisha8/11/2014 8/19/2014 DONE
DetailsTisha Gallop
Routing PW Drainage8/18/2014 8/18/2014 PASS
DetailsJason C. Taylor
Routing - PLAN CHECK8/8/2014 8/14/2014 PASS
DetailsTisha Gallop
failed PW Drainage, sent changemarks to applicant to resubmit
Routing - FIRE8/8/20148/8/20148/13/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 1 08-13-14
Routing - PUBLIC WORKS GRADING8/8/2014 8/13/2014 FAIL
DetailsJason C. Taylor
Please see changemarks in ePlan. Jason Taylor
Routing - PLAN CHECK7/29/2014 8/8/2014 DEFR
DetailsChristina Prado
Pending approvals from Fire and Drainage
Routing - FIRE7/29/20147/29/20148/5/2014 FAIL
DetailsCraig D. Hanson
See Fire Plan Review 08-05-14
Routing - PLANNING Land Div7/29/2014 8/5/2014 PASS
DetailsDave Abo
Routing PW Street Lights7/30/2014 7/30/2014 PASS
DetailsMike D Hedge
Street lights required, must be included in permit for building construction.
Routing PW Drainage7/30/2014 7/30/2014 FAIL
DetailsJason C. Taylor
Please see all changemark notes in eplan. Jason Taylor ###-####.
Routing - PUBLIC WORKS7/29/2014 7/30/2014 PASS
DetailsBeverly Mountain
Routing - Erosion and Sediment7/29/2014 7/30/2014 PASS
DetailsEvan Jenkins
Site Prep Inspection and Approval Required Prior to Any Earth Disturbance.
Plans ACCEPTED BY PLAN TECH  7/29/2014 DONE
DetailsChristina Prado
Intake Approval  7/29/2014 PASS
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  7/29/2014 DONE
DetailsChristina Prado
Routing - PLANNING7/29/2014 7/29/2014 PASS
DetailsJosh Wilson
Routing - Addressing7/29/2014 7/29/2014 PASS
DetailsEmily Dixon
Application received  7/28/2014 DONE
Application submitted via PDS Online on Jul 28 2014 11:15AM