PubWorks Occupancy Approval | 4/26/2016 | 4/26/2016 | 4/26/2016 | | DONE |
Tiffany Lowery
|
|
|
|
Case Summary (BLD) | | | 3/30/2015 | | DONE |
|
|
|
|
BLD-Final | 3/26/2015 | 3/27/2015 | 3/27/2015 | A | PASS |
Phil Shearer
|
|
|
Kurtis Phone #: ###-####
|
FIRE-Final Inspection | 3/26/2015 | 3/27/2015 | 3/27/2015 | A | PASS |
Troy Cobbley
|
|
|
LIfe safety passed
|
DOC - Permit Finaled | | | 3/27/2015 | | DONE |
|
|
|
|
BLD-Conference | 3/26/2015 | 3/26/2015 | 3/26/2015 | P | DONE |
Phil Shearer
|
|
|
Curtis Phone #: ###-####
|
BLD-Concrete | 11/5/2014 | 11/6/2014 | 11/6/2014 | P | PASS |
Phil Shearer
|
|
|
Rebar inspection- North side of office bldg. Phone #: ###-#### Inspection requested via web by Philip Allen
|
BLD-Concrete | 11/4/2014 | 11/5/2014 | 11/5/2014 | P | PASS |
Phil Shearer
|
|
|
Slab on Grade rebar Phone #: ###-#### Inspection requested via web by Philip Allen
|
OVERRIDE | | | 8/19/2014 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/19/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 8/19/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 8/18/2014 | | 8/19/2014 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/19/2014 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 8/19/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to Christina | 7/29/2014 | | 8/19/2014 | | DEFR |
Christina Prado
|
|
|
deferred to Tisha Gallop
|
Plan assigned to (LEG) Tisha | 8/11/2014 | | 8/19/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing PW Drainage | 8/18/2014 | | 8/18/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PLAN CHECK | 8/8/2014 | | 8/14/2014 | | PASS |
Tisha Gallop
|
|
|
failed PW Drainage, sent changemarks to applicant to resubmit
|
Routing - FIRE | 8/8/2014 | 8/8/2014 | 8/13/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 08-13-14
|
Routing - PUBLIC WORKS GRADING | 8/8/2014 | | 8/13/2014 | | FAIL |
Jason C. Taylor
|
|
|
Please see changemarks in ePlan. Jason Taylor
|
Routing - PLAN CHECK | 7/29/2014 | | 8/8/2014 | | DEFR |
Christina Prado
|
|
|
Pending approvals from Fire and Drainage
|
Routing - FIRE | 7/29/2014 | 7/29/2014 | 8/5/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 08-05-14
|
Routing - PLANNING Land Div | 7/29/2014 | | 8/5/2014 | | PASS |
Dave Abo
|
|
|
|
Routing PW Street Lights | 7/30/2014 | | 7/30/2014 | | PASS |
Mike D Hedge
|
|
|
Street lights required, must be included in permit for building construction.
|
Routing PW Drainage | 7/30/2014 | | 7/30/2014 | | FAIL |
Jason C. Taylor
|
|
|
Please see all changemark notes in eplan. Jason Taylor ###-####.
|
Routing - PUBLIC WORKS | 7/29/2014 | | 7/30/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 7/29/2014 | | 7/30/2014 | | PASS |
Evan Jenkins
|
|
|
Site Prep Inspection and Approval Required Prior to Any Earth Disturbance.
|
Plans ACCEPTED BY PLAN TECH | | | 7/29/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 7/29/2014 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/29/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLANNING | 7/29/2014 | | 7/29/2014 | | PASS |
Josh Wilson
|
|
|
|
Routing - Addressing | 7/29/2014 | | 7/29/2014 | | PASS |
Emily Dixon
|
|
|
|
Application received | | | 7/28/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 28 2014 11:15AM
|