BLD-Final | 12/26/2014 | 12/26/2014 | 12/26/2014 | P | PASS |
Phil Shearer
|
|
|
Call Dan for access Phone #: ###-#### Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 12/26/2014 | 12/26/2014 | 12/26/2014 | P | PASS |
Phil Shearer
|
|
|
|
PubWorks Occupancy Approval | 12/24/2014 | 12/24/2014 | 12/24/2014 | | DONE |
Jason C. Taylor
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Energy code compliance | 11/4/2014 | 11/4/2014 | 11/4/2014 | P | PASS |
Tony Young
|
|
|
Dan Appel Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 11/3/2014 | 11/4/2014 | 11/4/2014 | A | PASS |
Tony Young
|
|
|
Dan Appel Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 10/30/2014 | 11/3/2014 | 11/3/2014 | P | PART |
Tony Young
|
|
|
Dan Appel Phone #: ###-#### Inspection requested via web by Daniel Appel,, frame ok,, ok to insulate
|
BLD-Framing/Rough-in | 10/28/2014 | 10/29/2014 | 10/29/2014 | A | PART |
Tony Young
|
|
|
Late AM please call Dan when 30 minutes out Phone #: ###-#### Inspection requested via web by Daniel Appel,, need to provide fire blocking at ceiling lines,, strap plates ,, carry roof load direct on single top plates,, ok to insulate
|
BLD-Conference | 10/27/2014 | 10/27/2014 | 10/27/2014 | P | DONE |
Phil Shearer
|
|
|
Question regarding Canned lights in fire rated soffitt areas. You could call my electrician, Bob Schroder ###-#### in lieu of a site visit Phone #: ###-#### Inspection requested via web by Daniel Appel
|
Plan Modification Accepted | | | 10/27/2014 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 10/27/2014 | | 10/27/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Conference | 10/23/2014 | 10/23/2014 | 10/23/2014 | P | PASS |
Tony Young
|
|
|
Dan ###-####,, ? on drilling for wires
|
BLD-Wall Bracing | 10/20/2014 | 10/21/2014 | 10/21/2014 | A | PASS |
Tony Young
|
|
|
Dan Appel Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Wall Bracing | 10/17/2014 | 10/20/2014 | 10/20/2014 | A | PEND |
Tony Young
|
|
|
Dan Appel Phone #: ###-#### Inspection requested via web by Daniel Appel,, need to see if plans show shear walls,, called Dan
|
BLD-Foundation | 9/22/2014 | 9/23/2014 | 9/23/2014 | P | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, work in progress,, ok basement walls
|
BLD-Footing | 9/17/2014 | 9/18/2014 | 9/18/2014 | P | PASS |
Phil Shearer
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 9/16/2014 | 9/17/2014 | 9/17/2014 | A | NR |
Tony Young
|
|
|
Dane Phone #: ###-####,, late
|
BLD-Footing | 9/16/2014 | 9/16/2014 | 9/16/2014 | P | NR |
Tony Young
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 9/15/2014 | 9/16/2014 | 9/16/2014 | A | NR |
Tony Young
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 9/12/2014 | 9/15/2014 | 9/15/2014 | P | NR |
Tony Young
|
|
|
Dane Phone #: ###-####
|
PubWorks Subgrade Approval | 9/15/2014 | 9/15/2014 | 9/15/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 8/29/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/29/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 8/29/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 8/29/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 8/13/2014 | 8/13/2014 | 8/21/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed 8/19 T L2 Hillside ePlan**
|
Routing - PLANNING | 8/21/2014 | | 8/21/2014 | | PASS |
David Moser
|
|
|
|
Routing - PLAN CHECK | 8/21/2014 | | 8/21/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/21/2014 | | DONE |
|
|
|
|
1st review completed | | | 8/18/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 8/13/2014 | | 8/18/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see change marks in e plan
|
Plan assigned to (JG) | 8/1/2014 | 8/1/2014 | 8/13/2014 | | DEFR |
Javier Guzman
|
|
|
8/19 T L2 Hillside ePlan**
|
Routing - FIRE | 8/1/2014 | 8/1/2014 | 8/8/2014 | | PASS |
Scott Arellano
|
|
|
This structure has been evaluated for FD vehicle access. This structure shall comply with the provisions for defensible space as defined in BMC 7-01-69 section 4920 and be subject to periodic inspection by Boise Fire department Wildland Urban Interface mitigation team.
|
Routing PW Grading-Hillside | 8/1/2014 | | 8/5/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - MECHANICAL | 8/1/2014 | | 8/5/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/1/2014 | | 8/1/2014 | | FAIL |
David Moser
|
|
|
need to show the covered patio posts on site plan to confirm setbacks.
|
Routing - Addressing | 8/1/2014 | | 8/1/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/1/2014 | | 8/1/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Case Summary (BLD) | | | 8/1/2014 | | DONE |
|
|
|
|
Intake Approval | | | 8/1/2014 | | PASS |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/1/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Erosion and Sediment | 8/1/2014 | | 8/1/2014 | | PASS |
Evan Jenkins
|
|
|
Site Prep Inspection Required Prior to Earth Disturbance
|
Intake Approval | | | 7/30/2014 | | FAIL |
Christina Prado
|
|
|
Need engineering stamp on foundation, wall detail
|
Application received | | | 7/29/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 29 2014 11:17AM
|