Third Notice | | 6/14/2015 | 7/8/2015 | | DONE |
|
|
|
|
Third Notice | | 5/10/2015 | 6/9/2015 | | DONE |
|
|
|
|
Second Notice | | 3/13/2015 | 5/5/2015 | | DONE |
|
|
|
mailed 5-5-15
|
Telephone call | | | 3/16/2015 | | DONE |
Candy A. Nichols
|
|
|
called to try and get revised address-the one we have on file came back as undeliverable-left message on Johns phone
|
First Notice | | 2/19/2015 | 3/3/2015 | | DONE |
|
|
|
mailed 3-3-15
|
Permanent Occupancy | | | 2/9/2015 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 2/6/2015 | 2/6/2015 | 2/6/2015 | P | PASS |
Mike Jordan
|
|
|
Ok for perm occ.
|
BLD-Final | 2/5/2015 | 2/6/2015 | 2/6/2015 | A | NR |
Mike Jordan
|
|
|
John Phone #: ###-####. Needs to mpull plumbing permit for drinking fountain.
|
FIRE-Final Inspection | 2/5/2015 | 2/5/2015 | 2/5/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Telephone call | | | 1/26/2015 | | DONE |
Candy A. Nichols
|
|
|
called Pat Keegan to let know the temp c of o is getting close to expiring. He said he'c contact owners and see if it's ready and have them call it in
|
BLD-Framing/Rough-in | 11/28/2014 | 11/28/2014 | 11/28/2014 | A | PASS |
Jim Sly
|
|
|
john ###-####
|
Temporary Occupancy | 11/17/2014 | 2/15/2015 | 11/17/2014 | | DONE |
Kristal Soland
|
|
|
|
BLD-Final | 11/10/2014 | 11/12/2014 | 11/12/2014 | P | PART |
Mike Jordan
|
|
|
John Hyne Phone #: ###-####(please make notes if not need electrical, plumbing and mechanical to sign off on temp). ok for temp occ. during ti work.
|
FIRE-Final Inspection | 11/10/2014 | 11/12/2014 | 11/12/2014 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given with Scotts approval until the final build out of the tenant space is complete. I verified fire extinguishers, existing door hardware and exit/emergency lighting.
|
BLD-Final | 11/6/2014 | 11/7/2014 | 11/7/2014 | P | NR |
Mike Jordan
|
|
|
for temp // John Hoyne Phone #: ###-#### (please make notes if not need electrical, plumbing and mechanical to sign off on temp). Fire/life/safety failed.
|
FIRE-Final Inspection | 11/6/2014 | 11/7/2014 | 11/7/2014 | A | FAIL |
Troy Cobbley
|
|
|
Need city approved plans. I performed a conference with owner and went over fire extinguisher requirements and door hardware.
|
Print Occupancy Form | | | 11/6/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/8/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 8/8/2014 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 8/8/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 8/4/2014 | 8/4/2014 | 8/6/2014 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 8/6/2014 | | 8/6/2014 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/6/2014 | | DONE |
|
|
|
|
Routing - FIRE | 8/4/2014 | 8/4/2014 | 8/4/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 08-04-14
|
Routing - PUBLIC WORKS | 8/4/2014 | | 8/4/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLAN CHECK | 8/4/2014 | | 8/4/2014 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Sewer Rating | 8/4/2014 | | 8/4/2014 | | PASS |
Jennifer Bruner
|
|
|
|
1st review completed | | | 8/4/2014 | | DONE |
|
|
|
|
Intake Approval | | | 7/30/2014 | | PASS |
|
|
|
|
Routing - Addressing | 7/30/2014 | | 7/30/2014 | | PASS |
Emily Dixon
|
|
|
|
Application received | | | 7/29/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 29 2014 3:42PM
|