Letter of compliance/Occupancy | | | 9/5/2018 | | DONE |
|
|
|
|
BLD-Final | 8/31/2018 | 9/4/2018 | 9/4/2018 | P | PASS |
Dave Hannah
|
|
|
Victoria Phone #: ###-####
|
FIRE-Final Inspection | 8/31/2018 | 9/4/2018 | 9/4/2018 | A | PASS |
Jim Page
|
|
|
Final life fire safety inspection complete.
Victoria Phone #: ###-####
|
PubWorks Occupancy Approval | 1/18/2018 | 1/18/2018 | 1/18/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 2/2/2017 | 2/2/2017 | 2/2/2017 | | PASS |
Sarah Schafer
|
|
|
Approved with the requirement that the mechanical screening be extended to cover the visible duct work.
|
BLD-Conference | 1/19/2017 | 1/23/2017 | 1/24/2017 | P | PASS |
Dave Hannah
|
|
|
To review egress path for Annex level 4 terrace.. Phone #: ###-#### Inspection requested via web by Joe Borelli
|
FIRE-Conference | 1/19/2017 | 1/23/2017 | 1/23/2017 | P | DONE |
Jim Page
|
|
|
Fire conference complete
|
BLD-Wall cover | 1/17/2017 | 1/18/2017 | 1/20/2017 | P | PART |
Dave Hannah
|
|
|
Level 1 wellness center. Rated standpipe. cover inspection. Will be complete at 2:00pm. Call on arrival. Phone #: ###-#### Inspection requested via web by Jon Pederson needs to move duct work out of shaft ok to cover the rest
|
BLD-Wall cover | 1/5/2017 | 1/5/2017 | 1/5/2017 | P | PASS |
Dave Hannah
|
|
|
stair 1 rated wall. levels 2-6. Shaft enclosure at stand pipe levels 2,3,4. Phone #: ###-#### Inspection requested via web by Jon Pederson stair tower 2-6 ok standpipe on 3ok ok to keep working on the rest
|
BLD-Wall cover | 1/4/2017 | 1/4/2017 | 1/5/2017 | P | PART |
Dave Hannah
|
|
|
rated stand pipe. rated wall around stand pipe. office, stack 2. level 1-9 Phone #: ###-#### Inspection requested via web by Jon Pederson 3rd flloor ok
|
BLD-Wall cover | 12/29/2016 | 12/29/2016 | 12/29/2016 | P | CANC |
Dave Hannah
|
|
|
level 7 ceiling inspection at bathrooms. for drywall cover. Phone #: ###-#### Inspection requested via web by Jon Pederson
|
BLD-Wall cover | 12/28/2016 | 12/28/2016 | 12/28/2016 | A | PASS |
Dave Hannah
|
|
|
Shaft at bathroom level 5 for drywall cover. Bathroom top out at shaft level 6 for cover. Call when on site. Phone #: ###-#### Inspection requested via web by Jon Pederson
|
BLD-Wall cover | 12/23/2016 | 12/27/2016 | 12/27/2016 | A | PASS |
Dave Hannah
|
|
|
Level 6 Bathroom Shaft Phone #: ###-#### Inspection requested via web by Jon Pederson
|
BLD-Wall cover | 12/21/2016 | 12/22/2016 | 12/22/2016 | P | PASS |
Dave Hannah
|
|
|
Level 4 shaft at bathrooms cover inspection. Level 7 shaft at bathrooms cover inspection. Phone #: ###-#### Inspection requested via web by Jon Pederson
|
BLD-Wall cover | 12/16/2016 | 12/19/2016 | 12/19/2016 | A | PASS |
Dave Hannah
|
|
|
quad core elevator. Levels 4-7 shaft wall cover inspection. Mechanical shaft between bathrooms. levels 2 and 3. Shaft wall cover inspection. Phone #: ###-#### Inspection requested via web by Jon Pederson
|
BLD-Conference | 12/15/2016 | 12/15/2016 | 12/15/2016 | A | PASS |
Dave Hannah
|
|
|
Level 2 and 3 elev quad core lobby. walls and ceilings. shaft wall and cover inspection. Phone #: ###-#### Inspection requested via web by Jon Pederson
|
BLD-Conference | 12/12/2016 | 12/12/2016 | 12/13/2016 | P | PASS |
Dave Hannah
|
|
|
Level 1 elevator shaft. Caulk at electrical was not done. It is being done now by LEA electric. Will be finished at 12:00. please call when on site. Phone #: ###-#### Inspection requested via web by Jon Pederson
|
BLD-Conference | 12/12/2016 | 12/13/2016 | 12/13/2016 | A | PART |
Dave Hannah
|
|
|
level 1 quad core elev. lobby. Levels 2 and 3 quad core elev. lobby cover inspoections. Please call when on site. ###-####. Phone #: ###-#### Inspection requested via web by Jon Pederson level one ok to cover
|
BLD-Wall cover | 12/9/2016 | 12/12/2016 | 12/12/2016 | A | PASS |
Dave Hannah
|
|
|
Level 1 satck 1 drywall hard lid cover. Level 1 stack 2 quad core elevator cover. Please call when on site Phone #: ###-#### Inspection requested via web by Jon Pederson
|
FIRE-Conference | 11/19/2016 | 11/21/2016 | 11/22/2016 | P | DONE |
Jim Page
|
|
|
Conference complete
|
FIRE-Alarm Testing | 11/10/2016 | 11/14/2016 | 11/14/2016 | A | DONE |
Jim Page
|
|
|
Fire alarm testing complete for heat and smoke detectors on the simplot world headquarters basement level.
|
FIRE-Final Inspection | 10/21/2016 | 10/24/2016 | 10/24/2016 | A | PART |
Jim Page
|
|
|
Generator transfer for interior emergency/egress lighting tested/inspected for levels 1 through 9, exit signs on level 6 south balcony did not operate under emergency power, will verify operation on a future inspection. Exterior emergency egress lighting and parking level emergency egress/exit lighting will also be verified during a future inspection.
|
BLD-Conference | 10/20/2016 | 10/21/2016 | 10/24/2016 | A | CANC |
Dave Hannah
|
|
|
Requesting conference to review TCO sign off status with fire marshal. Phone #: ###-#### Inspection requested via web by Joe Borelli
|
FIRE-Final Inspection | 10/21/2016 | 10/21/2016 | 10/21/2016 | P | CANC |
Jim Page
|
|
|
Inspection request is going to be rescheduled for 24OCT2016.
|
FIRE-Conference | 10/20/2016 | 10/21/2016 | 10/21/2016 | A | DONE |
Jim Page
|
|
|
Fire conference complete, discussed remaining requirements in regards to life safety for TCO.
|
BLD-Final | 10/20/2016 | 10/21/2016 | 10/21/2016 | P | CANC |
Dave Hannah
|
|
|
Requesting TCO sign off for levels 2-7 of office building. Phone #: ###-#### Inspection requested via web by Joe Borelli
|
BLD-Framing/Rough-in | 10/19/2016 | 10/20/2016 | 10/20/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Final | 10/14/2016 | 10/18/2016 | 10/18/2016 | A | PEND |
Dave Hannah
|
|
|
Requesting TCO for levels 1-9 of SWHQ Office building. Phone #: ###-#### Inspection requested via web by Joe Borelli
|
BLD-Final | 10/8/2016 | 10/10/2016 | 10/10/2016 | A | NR |
Dave Hannah
|
|
|
Requesting TCO walk through for levels 2-4 of SWHQ Office building. Phone #: ###-#### Inspection requested via web by Joe Borelli walk floors needs to finish fire coulking needs signage finish installing office fronts ext
|
BLD-Conference | 10/6/2016 | 10/6/2016 | 10/6/2016 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Ceiling Grid Inspection | 10/4/2016 | 10/5/2016 | 10/5/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 9/28/2016 | 9/29/2016 | 9/29/2016 | A | PEND |
Dave Hannah
|
|
|
john Phone #: ###-####
|
BLD-Framing/Rough-in | 9/26/2016 | 9/27/2016 | 9/29/2016 | A | PEND |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 9/15/2016 | 9/16/2016 | 9/16/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 9/9/2016 | 9/12/2016 | 9/12/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 9/1/2016 | 9/2/2016 | 9/2/2016 | A | PASS |
Dave Hannah
|
|
|
John-ceiling framing 1st floor exterior Phone #: ###-####
|
BLD-Framing/Rough-in | 8/23/2016 | 8/24/2016 | 8/24/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 8/16/2016 | 8/17/2016 | 8/17/2016 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. 2nd. floor grid for wood panel in anex building ok.
|
BLD-Framing/Rough-in | 8/8/2016 | 8/9/2016 | 8/10/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-#### 4th floor anx ceilings/soffits ok to cover
|
BLD-Ceiling Grid Inspection | 8/9/2016 | 8/10/2016 | 8/10/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-#### 9th floor
|
BLD-Conference | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | PEND |
Dave Hannah
|
|
|
Victoria Phone #: ###-#### stair tower illumination
|
BLD-Ceiling Grid Inspection | 7/28/2016 | 7/29/2016 | 7/29/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Other | 7/22/2016 | 7/25/2016 | 7/28/2016 | A | PASS |
Dave Hannah
|
|
|
Ceiling cover, annex - John Phone #: ###-####
|
BLD-Wall cover | 7/20/2016 | 7/21/2016 | 7/21/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Wall cover | 7/18/2016 | 7/19/2016 | 7/20/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 7/13/2016 | 7/14/2016 | 7/14/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-#### soffit on anx
|
Inspection Record Card- Bld | | | 7/8/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/8/2016 | | DONE |
|
|
|
|
BLD-Other | 6/21/2016 | 6/22/2016 | 6/22/2016 | A | PASS |
Dave Hannah
|
|
|
John-slab edge fire stop Phone #: ###-####
|
BLD-Framing/Rough-in | 6/13/2016 | 6/14/2016 | 6/14/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Energy code compliance | 6/3/2016 | 6/6/2016 | 6/6/2016 | A | PASS |
Dave Hannah
|
|
|
7th fl exterior - John Phone #: ###-#### 7 and 8th floors ext insulation and 9th floor slab edge ok
|
OVERRIDE | | | 6/2/2016 | | |
|
|
|
|
BLD-Framing/Rough-in | 6/1/2016 | 6/2/2016 | 6/2/2016 | A | PART |
Dave Hannah
|
|
|
3rd fl annex - John Phone #: ###-#### shaft around mec ok cover
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/2/2016 | | DONE |
|
|
|
Both the building plan modification and the defered submittal of the greenhouse are now approved. TLW
|
Permit Ready to Issue | | | 6/2/2016 | | DONE |
Christina Prado
|
|
|
DO NOT RE-ISSUE - PLAN MOD & DEFERRED SUB APPROVAL ONLY
MUST PAY ALL FEES PRIOR TO CHANGING STATUS TO ISS
|
Routing Off Site - STRUCTURAL | 5/3/2016 | | 6/2/2016 | | PASS |
Tim L. Woodard
|
|
|
Routed resubmittals back for Greenhouse Plan Mod. TLW
|
Plan assigned to (TLW) | 1/19/2016 | | 6/2/2016 | | PASS |
Tim L. Woodard
|
|
|
Plan Mod
|
BLD-Framing/Rough-in | 5/27/2016 | 5/31/2016 | 5/31/2016 | A | PASS |
Dave Hannah
|
|
|
John-ceiling-John said inspection has nothing to do with the plan mod that''s in review Phone #: ###-#### second floor ok
|
BLD-Framing/Rough-in | 5/23/2016 | 5/24/2016 | 5/24/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Foundation | 5/16/2016 | 5/17/2016 | 5/17/2016 | A | PASS |
Dave Hannah
|
|
|
Slab; John Phone #: ###-#### level 4 crossover slabedge fire proofing
|
BLD-Framing/Rough-in | 5/12/2016 | 5/13/2016 | 5/13/2016 | A | PASS |
Dave Hannah
|
|
|
Annex building & Office Bldg - John Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/6/2016 | 5/9/2016 | 5/9/2016 | A | PART |
Dave Hannah
|
|
|
Johhn-plan mod not for this inspection Phone #: 371- fourth floor west half ok to cover
|
BLD-Other | 5/6/2016 | 5/9/2016 | 5/9/2016 | A | PART |
Dave Hannah
|
|
|
John-fire stop-plan mod not for this inspection Phone #: ###-#### 9th floor slab edge ok
|
BLD-Energy code compliance | 5/3/2016 | 5/4/2016 | 5/5/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### second floor stack 1 and 2 walls ok
|
BLD-Energy code compliance | 4/28/2016 | 4/29/2016 | 4/29/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### enerdy not ready but framing on 6th floor ok
|
BLD-Other | 4/25/2016 | 4/25/2016 | 4/25/2016 | P | PASS |
Dave Hannah
|
|
|
Fire stop // John Phone #: ###-#### level 2 anx splb edge f/p ok
|
BLD-Other | 4/25/2016 | 4/25/2016 | 4/25/2016 | P | PART |
Dave Hannah
|
|
|
Thermoal // John Phone #: ###-#### lev 6 ext insulation ok see plans for area
|
BLD-Ceiling Grid Inspection | 4/20/2016 | 4/21/2016 | 4/25/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-#### level 5 slab edge f/p ok
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/20/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (REV) | | | 4/20/2016 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 4/12/2016 | 4/13/2016 | 4/14/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-#### 5th fl
|
BLD-Energy code compliance | 4/7/2016 | 4/8/2016 | 4/12/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 4/11/2016 | 4/12/2016 | 4/12/2016 | A | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-#### anx ext mec sreen on roof
|
BLD-Energy code compliance | 4/4/2016 | 4/5/2016 | 4/5/2016 | A | PASS |
Dave Hannah
|
|
|
Exterior - John Phone #: ###-#### 5th floor west half
|
BLD-Framing/Rough-in | 3/24/2016 | 3/28/2016 | 3/29/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### 4th floor ok to cover walls
|
BLD-Energy code compliance | 3/22/2016 | 3/23/2016 | 3/24/2016 | A | PASS |
Dave Hannah
|
|
|
Insulation // John Phone #: ###-#### stack 2-3 floor 5 slab edge fire safing and floor 4 insulation ok
|
BLD-Framing/Rough-in | 3/18/2016 | 3/21/2016 | 3/21/2016 | A | NR |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 3/16/2016 | 3/16/2016 | 3/17/2016 | P | PART |
Dave Hannah
|
|
|
john Phone #: ###-#### second floor restroom ok to cover
|
BLD-Framing/Rough-in | 3/14/2016 | 3/15/2016 | 3/17/2016 | A | PEND |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Other | 3/9/2016 | 3/10/2016 | 3/11/2016 | A | PART |
Dave Hannah
|
|
|
John-slab edge-fire stop Phone #: ###-#### 5th floor sw area ok to spray
|
BLD-Conference | 3/7/2016 | 3/8/2016 | 3/10/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### third floor framing int and ext walls shell and core al but for stairs ok to cover
|
BLD-Conference | 2/26/2016 | 2/29/2016 | 3/1/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### 3rd floor ext wall framing inulation and slab edge fire protection pass all but for the east pod
|
BLD-Framing/Rough-in | 2/24/2016 | 2/25/2016 | 2/26/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### third floor restroom area ok to cover
|
BLD-Energy code compliance | 2/23/2016 | 2/24/2016 | 2/24/2016 | A | PART |
Dave Hannah
|
|
|
John-office building Phone #: ###-####third floor ext walls
|
BLD-Framing/Rough-in | 2/19/2016 | 2/22/2016 | 2/22/2016 | P | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 2/18/2016 | 2/19/2016 | 2/19/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### third floor south wing ok to cover walls all but for restrooms
|
BLD-Framing/Rough-in | 2/10/2016 | 2/11/2016 | 2/11/2016 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. South East Interior steel stud framed wall at annex, 2nd floor. All per supplied emgineering. Contractor to verify if clips are nedded or not on the horizontal stiffeners that are placed at 6ft. o.c. Supplied engineering does not show connections to studs.
|
BLD-Framing/Rough-in | 2/3/2016 | 2/4/2016 | 2/6/2016 | A | PART |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|
Routing - FIRE | 1/24/2016 | 1/24/2016 | 1/29/2016 | | PASS |
Katie Marron
|
|
|
Revised report (updated scope to reflect modifications) attached to case.
|
Routing - PLAN CHECK | 1/24/2016 | | 1/29/2016 | | PASS |
Tim L. Woodard
|
|
|
Approved modifications to existing building to accomodate greenhouse. Greenhouse Deffered submittal also approved at the same time. TLW
|
Routing Off Site - STRUCTURAL | 1/26/2016 | | 1/29/2016 | | FAIL |
Tim L. Woodard
|
|
|
|
BLD-Framing/Rough-in | 1/25/2016 | 1/26/2016 | 1/27/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 1/15/2016 | 1/19/2016 | 1/20/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### slab edge fire protection
|
Plan Modification Accepted | | | 1/19/2016 | | DONE |
Christina Prado
|
|
|
Plan mod requested for Greenhouse modifications per Angie B
|
BLD-Framing/Rough-in | 1/11/2016 | 1/12/2016 | 1/12/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### safts first floor
|
BLD-Framing/Rough-in | 1/5/2016 | 1/6/2016 | 1/6/2016 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 12/8/2015 | 12/9/2015 | 12/9/2015 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### walked site with john looked at bottoms of shafts in second floor
|
BLD-Framing/Rough-in | 11/3/2015 | 11/4/2015 | 11/4/2015 | A | CANC |
Mike Jordan
|
|
|
John Phone #: ###-####. Soffit framing at annex building ok.
|
BLD-Framing/Rough-in | 10/29/2015 | 10/30/2015 | 10/30/2015 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### edge framing on roof
|
BLD-Framing/Rough-in | 10/21/2015 | 10/22/2015 | 10/22/2015 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 10/8/2015 | 10/9/2015 | 10/14/2015 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 9/28/2015 | 9/29/2015 | 9/29/2015 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### second and third floor elec and mec rooms ok to cover tops
|
OVERRIDE | | | 7/29/2015 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/29/2015 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 7/29/2015 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/29/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/29/2015 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Routing - PLAN CHECK | 7/16/2015 | | 7/29/2015 | | PASS |
Tim L. Woodard
|
|
|
Approve Lab modification only. No re-review of the previously approved structure was conducted. TLW
|
Plan assigned to (TLW) | 5/28/2015 | | 7/29/2015 | | PASS |
Tim L. Woodard
|
|
|
Plan Mod
|
CHANGE ISSUED DATE | | | 7/29/2015 | | DONE |
Christina Prado
|
|
|
Issued twice by mistake, activity added to correct issue date only
|
Routing - MECHANICAL | 7/16/2015 | | 7/28/2015 | | PASS |
Troy James
|
|
|
Lab Plan Mod
|
Extend Review Timeline | | | 7/8/2015 | | DONE |
Christina Prado
|
|
|
2nd extension approved 7/8/15
|
Routing Off Site - STRUCTURAL | 6/23/2015 | | 6/29/2015 | | PASS |
Angela Brosious
|
|
|
Deferred submittal 1 (for AMMR2 curtains)
Structural approved by CH2MHILL
|
Routing - PLAN CHECK | 6/23/2015 | | 6/29/2015 | | PASS |
Tim L. Woodard
|
|
|
Deffered Submittal 1 review. TLW
|
Routing - PUBLIC WORKS | 5/28/2015 | | 6/24/2015 | | PASS |
Tim L. Woodard
|
|
|
Approvd in E-Plan. TLW
|
Routing - PLAN CHECK | 5/28/2015 | | 6/24/2015 | | FAIL |
Tim L. Woodard
|
|
|
Failed Plan Mod for roof screening and other miscallanoius work. Corrections Requested in E-Plan Review.
|
Routing Off Site - STRUCTURAL | 5/28/2015 | | 6/24/2015 | | PASS |
Tim L. Woodard
|
|
|
Plan Mod for Roof Screening Walls. TLW
|
Routing - PLUMBING | 5/28/2015 | | 6/10/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - MECHANICAL | 5/28/2015 | | 6/5/2015 | | FAIL |
Troy James
|
|
|
pending building review for fsd at shaft for new lab exhaust and supply ducts
|
Routing - Design Review | 5/28/2015 | | 6/1/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - FIRE | 5/28/2015 | | 6/1/2015 | | PASS |
Scott Arellano
|
|
|
No change in comments from previous approval.
|
Plan Modification Accepted | | | 5/28/2015 | | DONE |
Tim L. Woodard
|
|
|
Plan Mod accepted to add screen wall for Lab and additional structural support for Lab. LOTS of sheets changed...all dated 5-27-15. TLW
|
OVERRIDE | | | 5/8/2015 | | |
|
|
|
|
Plan assigned to (TLW) | 5/5/2015 | | 5/8/2015 | | PASS |
Tim L. Woodard
|
|
|
Simplot Headquarters - Reassigned from John Menard
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/8/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/8/2015 | | DONE |
|
|
|
need RP, ACHD, GC & rev Cert of Val
|
Routing PW Drainage | 2/9/2015 | | 5/7/2015 | | PASS |
Brian Murphy
|
|
|
|
Plan assigned to (JCM) | 8/11/2014 | | 5/5/2015 | | DEFR |
John Menard
|
|
|
1st Review Complete 10/16/2014
Reassigned to Tim Woodard
|
Routing - PLAN CHECK | 2/5/2015 | | 2/9/2015 | | FAIL |
John Menard
|
|
|
|
Routing - PLAN CHECK | 2/9/2015 | | 2/9/2015 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 11/24/2014 | | 1/27/2015 | | FAIL |
John Menard
|
|
|
|
Routing - PLUMBING | 1/12/2015 | | 1/12/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - MECHANICAL | 11/24/2014 | | 12/23/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 11/24/2014 | | 11/28/2014 | | FAIL |
Daryl Spivey
|
|
|
Need to vent OI-1 vaults out seperately from other venting as required.
|
Routing - FIRE | 11/24/2014 | | 11/24/2014 | | PASS |
Scott Arellano
|
|
|
*Need to sign off in e-plan review* Attached comments to plans.
|
1st review completed | | | 10/16/2014 | | DONE |
John Menard
|
|
|
|
Routing - PLAN CHECK | 8/11/2014 | | 10/16/2014 | | FAIL |
John Menard
|
|
|
|
Routing - MECHANICAL | 10/6/2014 | | 10/6/2014 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 8/11/2014 | 8/11/2014 | 10/2/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 10-02-14
|
Routing - PLUMBING | 8/11/2014 | | 9/22/2014 | | PASS |
Daryl Spivey
|
|
|
Need to install vents on oil intercepter tanks and run out seperately.
|
Routing - MECHANICAL | 8/11/2014 | | 9/17/2014 | | FAIL |
Troy James
|
|
|
|
Routing PW Environmental | 8/11/2014 | | 9/2/2014 | | PASS |
Rick Christenson
|
|
|
|
Route to Impact Fee Review | 8/11/2014 | 8/14/2014 | 8/26/2014 | | PASS |
Cindy M. Gould
|
|
|
Added Fire and Police Impact fees manually.
|
Routing PW Street Lights | 8/11/2014 | | 8/21/2014 | | PASS |
Mike D Hedge
|
|
|
No Street Light information.
|
(F) Reprint permit | | | 8/19/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Routing PW Sewer Design | 8/11/2014 | | 8/18/2014 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Solid Waste | 8/11/2014 | | 8/13/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - Erosion and Sediment | 8/11/2014 | | 8/13/2014 | | PASS |
Evan Jenkins
|
|
|
Shall Reference and Abide by Permit number: ESC12-00403
|
Routing - Design Review | 8/11/2014 | | 8/13/2014 | | PASS |
Josh Wilson
|
|
|
OK per DRH14-00012
|
Routing PW Drainage | 8/11/2014 | | 8/12/2014 | | FAIL |
Brian Murphy
|
|
|
NO EXISTING SEEPAGE BEDS FOR STORMWATER
|
Routing PW Sewer Rating | 8/11/2014 | | 8/12/2014 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 8/11/2014 | | PASS |
John Menard
|
|
|
|
Pending Assignment by JCM | 8/11/2014 | | 8/11/2014 | | DONE |
John Menard
|
|
|
|
Routing - PLANNING Land Div | 8/11/2014 | | 8/11/2014 | | PASS |
Dave Abo
|
|
|
|
Routing - Addressing | 8/11/2014 | | 8/11/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/11/2014 | | 8/11/2014 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 7/30/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 30 2014 12:39PM
|