BLD-Aging Inspection | 1/15/2016 | 1/15/2016 | 1/17/2016 | | DONE |
Tony Young
|
|
|
|
BLD-Aging Inspection | 1/14/2016 | 1/14/2016 | 1/15/2016 | | DONE |
Tony Young
|
|
|
|
DOC - Permit Finaled | 1/15/2016 | 1/15/2016 | 1/15/2016 | P | PASS |
Tony Young
|
|
|
done
|
BLD-Final | 9/1/2015 | 9/2/2015 | 9/2/2015 | A | PASS |
Jim Sly
|
|
|
JOSH Phone #: ###-#### OK per 415.
|
PubWorks Subgrade Approval | 9/2/2015 | 9/2/2015 | 9/2/2015 | | DONE |
Jason C. Taylor
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Final | 8/31/2015 | 9/1/2015 | 9/1/2015 | A | NR |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Final | 8/28/2015 | 8/31/2015 | 8/31/2015 | A | NR |
Tony Young
|
|
|
Josh Phone #: ###-####,, need engineering on glass guardrail,, hillside final,, roof soffit vents
|
BLD-Framing/Rough-in | 4/23/2015 | 4/24/2015 | 4/24/2015 | A | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####,, patio frame ok,, soffit ok
|
OVERRIDE | | | 4/16/2015 | | |
|
|
|
|
Plan assigned to (JG) | 4/13/2015 | 4/13/2015 | 4/16/2015 | | PASS |
Javier Guzman
|
|
|
Plan Mod patio extension
|
Routing - PLAN CHECK | 4/15/2015 | | 4/16/2015 | | PASS |
Javier Guzman
|
|
|
Could not locate original issued plans in filling cabinet, front desk or with planners.
|
Case Summary (BLD) | | | 4/16/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/16/2015 | | DONE |
|
|
|
DO NOT REISSUE. All requirements met
|
Telephone call | | | 4/16/2015 | | DONE |
|
|
|
called office- told them plan mod is ready for pick up and fees due
|
CHANGE STATUS TO (ISS) | | | 4/16/2015 | | DONE |
|
|
|
|
Routing - PLANNING | 4/15/2015 | | 4/15/2015 | | PASS |
Cody Riddle
|
|
|
|
Plan Modification Accepted | | | 4/13/2015 | | DONE |
|
|
|
plan mod received 2 sets of calcs and 2 sets of each sheet A1, A5, A7, A8, A9, A10, A12-Took to JG
|
BLD-Other | 4/2/2015 | 4/3/2015 | 4/3/2015 | P | PASS |
Tony Young
|
|
|
soffit/// Josh Phone #: ###-####
|
BLD-Wall Bracing | 4/1/2015 | 4/2/2015 | 4/2/2015 | P | PASS |
Tony Young
|
|
|
Shear // Josh Phone #: ###-####,, shear ok
|
BLD-Wall Bracing | 4/1/2015 | 4/2/2015 | 4/2/2015 | A | FAIL |
Jim Storey
|
|
|
Josh Phone #: ###-#### #7 c/n ceilling covered/ plm drain line in soffit not allowed
|
BLD-Energy code compliance | 3/26/2015 | 3/26/2015 | 3/26/2015 | P | PART |
Tony Young
|
|
|
Josh// please call 30min before- inspecting sheet rock in the eaves Phone #: ###-####,, see notes on frame inspection,, energy code ok so far
|
BLD-Framing/Rough-in | 3/26/2015 | 3/26/2015 | 3/26/2015 | P | PART |
Tony Young
|
|
|
Josh// please call 30min before Phone #: ###-####,, ok to sheet rock after sealing up the draft stops,, need to finish correction notice,, soffits need double layer in can light boxes and fire caulked,, plan mod for added porch in review?,, also took out closet in basement room without window well,, still pending plan mod approval on those 2 items
|
BLD-Framing/Rough-in | 3/11/2015 | 3/12/2015 | 3/12/2015 | P | FAIL |
Tony Young
|
|
|
Josh Phone #: ###-####,, correction notice posted
|
BLD-Wall Bracing | 2/18/2015 | 2/19/2015 | 2/19/2015 | A | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Foundation | 1/20/2015 | 1/20/2015 | 1/20/2015 | P | PASS |
Tony Young
|
|
|
Adam Phone #: ###-####
|
BLD-Footing | 1/14/2015 | 1/15/2015 | 1/15/2015 | A | PART |
Tony Young
|
|
|
Adam Phone #: ###-####,, lower ftgs ok
|
BLD-Footing | 1/14/2015 | 1/14/2015 | 1/14/2015 | P | PART |
Tony Young
|
|
|
Adam Phone #: ###-####,, getting forms in place
|
PubWorks Subgrade Approval | 1/14/2015 | 1/14/2015 | 1/14/2015 | | DONE |
Jason C. Taylor
|
|
|
* EAST, WEST, AND SOUTHERN FOOTINGS***A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Additional plans submitted | | | 1/14/2015 | | DONE |
Candy A. Nichols
|
|
|
received 2 geotechnical inspection reports-took to Jason Taylor
|
BLD-Foundation | 12/11/2014 | 12/11/2014 | 12/11/2014 | P | PART |
Tony Young
|
|
|
Adam Phone #: ###-####,, tall walls,, work in progress
|
BLD-Footing | 12/9/2014 | 12/9/2014 | 12/9/2014 | P | PART |
Tony Young
|
|
|
Adam Phone #: ###-####,, rear basement/ retaining ftgs,, work in progress
|
PubWorks Subgrade Approval | 12/9/2014 | 12/9/2014 | 12/9/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 12/3/2014 | 12/3/2014 | 12/3/2014 | P | NR |
Tony Young
|
|
|
Adam Phone #: ###-####,, need soils report
|
OVERRIDE | | | 12/3/2014 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/3/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 12/3/2014 | | DONE |
|
|
|
|
PubWorks Subgrade Approval | 11/10/2014 | 11/10/2014 | 11/10/2014 | | DONE |
Jason C. Taylor
|
|
|
* RETAINING WALLS ONLY****A letter from the applicant’s geotechnical engineer indicating that the retaining wall subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Routing PW Grading-Hillside | 11/10/2014 | | 11/10/2014 | | PASS |
Jason C. Taylor
|
|
|
Approved new retaining wall design (7.5'). Jason Taylor ###-####
|
Routing - PLAN CHECK | 11/10/2014 | | 11/10/2014 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/10/2014 | | DONE |
|
|
|
|
Telephone call | | | 11/10/2014 | | |
|
|
|
Called George-left message that engineering is ready for pick up
|
BLD-Foundation | 11/6/2014 | 11/6/2014 | 11/6/2014 | P | PEND |
Phil Shearer
|
|
|
Retaining wall rebar/requests 2 pm inspection, pouring at 3 - JR Phone #: ###-#### Retaining wall. Rebar ok as per engineered drawings that the contractor provided. There were not aproved drawing for this the retaining walls.
|
BLD-Foundation | 11/5/2014 | 11/5/2014 | 11/6/2014 | P | PEND |
Phil Shearer
|
|
|
JR-pour time 3:00 Phone #: ###-####. Retaining wall. Rebar ok as per engineered drawings that the contractor provided. There were not aproved drawing for this the retaining walls.
|
BLD-Footing | 11/3/2014 | 11/4/2014 | 11/4/2014 | P | PEND |
Tony Young
|
|
|
JR-pour time 3:00 Phone #: ###-####retaining ftgs,, pending soils
|
Additional plans submitted | | | 10/29/2014 | | |
Jason C. Taylor
|
|
|
routed to Jason Taylor per Javier G
|
Issue PAID IN FULL permit | | | 10/9/2014 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 10/8/2014 | | |
|
|
|
|
Plan assigned to (JG) | 7/31/2014 | 7/31/2014 | 10/8/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, 8/18 M L2 Hillside**
|
Routing - PLAN CHECK | 8/18/2014 | | 10/8/2014 | | PASS |
Javier Guzman
|
|
|
|
Telephone call | | | 10/8/2014 | | DONE |
Tisha Gallop
|
|
|
called Josh Baker and left vm permit is ready and fee due.
|
Case Summary (BLD) | | | 10/8/2014 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/8/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 10/8/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PUBLIC WORKS | 10/7/2014 | | 10/7/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Grading-Hillside | 10/1/2014 | | 10/7/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Plan resubmittals received | | | 10/6/2014 | | DONE |
Candy A. Nichols
|
|
|
received 2 sets of shallow injection well inventory form & injection well cals-took to JCT
|
Plan resubmittals received | | | 9/30/2014 | | DONE |
|
|
|
received two copies of grading plans C1, calculations, and engineering
|
Plan resubmittals received | | | 9/26/2014 | | DONE |
Tisha Gallop
|
|
|
received three copies of retaining wall calcs; taken to Javier.
|
Routing PW Grading-Hillside | 9/24/2014 | | 9/25/2014 | | FAIL |
Jason C. Taylor
|
|
|
See notes in PWE file for details. JCT
|
Plan resubmittals received | | | 9/24/2014 | | DONE |
Tisha Gallop
|
|
|
received two full sets of plans (sheets A1, A2, A2.1, A3, A3.1, A4, A5, A6, A7, A8, A9, A10, A11, A12) structural calcs, geotech report and , three copies of sheet C1; taken to Javier.
|
Routing - PLANNING | 9/17/2014 | | 9/17/2014 | | PASS |
Cody Riddle
|
|
|
Appeal period has lapsed for CFH. Eaves and chimney can encroach a max. of 2' into setbacks. Retaining walls shall not exceed 6' in side and rear setbacks.
|
Routing - MECHANICAL | 8/28/2014 | | 8/28/2014 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 8/15/2014 | | 8/18/2014 | | PASS |
Scott Arellano
|
|
|
NO comments.
|
Routing - PLAN CHECK | | | 8/18/2014 | | FAIL |
Javier Guzman
|
|
|
emailed review report to applicant
|
1st review completed | | | 8/18/2014 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Erosion and Sediment | 8/14/2014 | | 8/15/2014 | | PASS |
Andy J. Long
|
|
|
ESC plan narrative submitted and approved. Valid RP and PD designated for project.
|
Routing - MECHANICAL | 8/11/2014 | | 8/12/2014 | | FAIL |
Troy James
|
|
|
Emailed corrections to idaho hvac
|
Routing - Addressing | 8/1/2014 | | 8/8/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 8/8/2014 | | 8/8/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Grading-Hillside | 8/1/2014 | | 8/8/2014 | | FAIL |
Jason C. Taylor
|
|
|
Notes sent to engineer for review. Jason Taylor ###-####
|
Route to Impact Fee Review | 7/31/2014 | 8/5/2014 | 8/1/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Application received | | 7/31/2014 | 8/1/2014 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/31/2014 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/31/2014 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 7/31/2014 | | PASS |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 8/8/2014 | | | | FAIL |
|
|
|
Hillside permit # CFH12-00028 has expired. Needs new hillside review.
|