BLD-Final | 2/19/2015 | 2/19/2015 | 2/20/2015 | P | PASS |
Jim Sly
|
|
|
Micah Phone #: ###-####
|
DOC - Permit Finaled | 2/20/2015 | 2/20/2015 | 2/20/2015 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 12/23/2014 | 12/24/2014 | 12/24/2014 | A | PASS |
Phil Shearer
|
|
|
Micha Phone #: ###-####
|
BLD-Framing/Rough-in | 12/23/2014 | 12/24/2014 | 12/24/2014 | A | PASS |
Phil Shearer
|
|
|
Micha Phone #: ###-####
|
BLD-Framing/Rough-in | 12/22/2014 | 12/22/2014 | 12/22/2014 | P | PART |
Dave Hannah
|
|
|
Mika Phone #: ###-#### c/n on site ok to insulate
|
BLD-Wall Bracing | 12/11/2014 | 12/12/2014 | 12/12/2014 | A | PASS |
Jim Sly
|
|
|
Micah Phone #: ###-####
|
BLD-Foundation | 11/21/2014 | 11/21/2014 | 11/21/2014 | P | PASS |
Jim Sly
|
|
|
Jim Phone #: ###-####
|
BLD-Foundation | 11/13/2014 | 11/14/2014 | 11/14/2014 | P | CANC |
Jim Sly
|
|
|
Jim Phone #: ###-#### To cold to pour.
|
BLD-Foundation | 11/12/2014 | 11/13/2014 | 11/13/2014 | P | CANC |
Jim Sly
|
|
|
JIm Phone #: ###-####
|
BLD-Footing | 11/12/2014 | 11/12/2014 | 11/12/2014 | P | PASS |
Jim Sly
|
|
|
Ryan Phone #: ###-####
|
OVERRIDE | | | 11/7/2014 | | |
|
|
|
|
Application received | | 8/4/2014 | 11/7/2014 | | DONE |
|
|
|
|
Plan assigned to (JG) | | 8/4/2014 | 11/7/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, 8/14 TH L1**
|
Routing - PLAN CHECK | 8/12/2014 | | 11/7/2014 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 11/7/2014 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/7/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/7/2014 | | DONE |
|
|
|
|
Telephone call | | | 11/7/2014 | | DONE |
|
|
|
told Greg the remaining balance of permit and that it's ready for pick up
|
Permit Ready to Issue | | | 11/7/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 11/7/2014 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 11/6/2014 | | DONE |
Candy A. Nichols
|
|
|
received truss calcs and 2 sets of sheet A-2 & A-5- took tof JG
|
1st review completed | | | 8/12/2014 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 8/11/2014 | | 8/12/2014 | | FAIL |
Javier Guzman
|
|
|
emailed review report to applicant
|
Routing - MECHANICAL | 8/5/2014 | | 8/11/2014 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 8/4/2014 | 8/7/2014 | 8/6/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 8/5/2014 | | 8/5/2014 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - PUBLIC WORKS | 8/4/2014 | | 8/5/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 8/4/2014 | | 8/4/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/4/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 8/4/2014 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/4/2014 | | DONE |
Christina Prado
|
|
|
|