Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD14-02217
StatusFinaled
Name CAULKINS STEPHEN F TRUSTEE
Site Address 6710 W RANDOLPH DR
Project Name 
Customer Number 
ePlanReviewNo
Description
###1-6-2015 THIS PERMIT IS MODIFIED TO REFLECT THE COMPLETION OF THE BASEMENT FINISH INCLUDING ELECTRICAL, PLUMBING AND MECHANICAL. ADDED VALUE $5,000.00 pep###***8-8-2014 THIS PERMIT IS MODIFIED TO INCLUDE SELECT INTERIOR WALL AND CEILING COVER REMOVAL OT CREATE AN UNFINISHED CONDITION OF THE EXISTING BASEMENT ALL FIXTURES WILL BE REMOVED TO THE ROUGH-IN STAGES OR PER THE INSPECTORS APPROVAL PENDING PERMITS TO COMPLETE AN UNFINISHED BASEMENT IN THE NEAR FUTURE. NO ADDED VALUE AT THIS TIME. 8-8-2014 PEP ** This permit is for the installation of new wall coverings in the garage attached to an existing 2400s.f. single family dwelling. The project will include the replacement of the garage overhead door and windows of the farage. Separate electrical permit is required. All per the approved plans as marked and the plan review notes. pep
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/24/201511/25/201511/25/2015APASS
DetailsPhil Shearer
Stephen Phone #: ###-####
DOC - Permit Finaled11/25/201511/25/201511/25/2015PPASS
DetailsPhil Shearer
BLD-Conference10/27/201510/27/201510/27/2015PDONE
DetailsPhil Shearer
Steve Phone #: ###-####
BLD-Energy code compliance3/2/20153/3/20153/3/2015APASS
DetailsPhil Shearer
Steve Phone #: ###-####
BLD-Framing/Rough-in2/24/20152/25/20152/25/2015APASS
DetailsPhil Shearer
Steve Phone #: ###-####
BLD-Energy code compliance1/13/20151/14/20151/14/2015PPASS
DetailsPhil Shearer
Steve Phone #: ###-####
BLD-Conference1/13/20151/14/20151/14/2015PDONE
DetailsPhil Shearer
Steve Phone #: ###-####
Routing Walk-In (BLD)1/6/20151/6/20151/6/2015ADONE
DetailsPerry Paine
Inspection Record Card- Bld  1/6/2015 DONE
Case Summary (BLD)  1/6/2015 DONE
PLANS/APPL TAKEN TO FRONT DESK  1/6/2015 DONE
Issue PAID IN FULL permit  1/6/2015 DONE
BLD-Framing/Rough-in12/22/201412/23/201412/23/2014PPASS
DetailsPhil Shearer
Steve-asked for a insepction to check holes taht had the spray foam in them but needs a frame Phone #: ###-####
BLD-Conference11/24/201411/25/201411/25/2014APASS
DetailsPhil Shearer
call an hour before//steve Phone #: ###-####
Garage ok for cover
BLD-Framing/Rough-in10/9/201410/10/201410/10/2014ANR
DetailsPhil Shearer
Jim Phone #: ###-####
Routing Walk-In (BLD)8/8/20148/8/20148/8/2014APASS
DetailsPerry Paine
MODIFY PERMIT TO TAKE BASEMENT BACK TO ROUGH IN STAGE 8-8-2014 PEP
Case Summary (BLD)  8/8/2014  
Inspection Record Card- Bld  8/8/2014  
Routing Walk-In (BLD)8/5/20148/5/20148/5/2014ADONE
DetailsPerry Paine
Plan assigned to (PEP)8/5/20148/5/20148/5/2014 PASS
DetailsPerry Paine
1st review completed  8/5/2014 DONE
PLANS/APPL TAKEN TO FRONT DESK  8/5/2014 DONE
Permit Ready to Issue  8/5/2014 DONE
DetailsCandy A. Nichols
Issue PAID IN FULL permit  8/5/2014 DONE
DetailsCandy A. Nichols
Inspection Record Card- Bld  8/5/2014  
CHANGE ISSUED DATE  8/5/2014 DONE
DetailsJason Blais
Application received 8/5/2014