PubWorks Occupancy Approval | 8/20/2015 | 8/20/2015 | 8/20/2015 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 8/19/2015 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 8/18/2015 | 8/18/2015 | 8/18/2015 | P | PASS |
Jim Sly
|
|
|
Colin Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 8/17/2015 | 8/18/2015 | 8/18/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. There appears to be an issue with address. The computer and small documents say 5311 but the approved plans say 5317. Colyn is following up with the architect
|
FIRE-Final Inspection | 8/17/2015 | 8/17/2015 | 8/17/2015 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans. I noted that the thumbturn dead bolts will need to be removed from the two interior doors.
|
Zoning Approval | 8/14/2015 | 8/14/2015 | 8/14/2015 | | PASS |
Josh Wilson
|
|
|
|
BLD-Framing/Rough-in | 2/24/2015 | 2/24/2015 | 2/24/2015 | P | PASS |
Jim Sly
|
|
|
Colyn Phone #: ###-#### Pending MTI special inspections, tests and approvals.
|
BLD-Conference | 2/23/2015 | 2/24/2015 | 2/24/2015 | A | PEND |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 12/17/2014 | 12/17/2014 | 12/17/2014 | P | PART |
Jim Sly
|
|
|
Colyn Phone #: ###-#### Should have been Foundation wall. Wall OK pending MTI special insp, tests and approvals.
|
BLD-Footing | 12/9/2014 | 12/10/2014 | 12/10/2014 | P | PASS |
Jim Sly
|
|
|
Colyn Phone #: ###-#### OK Pend MTI Special insp, tests and approvals.
|
CHANGE STATUS TO (ISS) | | | 12/9/2014 | | DONE |
|
|
|
|
OVERRIDE | | | 11/14/2014 | | |
|
|
|
|
Print Occupancy Form | | | 11/14/2014 | | DONE |
Candy A. Nichols
|
|
|
|
(F) Reprint permit | | | 11/14/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 11/14/2014 | | DONE |
Candy A. Nichols
|
|
|
|
OVERRIDE | | | 11/13/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 11/13/2014 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 10/21/2014 | | 11/7/2014 | | PASS |
Tim L. Woodard
|
|
|
New Simplot Research Green House
|
Routing PW Drainage | 10/28/2014 | | 11/7/2014 | | PASS |
Brian Murphy
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/7/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/28/2014 | | 11/6/2014 | | PASS |
Tim L. Woodard
|
|
|
Approved with attached "modification letter". TLW
|
Plan resubmittals received | | | 10/28/2014 | | DONE |
Tim L. Woodard
|
|
|
Recieved in E-Plan and Routed. TLW
|
Route to Impact Fee Review | 10/23/2014 | 10/26/2014 | 10/24/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLAN CHECK | 10/21/2014 | | 10/23/2014 | | FAIL |
Tim L. Woodard
|
|
|
Refer to changemarks in E-Plan Review. TLW
|
1st review completed | | | 10/23/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Pending Assignment by JCM | 9/29/2014 | | 10/21/2014 | | DONE |
John Menard
|
|
|
|
Plan assigned to (AJS) | 9/29/2014 | | 10/21/2014 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
New Simplot Building
|
Routing - PLAN CHECK | 9/29/2014 | | 10/21/2014 | | PEND |
Adele J Schaffeld-Griffin
|
|
|
Rerouted plans to Tim W. TLW
|
Routing Off Site - STRUCTURAL | 9/29/2014 | | 10/14/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
approved in e plan
|
Routing PW Solid Waste | 9/30/2014 | | 10/10/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Drainage | 9/30/2014 | | 10/9/2014 | | FAIL |
Brian Murphy
|
|
|
need calcs drainage report,o and m,geotech
|
Routing - FIRE | 9/29/2014 | 9/29/2014 | 10/3/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 10-03-14
|
Routing - PLUMBING | 9/29/2014 | | 10/3/2014 | | PASS |
Daryl Spivey
|
|
|
premise protection to be changed to an R.P. and all water piping in building to be labeled per ISPC
|
Routing PW Street Lights | 9/30/2014 | | 10/1/2014 | | PASS |
Mike D Hedge
|
|
|
No stree lighting required.
|
Routing PW Environmental | 9/30/2014 | | 10/1/2014 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Sewer Rating | 9/30/2014 | | 9/30/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PUBLIC WORKS | 9/29/2014 | | 9/30/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 9/29/2014 | | 9/30/2014 | | PASS |
Evan Jenkins
|
|
|
Site Prep Inspection Required Prior to Earth Disturbance
|
Routing - Design Review | 9/29/2014 | | 9/30/2014 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLANNING Land Div | 9/29/2014 | | 9/29/2014 | | PASS |
Dave Abo
|
|
|
Parcel is over 5 acres in size. (10+ acres)
|
Routing - Addressing | 9/29/2014 | | 9/29/2014 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 9/29/2014 | | PASS |
John Menard
|
|
|
|
Intake Approval | | | 8/7/2014 | | FAIL |
John Menard
|
|
|
Please submit the structural plans and calculations for the proposed pre-engineered greenhouse portion of this project.
Also, please submit the information on the greenhouse finish materials.
|
Application received | | | 8/6/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 6 2014 4:26PM
|
First Notice | | 8/29/2015 | | | |
|
|
|
|