Print Statement | | | 9/18/2015 | | DONE |
|
|
|
|
Print Statement | | | 7/6/2015 | | DONE |
|
|
|
|
Telephone call | | | 7/6/2015 | | DONE |
|
|
|
Spoke with Dan and informed him that his Electrical and Plumbing contractors need to have a separate permits for this permit and BLD15-02838
|
First Notice | 5/12/2015 | 5/12/2015 | 6/10/2015 | | DONE |
Dave Hannah
|
|
|
Mailed out 6-10-15
|
BLD-Final | 5/11/2015 | 5/12/2015 | 5/12/2015 | A | PASS |
Dave Hannah
|
|
|
This is Phase 1 of the project which is the Pizza/Growler Area. Phone #: ###-#### Inspection requested via web by Mike Tsu
|
DOC - Permit Finaled | 5/12/2015 | 5/12/2015 | 5/12/2015 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 5/8/2015 | 5/11/2015 | 5/11/2015 | A | PASS |
Katie Marron
|
|
|
Fire life safety pass.
|
FIRE-Final Inspection | 5/6/2015 | 5/7/2015 | 5/7/2015 | A | NR |
Katie Marron
|
|
|
FIR14-00743 and FIR14-00711 permits need to be finaled before life safety can be completed.
|
FIRE-Conference | 11/14/2014 | 11/14/2014 | 11/14/2014 | A | DONE |
Forrest France
|
|
|
On site discussion with contractor regarding project related fire sprinkler, alarm and hood suppression permit work. Life safety items and scope of remodel.
|
BLD-Ceiling Grid Inspection | 11/12/2014 | 11/13/2014 | 11/13/2014 | A | DONE |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/12/2014 | 11/13/2014 | 11/13/2014 | A | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 11/5/2014 | 11/6/2014 | 11/6/2014 | A | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
OVERRIDE | | | 9/16/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/16/2014 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 9/16/2014 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 9/16/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CJW) | 8/14/2014 | 8/14/2014 | 8/29/2014 | | PASS |
Carl Westfall
|
|
|
WINCO GROCERY STORE - Level 3 TI - ePlanReview (15 days - Sept 2) (1st review done)
|
Routing - PLAN CHECK | 8/28/2014 | | 8/29/2014 | | DONE |
Carl Westfall
|
|
|
Started routing
Routing complete
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2014 | | DONE |
|
|
|
|
Route to Impact Fee Review | 8/27/2014 | 8/30/2014 | 8/28/2014 | | PASS |
Donna Wolf
|
|
|
No Impact Fees assessed - remodel of existing building with no additional sq ft. Exemption requested.
|
Plan resubmittals received | | | 8/28/2014 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 8/28/2014 | | 8/28/2014 | | PASS |
Evan Jenkins
|
|
|
Waiver Request Submittle is Approved
|
Routing - MECHANICAL | 8/27/2014 | | 8/27/2014 | | PASS |
Troy James
|
|
|
The pizza oven will be electric.
|
Routing - PLAN CHECK | 8/25/2014 | | 8/27/2014 | | PASS |
Carl Westfall
|
|
|
Drawings approved with "red lines".
|
1st review completed | | | 8/27/2014 | | DONE |
|
|
|
|
Routing Off Site - C.D.H | 8/14/2014 | | 8/26/2014 | | PASS |
Byron Grover
|
|
|
|
Routing PW Environmental | 8/14/2014 | | 8/25/2014 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLAN CHECK | 8/14/2014 | | 8/25/2014 | | FAIL |
Carl Westfall
|
|
|
Additional information required
|
Routing - FIRE | 8/14/2014 | | 8/21/2014 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - MECHANICAL | 8/14/2014 | | 8/19/2014 | | FAIL |
Troy James
|
|
|
gas piping design for the pizza oven
|
Routing - PLUMBING | 8/14/2014 | | 8/18/2014 | | PASS |
Bill VanDegrift
|
|
|
additional cross connection protection may be required
|
Routing - Design Review | 8/14/2014 | | 8/18/2014 | | PASS |
Josh Wilson
|
|
|
Josh Wilson - CZC14-00237
|
Routing - Erosion and Sediment | 8/14/2014 | | 8/15/2014 | | FAIL |
Evan Jenkins
|
|
|
Some sawcutting of parking lot
Due to Sawcutting, ESC Permit and ESC Plan w/ Narrative or ESC Waiver Letter Required
|
Pending Assignment by JCB | 8/14/2014 | | 8/14/2014 | | DONE |
Jason Blais
|
|
|
|
Routing PW Sewer Rating | 8/14/2014 | | 8/14/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 8/14/2014 | | 8/14/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/14/2014 | | 8/14/2014 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 8/13/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Tim Woodard. Plan Review Fees paid.
|
Application received | | | 8/7/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 7 2014 1:37PM
|