Third Notice | | 5/9/2015 | 6/9/2015 | | DONE |
|
|
|
|
Second Notice | | 3/13/2015 | 5/4/2015 | | DONE |
|
|
|
|
First Notice | 2/9/2015 | 2/9/2015 | 3/3/2015 | | DONE |
Mike Jordan
|
|
|
MAILED 3-3-15
|
Letter of compliance/Occupancy | | | 2/11/2015 | | DONE |
|
|
|
|
BLD-Final | 2/9/2015 | 2/9/2015 | 2/9/2015 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 2/9/2015 | 2/9/2015 | 2/9/2015 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 2/9/2015 | 2/10/2015 | 2/9/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Conference | 2/4/2015 | 2/5/2015 | 2/5/2015 | A | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Thornton
|
FIRE-Final Inspection | 2/4/2015 | 2/4/2015 | 2/4/2015 | P | FAIL |
Troy Cobbley
|
|
|
Need "FIre Door - Do Not Block" signs at the fire door and the project related fire alarm permit finaled before I can pass the life safety.
|
BLD-Wall cover | 1/9/2015 | 1/9/2015 | 1/10/2015 | P | PASS |
Dave Hannah
|
|
|
Inspect the progress of the West building. Phone #: ###-#### Inspection requested via web by Bob Thornton columns
|
BLD-Wall cover | 12/26/2014 | 12/29/2014 | 12/29/2014 | A | PASS |
Mike Jordan
|
|
|
Progress inspection of the East building electrical room ceiling. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Conference | 12/26/2014 | 12/26/2014 | 12/26/2014 | P | CANC |
Mike Jordan
|
|
|
Inspect the progress of the rated ceiling in the East building electrical room. Phone #: ###-#### >> Inspection requested via web by Bob Thornton Inspection cancelled from web by: Bob Thornton
|
BLD-Wall cover | 12/15/2014 | 12/15/2014 | 12/15/2014 | A | PASS |
Mike Jordan
|
|
|
Progress inspection of the rated ceiling on the West building Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Wall cover | 12/12/2014 | 12/12/2014 | 12/12/2014 | P | PASS |
Mike Jordan
|
|
|
Progress inspection of the rated ceiling. Phone #: ###-#### Inspection requested via web by Bob Thornton. Work in progress, completed work to this point ok.
|
BLD-Wall cover | 11/12/2014 | 11/13/2014 | 11/13/2014 | A | PART |
Mike Jordan
|
|
|
Please perform a progress inspection of the rated warehouse ceiling. Phone #: ###-#### Inspection requested via web by Bob Thornton. work in progress ok on rated ceiling and column wrap.
|
BLD-Conference | 11/7/2014 | 11/7/2014 | 11/7/2014 | P | PART |
Mike Jordan
|
|
|
Do a progress inspection of the rated warehouse ceiling. Phone #: ###-#### Inspection requested via web by Bob Thornton. Work in progress ok.
|
BLD-Conference | 11/4/2014 | 11/5/2014 | 11/5/2014 | A | PART |
Mike Jordan
|
|
|
Perform progress inspection of 3 hour walls. Perform progress inspection of the 1 hour ceiling. Phone #: ###-#### Inspection requested via web by Bob Thornton. Work in progress, ok.
|
BLD-Wall cover | 11/4/2014 | 11/4/2014 | 11/4/2014 | P | PASS |
Mike Jordan
|
|
|
Inspect the 1st layer on the 3 hour walls Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Wall cover | 10/31/2014 | 11/3/2014 | 11/3/2014 | A | PASS |
Mike Jordan
|
|
|
Inspect the interior 3 hour walls Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Wall cover | 10/14/2014 | 10/14/2014 | 10/14/2014 | P | PASS |
Mike Jordan
|
|
|
Inspect the last 3 hour window infill on the West building. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Framing/Rough-in | 10/9/2014 | 10/10/2014 | 10/10/2014 | A | PASS |
Mike Jordan
|
|
|
Look at the 3 hour exterior window infills. Phone #: ###-#### Inspection requested via web by Bob Thornton. 3hr. exterior window infills at prior loading dock location.
|
BLD-Conference | 10/2/2014 | 10/2/2014 | 10/2/2014 | A | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Thornton
|
OVERRIDE | | | 10/1/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/1/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/1/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/1/2014 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/22/2014 | 8/22/2014 | 9/30/2014 | | PASS |
Carl Westfall
|
|
|
PETERSON WAREHOUSE FIREWALL - Level 3 TI - ePlanReview - (15 days - Sept 11) (1st review done)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/30/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/23/2014 | | 9/30/2014 | | PASS |
Carl Westfall
|
|
|
Completed the 2nd review on 9-24-14. Waiting for Jason's decision about the alternate.
Completed the 3rd review on 9-30-14 after the code modification letter approved by Jason was uploaded.
|
Plan resubmittals received | | | 9/29/2014 | | DONE |
Carl Westfall
|
|
|
Code Modification approved by Jason was uploaded by Jason.
|
Plan resubmittals received | | | 9/23/2014 | | DONE |
Carl Westfall
|
|
|
Attic ventilation issue not resolved. Waiting for resolution.
|
1st review completed | | | 9/5/2014 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 9/5/2014 | | DONE |
|
|
|
Emailed a copy of the plan review report
|
Routing - PLAN CHECK | 8/22/2014 | | 9/4/2014 | | FAIL |
Carl Westfall
|
|
|
Completed the 1st IBC plan review. Revised drawings required.
|
Routing - FIRE | 8/22/2014 | 8/22/2014 | 9/2/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 09-02-14
|
Routing - Design Review | 8/22/2014 | | 9/2/2014 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - DRH14-00319
|
Routing - Erosion and Sediment | 8/22/2014 | | 8/25/2014 | | PASS |
Evan Jenkins
|
|
|
Waiver Request Approved: Separation of an existing buildings into 2 buildings, in an existing paved parking area. Very minor exterior work to be performed.
|
Intake Approval | | | 8/22/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin and plan review fees paid.
|
Pending Assignment by JCB | 8/22/2014 | | 8/22/2014 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 8/11/2014 | | FAIL |
|
|
|
This property is in a design review area. Please contact Sarah Schafer at ###-#### as there are changes being made to the exterior of this building. If you already havea zoning certificate for this work please upload it in the documents. Thank you
|
Application received | | | 8/8/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 8 2014 9:21AM
|