BLD-Final | 6/30/2016 | 7/1/2016 | 7/1/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
DOC - Permit Finaled | 7/1/2016 | 7/1/2016 | 7/1/2016 | P | PASS |
Dave Hannah
|
|
|
|
Zoning Approval | 6/30/2016 | 6/30/2016 | 6/30/2016 | | PASS |
Ted Vanegas
|
|
|
|
BLD-Final | 6/28/2016 | 6/29/2016 | 6/29/2016 | A | PEND |
Dave Hannah
|
|
|
John// please call before Phone #: ###-#### ok after zoning finals
|
BLD-Energy code compliance | 3/24/2016 | 3/24/2016 | 3/24/2016 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 3/23/2016 | 3/24/2016 | 3/24/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
OVERRIDE | | | 3/23/2016 | | |
|
|
|
|
Routing Walk-In (BLD) | 3/23/2016 | 3/23/2016 | 3/23/2016 | A | DONE |
Kristal Soland
|
|
|
|
Routing Walk-In (BLD) | 3/23/2016 | 3/23/2016 | 3/23/2016 | P | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 3/23/2016 | | 3/23/2016 | | PASS |
Brian McGowan
|
|
|
Plan Modification; Brought in Engineering for interior stairway.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/23/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/23/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/23/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/23/2016 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 3/23/2016 | | DONE |
|
|
|
engineering for stair modification
|
Routing Walk-In (BLD) | 3/16/2016 | 3/16/2016 | 3/16/2016 | P | FAIL |
Tisha Gallop
|
|
|
mod to add fixed stairway to access bonus room trusses.
need engineer to approve extra load on engineered pan deck floor.
|
Plan Modification Accepted | | | 3/16/2016 | | DONE |
|
|
|
received modifications for stairs leading to attic access
|
BLD-Framing/Rough-in | 3/11/2016 | 3/14/2016 | 3/15/2016 | P | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### ok to insulate but needs to resubmit plans showing stairs and bouns room above garage
|
BLD-Wall Bracing | 1/5/2016 | 1/6/2016 | 1/6/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Foundation | 12/11/2015 | 12/11/2015 | 12/11/2015 | P | PASS |
Dave Hannah
|
|
|
JOHN Phone #: ###-####
|
BLD-Foundation | 11/2/2015 | 11/2/2015 | 11/2/2015 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Wall Bracing | 10/30/2015 | 11/2/2015 | 11/2/2015 | A | CANC |
Dave Hannah
|
|
|
Haviro Phone #: ###-####
|
BLD-Footing | 10/22/2015 | 10/22/2015 | 10/22/2015 | P | PASS |
Dave Hannah
|
|
|
Alavro Phone #: ###-####
|
Fees Due Hold | 10/9/2015 | | 10/22/2015 | | DONE |
Brittany Hill
|
|
|
|
Routing Walk-In (BLD) | 10/15/2015 | 10/15/2015 | 10/15/2015 | P | DONE |
Brian McGowan
|
|
|
|
1st review completed | | | 10/15/2015 | | DONE |
Brian McGowan
|
|
|
Brought in engineering for change of foundation wall width to existing issued permit.
|
Routing - PLAN CHECK | 10/15/2015 | | 10/15/2015 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2015 | | DONE |
Brian McGowan
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/15/2015 | | DONE |
|
|
|
no fees due
|
(F) Reprint permit | | | 10/15/2015 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/9/2015 | | DONE |
|
|
|
|
Telephone call | | | 10/8/2015 | | DONE |
|
|
|
advised owner of requirments to transfer permit to new contractor. An admin fee of $46.31 and new RP is required.
|
Extend Permit 90/180 days | | 9/25/2015 | 9/25/2015 | | DONE |
Jason Blais
|
|
|
Permit extended 180 days. This is first extension request for an issued permit.
|
BLD - Request for Extension | 9/22/2015 | 9/23/2015 | 9/23/2015 | A | DONE |
Mike Jordan
|
|
|
Will be submitting a plan mod soon - Teri Phone #: ###-####. Left message with terry noting to send buiilding official a letter for extension and to explain why it is needed and when the work will begin. Also left my phone number for call back and any other questions contractor may have.
|
CHANGE STATUS TO (ISS) | | | 1/22/2015 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 1/15/2015 | 1/15/2015 | 1/16/2015 | P | PASS |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 1/16/2015 | | DONE |
|
|
|
|
Telephone call | | | 1/16/2015 | | DONE |
|
|
|
per phone call with Terri at Artisan Builders, additional value for basement is $40k
|
Case Summary (BLD) | | | 1/16/2015 | | DONE |
|
|
|
|
Telephone call | | | 1/16/2015 | | DONE |
Candy A. Nichols
|
|
|
called Terry to let know plan mod permit is ready and how much is owed
|
Routing Walk-In (Zoning) | 1/15/2015 | 1/15/2015 | 1/15/2015 | P | PASS |
Colleen T Carroll
|
|
|
|
OVERRIDE | | | 9/25/2014 | | |
|
|
|
|
Routing Walk-In (Zoning) | 9/25/2014 | 9/25/2014 | 9/25/2014 | A | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 9/25/2014 | 9/25/2014 | 9/25/2014 | A | DONE |
Perry Paine
|
|
|
|
Plan assigned to (PEP) | 9/25/2014 | 9/25/2014 | 9/25/2014 | | PASS |
Perry Paine
|
|
|
|
Inspection Record Card- Bld | | | 9/25/2014 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/25/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/25/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 9/25/2014 | | DONE |
Christina Prado
|
|
|
|
Routing Walk-In (Zoning) | 8/8/2014 | 8/8/2014 | 8/8/2014 | A | FAIL |
Matthew A Halitsky
|
|
|
Zoning Certificate required for accessory structure over 1000 sf.
|
1st review completed | | | 8/8/2014 | | FAIL |
|
|
|
|
Application received | | 8/8/2014 | | | |
|
|
|
|