Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD14-02322
StatusFinaled
Name JAYO CONSTRUCTION
Site Address 3332 S CADET AVE
Project NameTownhouse
Customer NumberBLD14-02323
ePlanReviewNo
Description
Permit for the construction of a new 1430 sq. ft., one story Townhouse with 2 bedrooms, 2 bathrooms, approximately 75 sq. ft. of covered patio/porch and a 421 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1C zoning and setbacks per planning.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection8/30/20168/30/20168/30/2016 DONE
DetailsJim Storey
DOC - Permit Finaled8/30/20168/30/20168/30/2016PPASS
DetailsJim Storey
BLD-Final4/15/20164/18/20164/18/2016APASS
DetailsJim Storey
Remember garage code - Cameron Phone #: ###-####
BLD-Energy code compliance1/25/20161/25/20161/25/2016PPASS
DetailsPhil Shearer
Camern Phone #: ###-####
BLD-Framing/Rough-in1/20/20161/21/20161/21/2016APASS
DetailsJim Storey
Cameron Phone #: ###-####
BLD-Other1/11/20161/12/20161/12/2016PPASS
DetailsJim Storey
soffit; Cameron Phone #: ###-####
BLD-Wall cover12/30/201512/30/201512/30/2015PPART
DetailsJim Storey
fire // cameron Phone #: ###-#### need fire wall out to out
BLD-Wall Bracing12/17/201512/18/201512/18/2015AFAIL
DetailsJim Storey
Cameron Phone #: ###-####
BLD-Wall Bracing12/17/201512/17/201512/17/2015PDEFR
DetailsJim Storey
Cameron Phone #: ###-####
BLD-Foundation12/16/201512/17/201512/17/2015PDEFR
DetailsJim Storey
firewall; Cameron Phone #: ###-####
BLD-Footing11/2/201511/2/201511/2/2015PPASS
DetailsJim Storey
Bill Phone #: ###-####
Issue PAID IN FULL permit  10/21/2015 DONE
OVERRIDE  10/1/2015  
Inspection Record Card- Bld  10/1/2015 DONE
Telephone call  10/1/2015 DONE
called Cameron to let know permit is ready and how much is owed-left message on his cell
Routing - PLAN CHECK10/1/2015 10/1/2015 PASS
DetailsJavier Guzman
Case Summary (BLD)  10/1/2015 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  10/1/2015 DONE
Permit Ready to Issue  10/1/2015 DONE
All Requirements Met
Plan assigned to (JG)8/13/2014 10/1/2015 PASS
DetailsJavier Guzman
1st review completed, 08/28 TH L2 Townhouse*
Plan resubmittals received  9/30/2015 DONE
received two copies of sheet A3-4- put with plans on Javier's desk
Routing - PLAN CHECK9/17/2015 9/17/2015 FAIL
DetailsJavier Guzman
need revised roof framing plan sheet
Plan resubmittals received  9/14/2015 DONE
resubmittals received 2 sets of sheets A2-1, A3.-1, A4-1-Took to JG
Routing - PLAN CHECK8/31/2015 9/2/2015 FAIL
DetailsJavier Guzman
emailed report to applicant
Routing - PUBLIC WORKS8/31/2015 8/31/2015 PASS
DetailsJennifer Bruner
Routing - Addressing8/31/2015 8/31/2015 PASS
DetailsEmily Dixon
Duplex 3328 & 3332 S Cadet Ave.
Routing - MECHANICAL8/25/2015 8/28/2015 PASS
DetailsTroy James
Routing - PLANNING8/25/2015 8/26/2015 PASS
DetailsSusan Riggs

The area between the two driveways must be landscaped.
The top row of the garage panels must be glass panels/window.
Extend Review Timeline  8/19/2015 DONE
DetailsJason Blais
Plan resubmittals received  8/18/2015 DONE
resubmittals taken to Javier
Extend Review Timeline  3/2/2015 DONE
DetailsJason Blais
Plan Reviewer's activity  2/25/2015 DONE
DetailsJavier Guzman
Sent 180 day letter to applicant on file 2/25/2015
Routing - PUBLIC WORKS8/15/2014 8/27/2014 PASS
DetailsJennifer Bruner
signed off in PW report by Jeniffer Bruner
1st review completed  8/27/2014 FAIL
DetailsJavier Guzman
Routing - PLAN CHECK8/26/2014 8/27/2014 FAIL
DetailsJavier Guzman
Routing - MECHANICAL  8/26/2014 PASS
DetailsTroy James
Routing - Addressing8/13/2014 8/15/2014 PASS
DetailsJason C. Taylor
Duplex 3316 & 3328 S Cadet Ave.
Route to Impact Fee Review  8/14/2014 PASS
Plans ACCEPTED BY PLAN TECH  8/12/2014 DONE
DetailsCandy A. Nichols
Intake Approval  8/12/2014 PASS
DetailsCandy A. Nichols
Recd Pcfee & Taken To Pln CK  8/12/2014 DONE
DetailsCandy A. Nichols
Application received 8/12/2014   
Routing - PLAN CHECK8/27/2014    
DetailsJavier Guzman
Routing - PLAN CHECK8/28/2015    
DetailsJavier Guzman
Routing - PLANNING8/15/2014   FAIL
DetailsSusan Riggs
Fail plans as they do not meet the Duples Design Standards. I spoke to Doug Jayo today and went over the ordinance requirements. He will need to submit a new design or request a variance. Additionally, the CUP must be modified. This can be done administratively.